CONTRACf CHANGE ORDER.
Change Order No. . 3
Engineer Project No. #98-OJ 4
Project Title: City Hall Sign
Contractor: Al Bosgraaf & Sons
Reason for Change _ Add stucco to sign base
Breakdown of Proposed Changes and Basis for Payment
(Includes pertinent drawings, specifications, and documentation where necessary)
Item No.. and Description Change in Contract
Coat +(..)
Labor 175.00
5 bags marblecrete 62.60
10% Profit & Overhead 23.76
(1) Total Proposed Change in Contract +( -) $ 261.36
(2) Original Contract Price $ 14 , 1 20 . 00
(3) Total All Previous Change Ordem $ 668.89
(4) New Contract Pricc(Total ofItcm 1,2 & 3) '$ 15,050.25
Recommended By Engineer: Date b / t/ 1 t
Accepted. By Contractor. Date 6/5/98