HomeMy WebLinkAboutBruce McGonigal, Inc. Change Order No. Two -1998 03 13
c..l~;-,A.
CONTRACT CHANGE ORDER
Change Order No.
Two
Engineer Project No.
#96-024
Project Title: Green&point Reclaimed Water Main Extension Drainage Improvements
Contractor: Bruce McGoniaal, Inc.
Reason for Change To bore and jack pipe under highwl\Y 434 to median for reclaimed water
irrigation system
Breakdown of Proposed Changes and Basis for Payment
(Includes pertinent drawings, specifications, and documentation where necessary)
Item No. and Description Change in Contract
Cost +(-)
1 Jack & Bore 10 inch steel casing & insert 4 Inch ductile iron $4,670.00
pipe inside of casing.
(1) Total Proposed Change in Contract +(-) $
(2) Original Contract Price $
(3) Total All Previous Change Orders(Change Order NO.1 thru..2....) $
4,670.00
159,400.92
5,204.50
(4) New Contract Price(Total ofItem 1,2 & 3)
$
169.275.42
Accepted By Contractor: Date
Accepted By Owner: ,;t ~ M ?tfI~ ~ Date
sIn /" r
/' ,
3//r'8
/
Recommended By Engineer: Date