CONTRACT CHANGE ORDER
Change Order No. 3
Engineer Project NO. #97-017
Project Title: Hayes Road, Moss Road, and Panama Road Paving and Drainage Improveme~
Contractor: Bergeron Land Development, Inc.
Reason for Change Add Bahama Road Paving
Breakdown of Proposed Changes and Basis for Payment
(Includes pertinent drawings, specifications, and documentation where necessary)
Item No. and Description
Change in Contract
Cost +(-)
1. Add 350' of Bahama Road west of Moss Road - includes
regrading, stabilizing 12" sub base, ribbon curb, 8" limerock, and
1.5" asphalt paving.
$21,126.35
Approved as Consent Agenda "D" on 12/8/97
(1) Totai Proposed Change in Contract +(-) $__~..21,126.35
(2) Original Contract Price $ 449,000.00
(3) Total All Previous Change Orders(Change Order No.1 thru 2) $ 10,083.23
(4) New Contract Price(Total ofItem 1,2 & 3)
$ 480,209.58
Accepted By Contractor:
Accepted By Owner:
Recommended By Engineer:
Date:12/22/97
Date Jan 5 1998
Date