HomeMy WebLinkAboutBergeron Land Development, Inc. Change Order 2 -1997 10 29
CONTRACT CHANGE ORDER
Change Order No. 2
Engineer Project No. #97-017
Project Title: Hayes Road, Moss Road, and Panama Road Paving and Drainage Improvements
Contractor: Bergeron Land Development, Inc.
Reason for Change New Houses have heen huilt requiring driveway culverts
Breakdown of Proposed Changes and Basis for Payment
(Includes pertinent drawings, specifications, and documentation where necessary)
Item No. and Description Change in Contract
Cost +(-)
1. Hayes Road - Sta. 4+33 to 4+73 RT - Remove/Reinstall $758.30
culvert to accommodate driveway at 300 Hayes Road.
2. Hayes Road - Sta. 9+50 RT - F & I 40 LF CulvertlMES $1,661.32
3. Moss Road - Sta. 29+50 RT - F & I 40 LF culvertlMES $1,661.31
15%O.H.&P $612.14
(1) Total Proposed Change in Contract +(-) $
(2) Original Contract Price $
(3) Total All Previous Change Orders(Change Order No.1 thru-D $
4,693 07
449,000.00
5,390.16
(4) New Contract Price(Total ofItem 1,2 & 3)
$
463,776.30
Recommended By Engineer
Accepted By Contractor
Date 10/28/97
Date10/29/97
Accepted By Owner:
Date 11/2/97