CITY OF WINTER SPRINGS
WINTER SPRINGS TOWN CENTER -HICKORY GROVE PARK ROAD & TUSKAWILLA
Contract Chance Order
No.: 15
Date: 3/13/03
k1 `~~~~ ~~ti'vxii{ti'~~}•. j.:~. \ivt.}}~iittiM1tM1ii~~M~ii~'i'~~.i,R.~ ~~. ~~~}, v,'~i'v~i M14vvv M1 4
.\
Project Title: Hickory Grove Park Road
Contractor: Esterson Construction Company, Inc.
Reason for Change: EXTRA WORK
Item No. and Descri tion Unit Quanti Unit Price Item Value Total
1. Demolition and disposal of LS $4,187.08 $4,187.08
12" asphalt South Tusk. Rd.
2. Seed and mulch: Easement between LS $1,454.00 $1,454.00
Temp School Rd. and City Hall,
East End of Hickory Grove
Median, North Tusk. Rd. at
outrall structures.
3. 45' of 5' Sidewalk LF 45 $3.25 $146.25 $146.25
Change Order Value: $ 5,787.33
Original Contract Price: $ 1,883,215.00
Total Value Previous Change Orders: $ 299,470.52
New Contract Price: $ 2,188,472.85
Original Contract Duration 270 days
Original Contract Completion pate 2-Nov-02
Approved Time Extensions 132 da s
Current Contract Duration 402 da s
Proposed Time Extension 0 da s
New Contract Duration 402 da s
New Contract Completion Date 14-Mar-03
Accepted By Contractor: Date: ~ ~ ~ 43
Cap. Prj. Coordinator: Date: ~ b3
Dir. Pb Wks/Utilities: Date: ~/ ,? a ~
Accepted By Owner: _ ~ ' ~ Date: y J 3 - ~ 3