HomeMy WebLinkAboutEsterson Construction Change Order 2 Orange Avenue Drainage and Roadway Improve -1998 01 12CONTRACT CHANGE ORDER
Change Order No. 2
Engineer Project No. #97-002
Project Title: Orange Avenue Drainage and Roadway Improvements
Contractor: Esterson Construction Inc.
Reason for Change Pavement of Park Entrance for Orange Avenue asper request from Parks
Department
Breakdown of Proposed Changes and Basis for Pavment
(Includes pertinent drawings, specifications, and documentation where necessary)
Item No. and Description Change in Contract
Cost + -
Paved entrance including 3.5" friction coarse and 8" Soil Cement $2,607.00
Base. 246syd @ $10.60/syd
Total Change Order: $2,607.00
(1) Total Proposed Change in Contract +(-) $ $ 2,607.00
(2) Original Contract Price $ $184,375.00
(3)Total All Previous Change Orders(Change Order No.l thru 2) $ $185,840.00
(4) New Contract Price(Total of Item 1,2 & 3) $ $188,447.00
Recommended By E
Accepted By Contra
ctor: Date ~ Z ! ~-- lr`~
Accepted By Owner: Date / ~ J „r l 9 $'
ngineer:~ $w ~~ ~ Date o~ ~ a q~qB