Loading...
HomeMy WebLinkAboutEsterson Construction Change Order 1 Orange Avenue Drainage and Roadway Improve -1997 07 16CONTRACT CHANGE ORDER Change Order No. 1 Engineer Project No. 97-002 Project Title: Orange Avenue Drainage and Roadway Improvements Contractor: Esterson Construction Reason for Change Change in location of 2 Storm Structures requiring additional pipe and labor. Labor includes all grading and/or tree removal required for the placement of the structure(sl Breakdown of Proposed Changes and Basis for Payment (Includes pertinent drawings, specifications, and documentation where necessary) Item No. and Description Change in Contract Cost +(-) I. Install the following: A. 36x15 Tee $470.00 B. 36" bands (2) 15" band $180.00 C. 20 LF 36" GDPE(Labor Only) $320.00 D. 40 LF 15" HDPE(Labor Only) $495.00 *Item D is intended to accommodate for existing drainage patterns and will be field located. (1) Total Proposed Change in Contract +(-) (2) Original Contract Price (3) Total All Previous Change Orders(Change Order No. l thru 1 ) (4) New Contract Price(Total of Ite,~n 1 & Item 4) Recommended By Engineer: ~.~~ ~, Accepted By Owner: $ 1,465.00 $184,375.00 $ 0.00 $185, 840.00 Date o7~ 6~~'i 7 Date .~ 7~! 6`17 rw~