HomeMy WebLinkAboutEncore Construction Company Change Order 1 -1998 06 11
Engineer Project No. W0449.02
Project Title: City of Winter Smogs Reclaimed Water Improvements -Contract B
Contractor: Encore Construction Company
Reason for Change: See Itemized Description Below
Breakdown of Proposed Changes and Basis for Payment
(Includes pertinent drawings, specifications, and documentation where necessary)
Item No. and Description Change in Contract
Cost +(-)
1. Increase in Building Permit fee over bid allowance. $642.00
2. Additiona124" DIP & MJ CAP for future pumps at the $1,574.00
Distribution Pump Station.
3. Increase size of electricaUstorage building to 20' x 20'. $2,058.00
4. Furnish new breaker, starter, wire, etc. for the existing air $1,607.00
compressor.
5. Change the disconnect switch for the 5 HP motor at the chlorine $1,659.00
building.
6. Install a new control panel for the master lift station, including $16,949.00
new bubbler system controls, a generator receptacle, breaker and
tenminal box.
7. Overlay approx. 1700 LF of existing service road w/6" of $39,831.00
limerock base and 1%" Type S-1 asphalt. Cost includes deduct.
for clay stabilized areas.
., .,. ,
Cl~~k
CONTRACT CHANGE ORDER
S..i~`j~d0`1
Change Order No. 1
(1) Total Proposed Change in Contract Cost +(-)
(2) Original Contract Price
(3) Total All Previous Change Orders
(4) New Contract Price (Total of Items 1, 2 and 3)
(5) Original Contract Time
(6) Additional Days Approved (Change Order No. =
(7) Current Contract Time
(8) Additional Days Proposed
(9) New Contract Time (Total of Items 7 and 8)
(10) New Construction Completion Date
through No. _)
$ 64,320.00
$ 1.065,400.00
$ 0.00
$ 1.129.720.00
240 Davs
0 Davs
240 Davs
10 Days
250 Days
September 28. 1998
Recommended By Engineer: .. - A Date: /
Accepted By Contractor: ~ Date: _~~~ / `~_
~+co~a GervS+t . i~~~/'
Accepted By Owner: Date: ~ /,5'
W044902.CHA/wpo