SECTION 00950
CHANGE ORDER FORM
Landscape Architect
Winter Spring Streetscapes
CPH Project No. W041 08
14 July 2003
GCI/General Constructors, Inc.
CPH Engineers, Inc.
Change Order No:
8
Project Title:
Engineer Job No.
Agreement Date:
Contractor:
This Change Order is necessary to cover changes in the work to be performed under this
Agreement. The GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS, and
STANDARD SPECIFICATIONS apply to and govern all work under this Chance Order.
Reason for Change:
Owner Requested/ Final Balancing of Quantities
THE FOLLOWING CHANGES ARE MADE TO THE CONTRACT DOCUMENTS:
1. Original Contract Price
2. Current Contract Price (Adjusted By Previous Change Orders 1-7)
3. Total Proposed Change in Contract Price
4. New Contract Price (Item 2 plus Item 3)
5. Original Construction Completion Date
6. Original Contract Time
7. Current Contract Time (Adjusted By Previous Change Orders)
8. Total Proposed Change in Contract Time
9. New Contract Time (Item 6 plus Item 7)
10. New Construction Completion Date
$781,795.37
$851,071.99
$2,740.56
$853,812.55
28 December 2003
240 Days
54 Days
72 Days
366 Days
4 May 2004
00950-1
SPECLIB082499
Item Change in Change in
No. Description Contract Contract
Price Time
1. Concrete Pavers $3553.88 0
2. Brick Pavers $(5639.53) 0
3. Concrete Banding 778.05 0
4. Sweet Viburnum $(17.78) 0
5. Bahia Sod $672.00 0
6. Live Oak $(2517.50) 0
7. 4#3/0-2" $1233.60 0
8. Raising 6" C/O & Brass Cap $(4468.38) 0
9. Edge Form Concrete for Sidewalk Pavers $(1556.40) 0
10. Mortar Set Pavers $(277.20) 0
11. 6" Spray Pop-Up $(446.12) 0
12. 12" Spray Pop-Up with Bubbler $(250.24 ) 0
13. Indian Hawthorne $(89.90) 0
14. Handicap Sign Concrete Post $1468.08 0
15. Firepower Nandia $(179.80) 0
16. Concrete Sidewalk $10478.00 0
17. Total $2740.56 0
00950-2
SPECLIBOB2499
, f "
.
WAIVER This Change Order constitutes full and mutual accord and satisfaction for the
adjustment of the Contract Price and Contract Time as a result of increases or decreases in
cost and time of performance caused directly and indirectly from the change. Acceptance of
this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change
Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall
waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution
of this Change Order shall constitute CONTRACTOR's complete acceptance and satisfaction
that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change
Order.
APPROVAL AND CHANGE ORDER AUTHORIZATION
ACKNOWLEDGMENTS
The aforementioned change, and work affected thereby, is subject to all provisions of the
original Agreement and specifically changed by this Change Order; and it is expressly
understood and agreed that the approval of the Change Order shall have no effect on the
original Agreement other than matters expressly provided herein.
Recommended By:
Engineer
Directo:~tief:!:K,lic
Date
t / t /0 '1
D/~.
Date
A..T.~
,~
(S reta )
~ t/b/tJ'f
Date I
(Corporate Seal)
ATTEST:
Owner
~W~p
By onald W. McLemore,
City Manager
ct- (, -- oC+
If! Uf
By
r-/ t If) 17
Date
Date
END OF SECTION