CONTRACT CHANGE ORDER
Change Order No.
1
Engineer Project No.
#98-015
Project Title: Old Sanford-Oviedo Road Water Main Imorovements
Contractor: Master Site Develooment. Inc.
Reason for Change Additional Fittinqs and Site Condition Chanqes
Breakdown of Prooosed Chanqes and Basis for Pavment
(Includes pertinent drawings, specifications, and documentation where
necessary)
I
Item No. and Description
Change in Contract
Cost +(-)
1. 2 - 8" 45 Bend $900.00
2. 8" 11 " Bend ($350.00)
3. Remove concrete drive - 235 OSO Road $1,050.00
4. Open Cut Driveway - 280 OSO Road $1,625.00
5. Overhead and Profit $483.75
(1) Total Proposed Change in Contract +(-)
(2) Original Contract Price
(3) Total Previous Change Orders (No.
$
$
$
3.708.75
79.105.00
(4) New Contract Price{Total of Item 1,2 & 3)
$
82,813.75
Recommended By Engineer:
Date ?/J~/tf f
, ,
Date 'r"/1.. f~
Date~ -' }1/ t~
Accepted By Contractor:
Accepted By Owner: