HomeMy WebLinkAboutMacAsphalt Contract Change Order No. 2 -1996 09 30
( Itt')L
..) . ,....
CONTRACT CHANGE ORDER
Change Order No. 2
Engineer Project No. 96-016
Project Title: Street Resurfacing
Contractor: MacA$.phalt
Reason for Change Finali7.ation ofE!rt:lmated Quantities
Breakdown of Proposed Changes and Basis for Payment
(Includes pertinent drawings, specifications, and documentation where necessary)
Item No. and Description Change in Contract
Cost +(-)
SEE ATTACHED SHEET FOR DESCRIPTION OF CHANGE
(1) Total Proposed Change in Contract +(-)
$ 10.173.86
(2) Original Contract Price
$ 229.627.37
(3) Total All Previous Change Orders(Change Order No.1 )
$ 7,922.72
Accepted By Contractor:
$ 247.723.95
Date <i' J ~o / C; ~
.
Recommended By Department Head:
Accepted By Owner: If ~~ 4U-H
(7
Date qj rO If {
/ I
Date 7/1r7~
-,~''''A!\,'I\5.f'''~''~,','''''C--'-'''
-~"}~'~~
"~'jP"'~i"'Y:7,j;'!".~::""
..
.... ". ~ .......",
Change Order #2
Purchase Order 39179
ItemNo. - 1 Winter Springs Blvd - C.O. #1
Estimated 1352.0 sq yds
Actual 1627.5 sq yds
Difference
275.5 sq yds at $5.86 per sq yd
$1614.43
Item No. - 2 Eagle Nest Circle
Estimated 1793 sq yds
Actual 2262 sq yds
Difference
469 sq yds at $17.47 sq yd
$8193.43
Item No. - 3 Manhole Rings
Estimated 116 rings
Actual 120 rings
Difference
4 at $94.00 each
$ 376.00
Item No. - 4 Blue Reflectors
Estimated 51
Actual 50
Difference
1 at $10.00
($10.00)
Total
$10,173.86