HomeMy WebLinkAboutM.H. Williams Construction Contract Change Order No. 2 -2000 06 12CONTRACT CHANGE ORDER
Project Title: CITY OF WINTER SPRINGS Parks Improvement Project
Contractor: M. H. Williams Construction Co.
Reason for chan! Approved Facillities Commission Approval 12 Jun 00
N0. 02
12- Jun -00
Ttw FcUowi Modifications to the PM 66( are Hereby Ordered
Item No. and Description
1
Substitute soccer goals
deduct $ 5,815.00
2
Allowance adjustment for fishing piers
deduct $ 1,643.00
3
Omit secondary kiosk at Central Winds Park
deduct $ 10,000.00
4
Omit septic tank and drainfield at Central Winds Park concession stand
deduct $ (5,250.00)
5
Overlay paving at entry to Sam smith Park
add $ 1,375.50
6
Stiping of parking lots at Trotwood, Sam Smith, and Moss Parks
add $ 1,617.00
7
Change to more native plant material at various parks
add $ 483.00
8
Add duplex outlets to large pavilions at Trotwood, Sam Smith, and Sunshine
add $ 1,930.00
9
Add (8) new doors to Civic and Seniors Center buildings at Sunshine Park
add $ 6,635.47
10
De -muck soils at Sunshine Park pavilion slabs
add $ 8,224.00
11
Provide smaller sink at Central Winds Park concession stand
add $ 1,034.00
12
De -muck soils at Torcaso Park pavilion and bathroom slabs
add $ 8,500.00
Change Order Value:
$ 7,090.97
Original Contract Price:
$ 2,260,689.00
Total Value Previous Change Orders:
c.o. no. 1) $ 36,443.21
New Contract Price:
$ 2,304,223.18
Original Contract Duration
300 days
Original Contract Completion Date
10 -Se -00
Approved Time Extentions
none
Current Contract Duration
300da s
Proposed Time Extention
30 days
New Contract Duration
330 days
New Contract Completion Date
10 -Oct -00
Accepted by Contractor:
Date if ZZ, C6
Coordinator: / 'ice
Date
Capital Projects
Parks & Recreation Director:
Date
City Manager:
Date
MEMORANDUM
TO: Andrea Lorenzo - Luaces, City Clerk
FROM: George Edwards, Capital Projects
City of Winter Sarin_as Bid # ITS- 012 -99TL
DATE: August 2, 2000
Transmitted herewith are the following executed documents for your files:
1) Change Order #1
2) Change Order #2