CONTRACT CHANGE ORDER
Change Order No.
Engineer Project No. W0464.01
Project Title: Hayes Road Bridge Replacement
Contractor: Prime Construction Group. Inc.
Reason for Change: Field required changes and additional work requested by Owner.
Breakdown of Proposed Changes and Basis for Payment
(Includes pertinent drawings, specifications, and documentation where necessary)
V~
Item No. and Description Change in Contract
Cost + (-)
Additions and deletions as outlined in the attached letter. $ 9,358.03
(1) Total Proposed Change in Contract Cost +(-)
(2) Original Contract Price
(3) Total All Previous Change Orders
(4) New Contract Price (Total of Item 1 & Item 4)
$ 9.358.03
$ 348.800.00
$ 0.00
$ 358.158.03
Recommended By Engineer: :~i'~• Date: ~/ Z~! ~,
Accepted By Contractor: f Date: 3'Z's
Accepted By Owner: ~~ ~ Date: ~ ) a a ~ J`~
W046401.cha - `
1
wPRIivIE CONSTRUCTION GROUP, INC.
5528 Force Four Parkway
Post Office Box 590507
Orlando, FL 32809-0507
March 20, 1997
Conklin, Porter & Holmes Engineers, Inc.
1104 East Robinson Street
Orlando, FL 32801
Attn: Terry Zaudtke, P. E.
Re: Hayes Road Bridge Replacement
Change Order #1
Dear Mr. Zaudtke:
Telephone (407) 856-8180
Fax (407) 856-8182
The following is a Change Order proposal for your review and approval:
The deleted items:
15" Headwall ($ 620.00)
24" Headwall ($ 830.00)
6' Chain Link Fence (+/- 30") ($ 648.00)
60' Storm Pipe ($ 750.00)
14' Sidewalk ($ 100.80)
P-4 Inlets -Quantity of 2 (1760.00
Subtotal deleted amounts ($4708.80)
Proposed items:
Installation of 6' Aluminum Handrail $ 243.96
64' Curb Removal & Reinstall $ 720.80
Raised Trash Structure (top to meet curb) $ 480.00
Raised "C" Inlet $ 260.00
Install 6' x 21' Headwall $2100.00
Remove and haul off Railroad Ties $ 135.00
Realign & Extend Waterline $ 944.71
Modify Inlet Tops (Quantity of 2) $2240.00
Milled Asphalt (490 SY) $1166.00
Install 28+/- SY of Base at Additional Curb $ 620.00
Install approx. 173' of 4' Sidewalk $1245.60
Install 490 SY of Asphalt at 2" with 4' Transition 2620.00
Subtotal Proposed Amounts $12776.07
PCG Burden Amount 1290.76
Total $9358.03
Please call me at our office if you have any questions or need more information on this proposal at 407-856-8180.
Respectfully,
Thomas M. Perley
Project Manager