HomeMy WebLinkAboutSunshine Building and Development Change Order 1 - 4th Addition to WM Improvements -1997 09 19C/~r~
CONTRACT CHANGE ORDER
Change Order No. 1
Engineer Project No. W0452.02
Project Title: North Orlando Fourth Addition Water Main Improvements
Contractor: Sunshine Building and Development Corporation
Reason for Change: Owner Requested Additions
Breakdown of Proposed Changes and Basis for PaXment
(Includes pertinent drativings, specifications, and documentation where necessary)
Item No. and Description Change in Contract
Cost +(-)
1. Additonal underdrain at seven (7) locations at 15 LF each $1,477.35
105 LF @ $14.07/LF
2. Add one short shingle service $389,31
1 @ $389.31/EA
3. Add 132 days to the Contract to allow for construction completion, N/C
FDEP certification and final installation/connection of water meters. New
completion dates are:
October 1, 1997 -Substantial completion of water mains/Receipt
of As-Builts
November 1, 1997 -Receipt of FDEP clearance
December 1, 1997 -Final Completion
(1) Total Proposed Change in Contract Cost +(-)
(2) Original Contract Price
(3) Total All Previous Change Orders
$ 1.866.66
$ 462.030.95
$ 0
(4) New Contract Price (Total of Items 1, 2 and 3)
Recommended By Engineer:
Accepted By Contractor:
Accepted By Owner:
W045202.cha
$ 463.897.61
Date: / /~ ~<
Date: `' C~i
Date: ' /~ 6~`/ %