CONTRACT CHANGE ORDER
Change Order No. 1
Engineer Project No. W0402.08
Project Title: Winter Springs Restroom Facility -Bid No. 95-012
Contractor: _ The Watau a Company
Reason for Change: A change in groundwater conditions and request by Building
Department.
Breakdown of Proposed Changes and Basis for Payment
(Includes pertinent drawings, specifications, and documentation where necessary)
Item No. and Description Change in Contract
Cost + (-)
1. Furnish and install duplex pump system and elevated leach field per
the requirements of the Health Dept. $7,491.00
2. Add a changing table for the men's side of the restroom. $374.00
3. Add emergency lights. One in each section. $331.00
Additional time granted 30 days for this additional work. Completion date is
October l6, 1995.
(1) Total Proposed Change in Contract Cost +(-)
(2) Original Contract Price
(3) Total All Previous Change Orders
(4) New Contract Price (Total of Items 1, 2 & Item 3)
Recommended By Engineer:
Accepted By ~~`
Accepted By Owner:
1~cG~+r.Q,1•Y ~ON~iar~r
$ 8,196.00
$ 59.557.00
$ -0-
$ 67.753.00
Date: ~/~--5/ ~~~
Date: ~ ~
Date: ~ a~s
S z s
gyz~s
a
f
Detailed Documentation for Change Order No. 1
Item 1: Due to a change in the groundwater table at the site, the Health Dept. is
requiring an elevated drainfield which also requires a pump chamber and a
duplex pump system. The contractor will provide the following:
1) 750 gallon pump tank.
2) Two (2) pumps and alternator.
3) Electrical connection and installation.
4) Excavate and elevate drainfield.
5) Furnish and install 164 CY clean sand.
6) Furnish and install 130 CY fill for normal slope and cover.
7) Seed and mulch stabilization and 90 CY for 5 to 1 slope.
Item 2: During review for the building permit, the Building Department required the
installation of emergency lights. Contractor will furnish and install lights in
both sections.
Item 3: During review for the building permit, the Building Department required the
installation of a second baby, changing table in the men's washroom.
Contractor will furnish and install this second unit.
END OF SECTION