HomeMy WebLinkAbout1997 10 27 Consent Item C
COMMISSION AGENDA
ITEM C
REGULAR
CONSENT X
INFORMATIONAL
..Qctober 21, 1997
Meeting
MG~~ IDEPT ;JY
Authorization
REQUEST: Public Works Department Requesting Authorization to Execute Supplement
No.1 to Amendment 43 for Consulting Engineering Services with Conklin,
Porter & Holmes Engineers, Inc.
PURPOSE: The purpose of this Board item is to request authorization for the execution of
Supplement No.1 to Amendment 43 for Northern Way Bridge Repair Construction
Administration Services with Conklin, Porter & Holmes Engineers, Inc. at a cost of
$3,751.00.
CONSIDERATIONS:
This supplement is needed to provide construction administration services for the
repairs to the Northern Way bridge over Bear Creek. The City does not have the staff for
full construction administration nor the expertise for bridge structural repair reviews and this
service has been historically contracted out. The scope of work includes preconstruction and
progress meetings, shop drawing review, periodic inspections, pay request processing, and
record drawings.
The design ofthis project was previously authorized under Amendment 43 at a cost
of$13,OOO.OO. The project construction contract is recommended to be awarded to Seig &
Ambachtsheer, Inc. at a cost of $48,925.00. Construction is scheduled to begin around
November 15, 1997 with completion in 90 days.
October 27, 1997
Consent Agenda Item C
Page .2
FUNDING:
The cost for Supplement No.1 to Amendment 43 is $3,751.00. The source of funds
would be the consulting services line code (104-53180) ofthe Transportation Improvement
Fund. Funds would be expended in 90 days.
RECOMMENDATION:
It is recommended that authorization be given for the execution of Supplement No. 1 to
Amendment 43 for Northern Way Bridge Repair Construction Administration Services with
Conklin, Porter & Holmes Engineers, Inc. at a cost of$3,751.00 payable from the Transportation
Improvement Fund consulting engineering line code (104-53180).
IMPLEMENTATION SCHEDULE:
The scope of services will be completed within 90 days of approval.
ATTACHMENTS:
1. Supplement No. 1 to Amendment 43
COMMISSION ACTION:
FROM (PH Engineers
4076481036
10-17-97 09:45AM TO K. Lockcuff
3270942
u186 P.1/6
ATTACHMENT NO. 1
AMENDMENT NO. 43
SUPPLEMENT NO.1
CONSULTING ENGINEERING SERVICES
Constnlction Administration
Northern Way and Bear Creek Bridge Repairs
This Supplement is made and entered into this _ Day of 1997, by and
between the City of Winter Springs and Conklin, Porter and Holmes-Engineers, Inc.
WHEREAS, the CITY and ENGINEER have preyiou~ly entered into an Agreement for
the ENGINEER'S professional services (Amendment No. 43); and
WHEREAS, the CITY and ENGINEER shall refer to Amendment 43 herein, and desire
to have it incorporated by reference; and
WHEREAS, the CITY now wishes to authorize Construction Administration Services.
NOW THEREFORE.. in consideration of the mutual promises and covenants contained
herein and gi ve one to thc othcr, the sufficiency of which is hereby acknowledged. the parties
agree as follows:
I SCOPE Olf "VORK
The scope of work has been agreed to by the parties. and js attached hereto and
incorporated herein, by reference, as Exhibit 1. Mr. Terry M. Zaudlkc. P.E.,
Senior Vice President, has been designated as Project Manager for this project, by
the ENGINEER.
II fEE
The fee has been agreed to by the parties, and as attached hereto and incorporatcd
herein, by reference, as EXHIBIT n.
III TER1Vl
The term of this Supplement shalJ be for four (4) months from the date of final
ext::cution by (he City.
FROM CPH Engineers
4075481035
10-17-97 09:45AM TO K. Lockcuff
3270942
11185 P.2I6
IV l~NTIRE A.C~EEMENT
This Supplement supersedes all previous authorizations, agreements. or
representations, either verbal or written, heretofore in effect between the CITY and
the ENGINEER that may have concerned the matters covered herein, except that
this Supplement shall in no way supersede Of amend Amendment 43 or other
authorizations except as specifically provided herein. No additions, alterations, or
variations to the terms of this Supplement shall be valid, nor can the provisions of
this supplement be waived by either party, unless such additions. alterations, or
waivers are expressly set forth in writing in a document of imporl equal to
Amendment 43 or the Supplement, and duly executed.
IN WITNESS WHEREOF, the parties hereto have executed this Supplement No.] on the
day and year first written above.
CITY OF WINTER SPRINGS, fLORIDA
BY:__
DATE:
ATTEST:
CONKLIN. PORTER AND HOLMES
ENGINEERS, INC.
~~ "2/7 n _ ./..l::Y)
BY:.: :J~I'._.-~
-- 0 ·
DATE: /0 It?/? 7 ,."....______
.
ATTEST:
FROM (PH Engineers
4076481036
10-17-97 09:46AM TO K. Lockcuff
3270942
11186 P.3/6
EXHIBIT I
SUPPLEMENT NO.1 (Amend. 43)
SCOPE OF WORK
CONSTRUCTION ADMINISTRATION SERVICES
1) Retain the services of a soils subconsultant to observe installation of the key elements,
Their services are auached hereto.
2) Conduct a preconstmction conference and one (1) progress meeting.
3) Make three (3) site visits to determine construction progress and inspect the work. We
have estimated two (2) hours per visit,
4) Check and approve shop drawings, illustrations, calculations, etc., required as part of the
project for conformance with the contract documents.
5) Prepare routine Change Orders, if an)'.
6) Review Pay Reque~ls.
7) Participate in substantial completion inspection and generate a punch list.
8) Parlicipatc in the Final inspection.
9) Furnish the OWNER a set of reproducible record drawings for the consullction contract
based on observations and information provided by the Contractor.
10) Furnish copies of plans and specifications to the Contractor for use during the work.
FROM (PH Engineers
40754B1035
10-17-97 09:45AM TO K. Lockcuff
3270942
EXHIBIT II
SUPPLEMENT NO.1 (AM. 43)
COST ANALYSIS
Construction Administration Services
(Supplement No.1)
$ 3,751.00
Original Authorization
Am. 43 (Design. Permitting, Bidding) $10,500.00
Supplement No.1 Construction
Administration $ 3,751.00
Total Authorization $14,251.00
u1B5 P.4/5
FROM CPH Engineers
4076481036
10-17-97 09:46AM TO K. Lockcuff
3270942
11186 P.5/6
EXHIBIT II (cent) - MANPOWER ESTIMATE
Item of Work P E T/D S EXDenses
Retain and Coordinate Soils Consultant SelVices 1 0.5 $1,768
Construction Administration Services
Conduct preconstruction meeting and progress meeting 3 3 0.5
Field visits (Three Visits) 6
Shop Drawing review 2 2 0.5
Change Order Preparation 0.5 0.5
Review pay requests (two anticipated) 1
Substantial completion inspection and punch list 0.5 :2
Final inspection 0.5 2
Reproducibles 0,5 0.5 4 0.5
Plans and soecs for contractor ( three sets) $50
Total Hours 5.5 17 6 2.5 $1.818
FROM (PH Engineers
4076481036
10-17-97 09:47AM TO K. Lockcuff
3270942
11186 P.5/5
Nodarse
&. Associates, Inc.
ESTIMATED SCO~t OF SERVJC~S & BUDGETA~Y COST
CONSTRUCTION MATERIALS TEsTING & INsPECTION
REPAIRS @ NORTHERN WAY BRIDGE
WINTER SPRINGS, FLoRIDA
N&A PROPOSAL No. W97-C.238P
1, QFi~ T':. M'1'E" ',',',f',.:il1Nl'r:' 1.17.:~J:0b.NT' :, ,.
I..: '. ., ~""',,,:.rDoMON OFnn'VDV ..' " '.',
_.' ". of . ~~"~.' T"V~ .... . , J" ....
I. FIELD SERVICES
A. Observations of Tie-Back. Construction by Staff
. Engineer (Assume 6 Vi!It! @ ~ HourslVisit)
8 S 65.00 per hour $
520.00
II. LAHORATORY SERVICES
A. Mold, Transport, Cure & TeSt Concrete CyJ.i.IWrs for
Dead Man Construction
2 $ 65.09 each
130.00
m. PROFESSIONAL & CLERICAL SERVICES
A. Chief Engineer (Includes review elf ccntrattors design
calculations for a.nc.horage syslem.)
B. Project Maliager
C. Clerital
6 $ 100.00 per hour
6 $ 65.00 per hour
4 $ 32.00 per hour
600.00
390.00
128.00
1,768.00
,
ESTIMATED TOTAL.J
.'
7238P,DO. Rlvised 10/1(1/511
Geotechnlc.al. Environmental Geot~chnlc..s &. Mat~rial Engineers
10M North Orlando Avenue. Suite A. . Wintgr Pork, Florida 32789. T<Jlsphone .1D7.7~O.6110 . FocS\fT'IIlll 407.7dQ,Ol,12
e'moil IicdarJo@nodofse,com
Clf~k.
AMENDMENT NO. 43
SUPPLEMENT NO.1
CONSULTING ENGINEERING SERVICES
Construction Administration
N orthem Way and Bear Creek Bridge Repairs
This Supplement is made and entered into this _ Day of 1997, by and
, between the City of Winter Springs and Conklin, Porter and Holmes-Engineers, Inc.
WHEREAS, the CITY and ENGINEER have previously entered into 'an Agreement for
the ENGINEER'S professional services (Amendment No~ 43); and
WHEREAS, the CITY and ENGINEER shall refer to Amendment 43 herein, and desire
to have it incorporated by reference; and
WHEREAS, the CITY now wishes to authorize Construction Administration Services,
NOW THEREFORE, in consideration of the mutual promises and covenants contained
herein and give one to the other, the sufficiency of which is hereby acknowledged, the parties
agree as follows:
I SCOPE OF WORK
The scope of work has been agreed to by the parties, and is attached hereto and
incorporated herein, by reference, as Exhibit I. Mr. Terry M. Zaudtke, P.E"
Senior Vice President, has been designated as Project Manager for this project, by
the ENGINEER.
-
II FEE
The fee has been agreed to by the parties, and as attached hereto and incorporated
herein, by reference, as EXHIBIT II.
III TERM
The term of this Supplement shall be for four (4) months from the date of final
execution by the City.
IV ENTIRE AGREEMENT
This Supplement supersedes all previous authorizations, agreements, or
representations, either verbal or written, heretofore in effect between the CITY and
the ENGINEER that may have concerned the matters covered herein, except that
this Supplement shall in no way supersede or amend Amendment 43 or other
authorizations except as specifically provided herein. No additions, alterations, or
variations to the terms of this Supplement shall be valid, nor can the provisions of
this supplement be waived by either party, unless such additions; alterations, or
waivers are expressly set forth in writing in a document of import equal to
Amendment 43 or the Supplement, and duly executed.
IN WITNESS WHEREOF, the parties hereto have executed this Supplement No.1 on the
day and year first written above.
CITY OF W NTER SPRINGS, FLORIDA
BY: ~
DATE: /~ -d7- ?7
ATTEST:
~~'4~
CONKLIN, PORTER AND HOLMES
ENGINEERS, INC.
BY: .:k~J}~
DATE: /oJ/7/?7
.
ATTEST:
EXHIBIT I
SUPPLEMENT NO.1 (Amend. 43)
SCOPE OF WORK
CONSTRUCTION ADMINISTRATION SERVICES
1) Retain the services of a soils subconsultant to observe installation of the key elements.
Their services are attached hereto.
2) Conduct a preconstruction conference and one (1) progress meeting.
3) Make three (3) site visits to determjne construction progress and inspect the work. We
have estimated two (2) hours per visit.
.4) Check and approve shop drawings, illustrations, calculations, etc., required as part of the
project for conformance with the contract documents.
5) Prepare routine Change Orders, if any.
6) Review Pay Requests.
7) Participate in substantial completion inspection and generate a punch list.
8) Participate in the Final inspection.
9) Furnish the OWNER a set of reproducible record drawings for the construction contract
based on observations and information provided by the Contractor.
10) . Furnish copies of plans and specifications to the Contractor for use during the work.
EXHIBIT II
SUPPLEMENT NO.1 (AM. 43)
COST ANAL YSIS
Construction Administration Services $ 3,751.00
(Supplement No.1)
Original Authorization
Am. 43 (Design, Permitting, Bidding) $tO,500.00
Supplement No. 1 Construction
Administration $ 3,751.00
Total Authorization $14,251.00
EXHIBIT II (cont) - MANPOWER ESTIMATE
Item of Work P E TID S Expenses
Retain and Coordinate Soils Consultant Services 1 0,5 $1,768
Construction Administration Services
Conduct preconstruction meeting and progress meeting 3 3 0,5
Field visits (Three Visits) 6
Shop Drawing'review 2 2 0,5
Change Order Preparation 0,5 0,5
Review pay requests (two anticipated) 1
Substantial completion inspection and punch list 0,5 2
Final inspection 0,5 2
Reproducibles 0,5 0,5 4 0,5
Plans and specs for contractor ( three sets) $50
Total Hours 5,5 17 6 2,5 $1,818