HomeMy WebLinkAboutControlled Environments for Industry Contract Change Order -1999 10 25~ 1 e •
C~~t,~.f ~!Vinter Springs
CUN7~Iw.:ACT CHANGE ORDER
Change Order No.1
Project No. 017-99
Project Title: Blower Replacement and Installation
Contractor: Controlled Environments for Industry, Inc.
Reason for Change Deletion and Addition of Items
The Following Modifications to the Contract are Hereby Ordered:
Item No. and Description Item Value
SECTION 11373 BLOWERS•
1 Delete Sub-section 1.04.A.4 Anchoring Blower to Pad $ (300.00)
2 Delete Sub-section 1.04.C, Special tools, etc. $ (1,630.00)
3 Delete Sub-section 1.04.D, Spare Parts $ (1,500.00)
4 Delete Sub-section 2.08 A, 1- ButterFly Valve $ (1,600.00)
5 Delete Sub-section 2.08 B, 1- 12" Wafer Check Valve $ (3,500.00)
6 Delete Sub-section 2.08.C,1-12" Expansion Joint $ (1,650.00)
7 Delete Sub-section 2.09, Control Panel and Accessories $ (4,600.00)
TOTAL DEDUCTS ($14,780.00)
1 Substitute TEFC Premium Efficiency Motor $ 2,350.00
TOTAL ADDITIONS $2,350.00
CHANGE ORDER VALUE: ($12,430.00)
Origional Contract Price: $71,315.00
Total Value Previous Change Orders: $0.00
Total Value CO #1 ($12,430.00)
New Contract Price: $58,885.00
Origional Contract Duration 60 days
Proposed Time Extension 60 days
New Contract Duration 120 DAYS