HomeMy WebLinkAbout1998 12 14 Consent Item I
COMMISSION AGENDA
ADD ON
ITEM I
Consent X
Informational
Public Hearing
Regular
December 14. 1998
Meeting
MGR ~EPT
Autho~ization
REQUEST: City Manager requesting the City Commission approve a
contract amendment with S.R.I. Planning and Architecture, Inc.
PURPOSE: This agenda item is needed to fund additional architectural and
engineering structures needed to complete an expanded scope of
services requested by the City relative to the City Parks
Improvement Program.
CONSIDERATION:
On January 12, 1998 the City entered into a contract with S. R.1. to
prepare construction documents and to provide construction
supervision services for the construction of the City's Parks
Improvement Program in the amount of $65,000.
At the City's request the scope is being expanded to include the
following design services at an additional cost of $45,000.
1. Grizzly soccer and football field complex.
2. Winding Hollow environmental park.
3. Central Winds Park restrooms, concession stand, service
road, field "1" re-design.
4. Civic/Senior Center entranceways.
In addition, approximately 9,000 is needed for geo-technical and
surveying services needed for completion of the design and
construction documents.
FUNDING:
Funding for this project will be provided from the general fund which
will be reimbursed from the bond issue that will be presented to the
Commission on the January 11, 1999 Commission meeting.
A&E
Services
S.R.1.
S.R.1. Amendment
Total S.R.t
A&E
Cost
$65,000
$45.000
$110,000
Estimated % of Construction
Construction Cost Cost
$1,100,000 5.9%
$1.035.300 4.3%
$2,135,300 5.2%
Engineering
$9,000
$2,135,300
.04%
The original construction estimate of $1,200,000 upon which the
original S.Rt. contract was negotiated was developed by the City.
The revised construction estimates of $2,135,300 were provided by
S.RI. The $2,135,300 estimate includes a $194,100 contingency
in addition to the normal pricing due to below cost estimates due to
the volatility of the current construction marketplace.
RECOMMENDATION:
It is recommended that the Commission approve $45,000 for
amendment "1" to S.RI.'s original contract and $9,000 for
engineering services needed to complete the construction
documents.
ATTACHMENTS:
Amendment "1" S.Rt. Contract
Revised Cost Estimates
COMMISSION ACTION:
Dee 10 98 03:58p
Joe Ranaldi
407-977-1019
p. 1
.
sri
10 Dee 98
Ronald W. McLemore
City Manager
1000 East SR 434
Winter Springs. Florida 32708
Re: Amendment No.1
To the Agreement Between Owner and Architect dated 24 Mar 98
For the Local Parks Rehabilitation Project
Ron
Based on our presentation to the City Commission on 26 Oct 98, and their approval of the overall
improvements and estimated construction budget. as well as our recent conversations regarding additional
survey and geotechnical work needing to be done, please accept this amendment to our above referenced
contract to cover our expense for completing the work
I Scope or Amendment
This amendment shall become part of the above referenced contract including the terms and
conditions therein;
A. The first change to the scope of work entails an expanded design effort to include the
following park designs which also increased Ule project's constmction budget from $
1,200,000 to $ 2,135,300: (1,941,200 plus a l00A1 contingency )
1) Add "'Grizzly Field" to the list of park improvements
2) Add a nature trial between Moss Park and Sunshine Park
3) Add a nature trail to Winding Hollow
4) Add a restroom prototype design to the project (restroom facilities originally by
others)
S) Add minor improvements to "Central Winds" to the list of park improvements
B. The second issue is 110t a change but rnther a clarification, which is the additional sU1'Vey and
geotechnical worlc required to complete our design. which is not part of our scope of service
in the original contmct. and in fact is listed as by owner. We in an effort to stay on schedule
have solicited proposals for these services and want to confirm here that the City will pay for
same. The approximate cost for survey and geotechnical services is as follows:
1) Smvey work at Trotwood Parle $ 1219.00
2) SurveyworkatSun.shinePark 1474.00
3) Survey work at Winding Hollow 1474.00
4) Geotechnicnl work at all p8rks 4660.00
Starmer RanaJdi Planning and Architec.ture loco AA-002984
890 Northern Way Suite B-1 Winter Springs. Florida 32708 Phone 407 m 1080 Pax 407 977 1019
Dee 10 98 03:58p
Joe Ranaldi
407-977-1019
p.2
II. Schedule of Fees
A. For the additional design wort<: we propose the original fee of 65,000 be increased by 45,000.
bringing the total to $ 110,000 or 5.15% of the $ 2,135,300 construction budget.
B. For the swvey and geotechnical work we are proposing an allowance of $ 9,000 be set aside
and we will forward all invoices for these services directly to the City for payment
As you know tinting is of the essence for this project and with the anticipated 2 to 3 week turn around time
for the survey and geotechnical work we need to proceed as soon as possible.
We tn1st this proposal will be well received and upon your written authorization below we will proceed
with getting this additi work done immediately.
President
Amendment No. 1 Aocepted_...__
Ronald W. Mclemore City Manager
Date
Dee 10 98 01:06p
Joe Ranaldi
10 Dee. 98
Winter Springs Parks Improvement Program
Estimate of Probable Cost
Summary
l.
2.
3.
4_
5.
6_
7_
8.
9.
Central Winds Park
Grizzly Field
Moss Park
Sam Smith Park
Sunshine Park
Torcaso Park
Trotwood Park
Winding Hollow Park
Sunshinetrorcaso Trail % (6500)+1 bridge(2500)
Subtotal
Continftllcv (Q) 10%
Total Estimated Cost
Breakdown per Park
1.
Central Winds Park
a. Restrooms I Concession Facility
b. New Practice Fields
c. Clay Storage Fencing
d_ Access Road
e. Site Electrical
Const. Cost
85000
20000
2000
15000
3500
407-977-1019
Const.
Cost
125,500
35,000
234,700
99,200
153,000
248,900
529,800
214,100
9000
1.649.100
164.900
1,814,100
Equip. Cost
NA
NA
NA
NA
NA
Equip.
Cost
NA
NA
59,000
59,000
59,000
25,000
59,000
31,000
NA
291.000
29.200
321,200
p. 1
Total
Cost
125,500
35,000
293,700
158,200
212,000
273,900
588,800
245,100
9,000
1.941.200
194.100
1,135,300
Total COnstructiOD COlli
125,500
2. Grizzly Field Const. Cost Equip. Cost
a. Stabilized road and parking 23500 NA
b. Grade fields & seed 5000 NA
c. Proof roll fields 1500 NA
d. Baseball practice fields (2) 5000 NA
E. W.S. to provide irrigation NA
Total Construction Cost 35,000
004CstEst2
lof5
.
sri
Dee 10 98 11:o5a
Joe Ranaldi
407-977-1019
p.2
3. Moss Park Const. Cost Equip. Cost
a. Primary entry kiosk 8600
b. Secondary entry kiosk 4200
c. Primary entry landscaping 4500
d. Secondary entry landscaping 1500
e_ Entry road 80 If(45) 3600
f Parking 10(500) 5000
g. Walkway 700 If(12) 6500
h. Bridge 4000
i. Restrooms 70000
j. Medium pavilion P2 13400
k. Small pavilion PI 10800
1. Large Tot-lot play area 3000
m. Tot-lot equipment 25000
n. Large youth play area 5000
o. Youth play area equip. 34000
p. Basketball court 37000
Q. Half court 21000
r. Walkway lighting 4(2500) 6000
s_ Coun lighting 10000
1. Site grading & drainage allowance 7500
u. Demolition SOOO
v. Drinking fountains 4600
w. Site Electrical 3500
Total Construction COllt 234,700
Equipment Cost 59,000
4. Sam Smith Park Coast. Cost Equip. Cost
a. Primary entry kiosk 8600
b. Secondary entry kiosk 4200
c. Primary entry landsc.aping 4500
d. Secondary entry landscaping 1500
e. Entry road 2000 If (45) 9000
f Parking 12 (500) 6000
g. Walkway 1300 If(12) 15600
h. Medium pavilion P2 ]3400
i. Small pavilion PI 10800
j_ Large Tot..Jot play area 3000
k. Tot-lot equipment 25000
l. Large youth play area 5000
m. Youth play area equip. 34000
n. Site grading & drainage allowance 7500
o. Drinking fountains (2) 4600
p. Demolition 2000
q. Site electrical 3500
Total Construction Cost 99,200
Equipment Cost 59,000
004CstEst2
20f5
.
SrI
Dee 10 98 11:o6a
Joe Ranaldi
407-977-1019
p.3
S. Sunshine Park Const. Cost Equip. Cost
11. Primary entry kiosk 8600
b. Primary entry landscaping 4500
c. Entry road 80 tf(45) 3600
d. Walkway 600 If(12) 7200
e. Large pavilion P3 27000
f. SmaU pavilion PI 10800
8. Large Tot.lot play area 3000
h. Tot-lot equipment 25000
i. Large youth play area 5000
J. Youth play area equip. 34000
k. Basketball court 37000
J. Half court 21000
m. Building entry enhancements 10000
k. Site grading & drainage allowance 7500
I. Drinking fountains (2) 2300
m. Demolition 2000
n. Site electrical 3500
Total Construction Cost 153,000
Equipment Cost 59,000
6. Torcaso Park CODIIt. Cost Equip. Cost
a. Primary entry kiosk 8600
b. Secondary 6Jltry kio~k 4200
c.Primary entry landscaping 4500
d. Secondary entry landscaping 1500
e. Entry road 100 If(45) 4500
f. Parking 12 (500) 6000
g. WaJkway 1600 If(l2) 19200
h. Fishing pier 4 (I 6,5(0) 66000
i. Restrooms 70000
j. Medium pavilion P2 13400
k. Small pavilion PI 10800
1. Large Tot-lot play area 3000
m. Tot-lot equipment 25000
n. Walkway lighting 14 (600) 8400
o. Court lighting 4 (2500) 10000
p. Site gradins & drainage allowance 7500
q. Water feature 3500
o. Drinking fountains (1) 2300
p. Demolition 2000
q. Site electrical 3500
Total Construction C<lBt 148.900
Equipment Cost 25,000
004CstEst2
30f5
.
sri
Dee 10 98 11:06a
Joe Ranaldi
407-977-1019
p.4
7. Trotwood Park Const. Cost Equip. Cost
a. Primary entry kiosk 8600
b. Secondary entry kiosk 4200
c. Primary entry landscllping 4500
d. Secondary entry land~ing 1500
e. Entry road 900 If (451 40500
f. Parking 130 (500) 65000
g. Walkway 2600 If(12) 24000
h. Medium pavilion P2 (4) 53600
i. Small pavilion PI 10800
j. Large Tot-lot play area 3000
k. Tot-lot equipment 25000
1. Large youth play area 5000
m. Youth play area equipment 34000
n. Soccer field 3 (36000) 108000
o. Ball Field 3 (40000) 120000
p. Fishing pier 2 (16500} 33000
q. Site grading & drainage allowance 35000
r. Drinking fountains (2) 4600
s. Demolition SOOO
t Site electrical 3500
Total CODstmction C~Rt 529.800
Equipment Cost 59,000
8. Winding Hollow Park CODst. Cost Equip. Cost
a. Primary entry kiosk 8600
b. Primary entry landscaping 4500
c. Entry road 100 If(45) 4500
d. Parking 6 (500) 3000
e. Wa1lcway 100 If(I2) 1200
f. Small pavilion PI 10800
g. Small Tot-lot play area 3000
h. Tot-lot equipment 15000
i. Small youth play area 3000
j. Youth play equipment 16000
k. Site grading & drain<lge allowance 3000
I. Winding Hollow Trail ( 4miles)
(16 x: 6500) + 6 bridHes (2500) 119000
m. Trail breakout decks (1 Ox5000) 50000
q. Site electrical 3500
Total CoDstrudion COlil 214,100
Equipment Cost 31,000
9. Sunshine/Torcaso Trail Const.Cost Equip. Cost
Trail 6500
Bridge 2500
Total Construction Cost 9,000 .
004CstEst2 4of5 SrI
Dee 10 9a 11:o6a
Joe Ranaldi
407-977-1019
p.5
General Unit Prices
1. Primary Entry Kiosk Lump Sum 8600
2. Secondary Entry Kiosk Lump Sum 4200
3. Primary Entry Landscaping Lump Sum 8500
4. Secondary Entry Landscuping Lump Sum 4500
5. Large Pavilion up3" Lump Sum 27000
6. Medium Pavilion "P2" Lump Sum 13400
7. Small Pavilion "PI" Lump Sum 10800
8. Fishing Pier Lump Sum 16500
9. Large Tot Lot Play Area. "TI" Lump Sum 3000
10. Large Tot Lot Equip. Lump Sum 25000
11. Small Tot Lot Play Area "T2" Lump Sum 3000
12. Small Tot Lot Equip. Lump Sum 15000
13. Large Youth Play Area "YI" Lump Sum 4000
14. Large Youth Play Equip. Lump Sum 35000
15. Small Youth Play Area "Y2" Lump Sum 4000
16. Small Youth Play Area Equip. Lump Sum 21000
17. New Basketball Coun Lump Sum 37000
18. New Power Court Lump Sum 21000
19. Resurface Court Per sf 6
20. Paved Road Per If 45
21. Stabilized Parking Per space 500
22. 6' Wide Side Walk Per If 12
23. Stabilized Road Per cy 8.5
24. Court Light Each 2500
25. Walk Light Each 600
26. Bridge Lump Sum 12000
27. Soccertle1d Lump Sum .36000
28. Ballfield Lump Sum 40000
25. Restrooms I concession:. Per sf ]00
26. Water Fountains Each 2300
21. Site Electrical Each 3500
004CstEst2
SofS
.
sri
r~
sri
10 Dec 98
Ronald W. McLemore
City Manager
1000 Bast SR 434
Winter Springs, Florida 32708
Re: Amendment No. l
To the Agreement Between Owner and Architect dated 24 Mar 98
For the Local Parks Rehabilitation Project
Ron
Based on our presentation to the City Commission on 26 Oct 98, and their approval of the overall
improvements and estimated construction budget, as well as our recent conversations regarding additional
survey and geotechnical work needing to be done, please accept this amendment to our above referenced
contract to cover our expense for completing the work
I. Scope of Amendment
This amendment shall become part of the above referenced contract including the terms and
conditions therein:
A. The first change to the scope of work entails an expanded design effort to include the
following park designs which also increased the project's construction budget from $
1,200,000 to $ 2,135,300: (1,941,200 plus a 10% contingency )
1) Add "Crrizzly Field" to the list of park improvements
2) Add a nature trial between Moss Park and Sunshine Park
3) Add a nature trail to Winding Hollow
4) Add a restroom prototype design to the project (restroom facilities originally by
others)
5) Add minor improvements to "Central Winds" to the list of park improvements
B. The second issue is not a change but rather a clatification, which is the additional survey and
geotechnical work required to complete our design, which is not part of our scope of service
in the original contract, and in fact is listed as by owner. We in an effort to stay on schedule
have solicited proposals for these services and want to confirm here that the City will pay for
same. The approximate cost for survey and geotechnical services is as follows:
1) Survey work at Trotwood Park $ 1219.00
2) Survey work at Sunshine Park 1474.00
3) Survey work at Winding Hollow 1474.00
4) Geotechnical work at all parks 4660.00
Starner Ranaldi Planning and Architecture Inc. AA-002984
890 Northern Way Suite E-1 Winter Springs, Florida 32708 Phone 407 977 1080 Fax 407 977 1019
~ -, •
II. Schedule of Fees
A. For the additional design work we propose the original fee of 65,000 be increased by 45,000,
bringing the total to $ 110,000 or 5.15% of the $ 2,135,300 construction budget.
B. For the survey and geotechnical work we aze proposing an allowance of $ 9,000 be set aside
and we will forward all invoices for these services directly to the City for payment.
As you know timing is of the essence for this project and with the anticipated 2 to 3 week turn azound time
for the survey and geotechnical work we need to proceed as soon as possible.
We trust this proposal will be well received and upon your written authorisation below we will proceed
with getting this additional work done immediately.
Re ds
W er N •
President
Amendment No. 1 Accepted `Z ~~v~uP.~Q 'vJ • `~~,~..~._ " .I)ate~ g