CHANGE ORDER FORM
Project Title: SR434 and Doran Drive Signalization Project Change Order No
Agreement Date: February 23, 2005
Contractor: Traffic Control Devices. Inc.
This Change Order is necessary to cover changes in the work to be performed under this
Agreement. The GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS, and
STANDARD SPECIFICATIONS appl to and overn all work under this Chan a Order.
Reason for Change:
Update steel and concrete unit prices based on new contract with Seminole County, and the
addition of McLeod's Way.
THE FOLLOWING CHANGES ARE MADE TO THE CONTRACT DOCUMENTS:
Item No. and Description Change in
Contract Price Change in
Contract Time
1. See Attached Work Sheet $29,620.55 Completion Date of
January 31, 2006
2.
3.
4.
5.
1. Original Contract Price
2. Current Contract Price (Adjusted By Previous Change Orders)
3. Total Proposed Change in Contract Price
4. New Contract Price (Item 2 plus Item 3)
5. Original Construction Completion Date
6. Original Contract Time
7. Current Contract Time (Adjusted By Previous Change Orders)
8. Total Proposed Change in Contract Time
9. New Contract Time (Item 6 plus Item 7)
10. New Construction Completion Date
$141,865.42
$141, 865.42
$29,620.55
$171,485.97
N/A
N/A
N/A
N/A
N/A
January 31, 2006
~ ~
WAIVER This Change Order constitutes full and mutual accord and satisfaction for the
adjustment of the Contract Price and Contract Time as a result of increases or decreases in
cost and time of performance caused directly and indirectly from the change. Acceptance of
this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change
Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall
waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution
of this Change Order shall constitute CONTRACTOR s complete acceptance and satisfaction
that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change
Order.
APPROVAL AND CHANGE ORDER AUTHORIZATION
ACKNOWLEDGMENTS
The aforementioned change, and work affected thereby, is subject to all provisions of the
original Agreement and specifically changed by this Change Order; and it is expressly
understood and agreed that the approval of the Change Order shall have no effect on the
original Agreement other than matters expressly provided herein.
Recommended By:
`~~ .
Engineer
i
Directo tilit~~ blic rks
"~ Capita~pj'ects Coor~nator
9--/a-os
Date
~~~ 3~0 ~~
Date
~ S
Dat
ATTEST:
(Secretary)
Date
(Corporate Seal)
ATTEST:
By
Contractor
/
y /acr ,tC,s~v~a.v~
9- S -os
Date
Owner
By Ronald W. McLemore,
City Manager
~a/z/.s~
Date Dafe
• i
5R434 at Doran Drive -Change Order No,1
Traffic Control Devices, Inc.
25-Aug-05
Deductions
Item No. Item Descri tion Quantit Unit Unit Price Tatal Price
341 648-11-45F Mast Arm Assem. 1 EA $ 7,712.00 $ 7,712.00
343 648-11-50F Mast Arm Assem 2 EA $ 8,171.00 $16342.00
345 648-11-55F Mast Arm Assem 1 EA $ 8,221.00 $ 8,221.00
438 648-99D Deco Base 4 EA $ 1,921.00 $ 7,684.00
447 715-99 Luminaire Acom 4 EA $ 1,714.00 $ 6 856.00
89 648-1 B 48" Conc. Foundation 64 LF $ 202.16 $12,93824
237 659-108 Steel Pedestal 2 EA $ 480.94 $ 961.88
238 659-109 Concrete Pedestal 1 EA $ 490.23 $ 490.23
653-181 Ped Si nal LED 2 EA $ 514,71 $ 1,029.42
Total $ 62 234.77
Addltlons (U dated Prices
Item No. Item Descri tion Quanti Unit Unit Price Total Price
341 648-11-45F Mast Arm Assem. 1 EA $ 7,405.00 $ 7,405.00
343 648-11-50F Mast Arm Assem 2 EA $ 9,090.00 $18,180.00
345 648-11-55F Mast Arm Assem 1 EA $10,685.00 $10,685.00
438 648-99D Deco Base 4 EA $ 2,265.50 $ 9,062.00
447 715-99 Luminaire Acom 4 EA $ 1,714.00 $ 6,856.00
89 648-1 B 48" Conc. Foundation 54 LF $ 555.50 $ 29,997.00
237 659-108 Stee! Pedestal 2 EA $ 1,115.00 $ 2,230.00
238 659-109 Concrete Pedestal 1 EA $ 590.00 $ 590.00
Total $ 85,005.00
Addltlons Revised Plans
630-1-12 Conduit Under round 60 LF $ 5.25 $ 315.00
635-1-11 Pull Box 1 EA $ 276.50 $ 276.50
650-1-111 B LED Red Ball 2 EA $ 65.00 $ 130.00
650-1-111 E LED Yellow Ball 2 EA $ 82.25 $ 164.50
650-1-111 H LED Green Ball 2 EA $ 121.00 $ 242.00
650-1-111 N LED Yellow Amow 1 EA $ 61.25 $ 61.25
650-1-111Q LED Green An•ow 1 EA $ 91.00 $ 91.00
650-51-311 3-Section Head 1 AS $ 520.00 $ 520.00
650-51-511 5-Section Head 1 AS $ 730.50 $ 730.50
653-182 Ped Si nal - 2-Wa 2 AS $ 1,029.42 $ 2,058.84
680-1-105 Loo Det 2 EA $ 252.91 $ 505.82
660-1-106 Loo Det 1 EA $ 252.91 $ 252.91
660-2-106 Loo Assembl T e F 2 AS $ 650.00 $ 1,300.00
665-11 Ped Detector 2 EA $ 101.00 $ 202.00
Total $ 13,850.32
Total Chan a Order Amount $ 29,820.55