Update to Design + Construction Services for the East & West WRFs
C A R O L L O / 2
•Recap of Existing Facilities & Project Purpose
•East WRF Design & Construction Updates
•Funding & Design Updates
•Construction Cost Estimate
Meeting Agenda
C A R O L L O / 3
Existing Facilities
East WRF
West WRF
C A R O L L O / 4
•East & West WRFs
•Outdated, used steel-ring package plants
installed in the 1970/80’s
•Surpassed the end of their useful life by at least
a decade – failing infrastructure, highly-
corroded tank walls, antiquated design, etc.
•Existing facilities include a single-train process
•One disruption impacts the entire treatment process
•Require both replacement & modernization
•New facilities are designed for flexibility,
reliability, and treatment effectiveness
•Facilities will have multiple trains in parallel –
allows for minimal process impact while service
occurs
Existing Facilities
C A R O L L O / 5
•Design
•Currently focused on the East WRF;
West WRF is to follow
•Preliminary Engineering & Design for
the East WRF was completed in
February 2025
•Construction permit was issued based
on Preliminary Design in March 2025
•Final Funding Application Design
drafted for funding application (SRF)
June 2025
Design Updates
C A R O L L O / 6
•Funding
•Commission authorized project funding (design) to be secured through Clean Water State Revolving Fund
(CWSRF) financing on June 13, 2022
•Design Loan funding was secured
•Clean Water SRF & ARPA
•Construction anticipated to be primarily funded by SRF, and project team is evaluating additional grant funding
opportunities
•Supplemental Appropriation for Hurricanes Helene & Milton
•Protecting Florida Together Grants (i.e., Water Quality Improvement Grant)
•Next step: submission of Final Construction Funding Request for Inclusion
•Submittal date: June 30, 2025
•Requires:
•SRF loan application – completed & in review with FDEP
•Design plans and specifications – completed & in review with FDEP
•FDEP permit – completed & approved by FDEP in March 2025
•Construction cost estimate for SRF Funding Request – completed
Funding Updates
C A R O L L O / 7
•Guaranteed Maximum Price (GMP)
•How is it developed?
•OPEN BOOK!
•CMAR Differs from Hard-Bid
•GMP Design Review
•GMP Bid Manual Development
•Competitive Bidding
•Thorough Review of Bids
•Assembly of final GMP including:
•Breakdown of all bids received
•General Conditions Costs
•Risk Register
•Schedule
•Clarifications
What is a GMP?
C A R O L L O / 8
•What is a Risk Register?
•A Tool to define both the known and unknown project risks
•What is the Risk Register Used for?
•Outlining risk mitigation strategies
•Defining contingency and allowance cost allocations
Risk Register
C A R O L L O / 9
•Components of the Estimate
•Direct Costs – All equipment, materials, and subcontract costs associated with the
work-in-place
•General Conditions (GC’s) – Project staffing and administration costs
•Contingency – Based on the Risk Register – Cost for unexpected or non-quantifiable
costs and for design yet to be completed
•Escalation Contingency – Estimate of potential cost escalations due to Tariffs,
material shortages, etc.
•Bond – Contractors Payment and Performance Bond as required by the contract
•Insurance – Contractors General Liability Insurance as required by the contract
•Fee – Contractor's profit and non-direct overhead costs
SRF Deliverable Estimate
C A R O L L O / 10
•Key Takeaways & Next Steps
•Overall Project Cost - $/Treatment
Gallon is in line with current market
•As design moves to GMP/Bid Phase
(November/December) it is expected
that Contingency will go down, Direct
Costs may increase
•Continued Value Engineering (VE) &
Design Workshops will take place to
reduce cost and improve efficiency
will occur over next 5 months
•Guaranteed Maximum Price (GMP)
Bid phase will commence in
December
SRF Deliverable Estimate
SRF Funding Request
C A R O L L O | 11
East WRF Schedule
2025 2026 2027 2028
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
SRF Funding Application
and Approval
Finalization of Design and GMP
East WRF Material and
Equipment Procurement
East WRF Construction
Submission of SRF Construction Application to FDEP.
SRF Construction Funding Approval.
Construction Cost Estimate Update.
C A R O L L O | 12
Future / Lookahead Schedule
2025 2026 2027 2028 2029
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
SRF Funding Application
and Approval
Finalization of Design and
GMP
East WRF Material and
Equipment Procurement
East WRF Construction
West WRF Design,
Permitting & Material
Procurement
West WRF Construction
Submission of SRF Construction Application to FDEP.
SRF Construction Funding Approval.
SRF Construction Funding Approval.
Submission of SRF Construction Application to FDEP.
Construction Cost Estimate Update.