HomeMy WebLinkAbout2022 05 23 Consent 301 - Trotwood Park Basketball CourtCONSENT AGENDA ITEM 301
CITY COMMISSION AGENDA | MAY 23, 2022 REGULAR MEETING
TITLE
Trotwood Park Basketball Court
SUMMARY
Considering the current and future uses of Trotwood Park, staff is
recommending moving the basketball courts to the Northwest corner of the
park. Additional parking is needed at the park, as parking continues to be
insufficient for the users of the park, and the current basketball courts are
due for an upgrade. New courts will be installed and the old courts will be
turned into additional parking area. The cost to install new courts in the park
will be $315,256 including a 10% contingency for unknown issues or price
increases that may arise.
RECOMMENDATION
Staff recommends City Commission approve funding not to exceed $315,256
dollars and to authorize the City Manager and City Attorney to prepare and
execute any and all Applicable contract documents consistent with this
agenda item.
24
CITY OF WINTER SPRINGS
TROTWOOD PARK
BASKETBALL ADDITION COST ESTIMATION
ITEM AMOUNT
Kimley Horn Engineering 24,500
Southeastern Survey 3,147
Varsity Courts 70,950
Basketball Couts Custome design artwork upgrade 20,000
Irrigation 3,000
Landscaping 15,000
Site Furnishings benches, water fountain, tables, Trash Bike rack 10,000
Concrete (Connectivity, ribbon curbs, pads)25,000
Site Restoration Sod, fill dirt etc.10,000
Misc 5,000
Stormwater requirements SJWMD Estimate 100,000
10% Contingency 28,659
TOTAL 315,256
25
26
27