HomeMy WebLinkAbout2022 05 23 Consent 300 - Pickleball Court Project - Central Winds ParkCONSENT AGENDA ITEM 300
CITY COMMISSION AGENDA | MAY 23, 2022 REGULAR MEETING
TITLE
Pickleball Court Project - Central Winds Park
SUMMARY
Staff has presented a concept plan for the pickleball stadium to both the City
Commission and the City Parks and Recreation board. This stadium will be
located in Central Winds Park. The facility will have 14 pickleball courts, 98
parking spaces and a restroom.
Staff is coordinating with contractors to obtain materials and supplies. The
estimate for the courts, parking lot and restrooms is Two Million Two
Hundred and Ninety-Four thousand Four Hundred and Fifty-Two dollars. The
funds for this project are included in the current year's approved budget for
Perk Up Parks. A breakdown of the costs are as follows:
Site Work $236,121
Pickleball Courts $689,050
Restrooms $175,000
Parking Lot $861,229
Stormwater/Utilities $223,793
5% Contingency $109,259
TOTAL $2,294,452
RECOMMENDATION
Staff recommends City Commission approve funding not to exceed Two
Million Two Hundred and Nine-Four thousand Four Hundred and Fifty Two
dollars to complete the Pickleball court project and to authorize the City
Manager and City Attorney to prepare and execute any and all applicable
contract documents consistent with this agenda item.
9
10
11
12
13
14
15
16
17
18
19
20
21
CITY OF WINTER SPRINGS
Central Winds Park
Pickle Ball Courts / Parking Lot
Pro-Forma
Expense Estimated Amount
SITE WORK
Clearing & Demolition
General Demolition 8,402
Clearing/Grubbing 3,028
Erosion Control
Type III slit Fence 2,915
Stabilized Construction Entrance 1,550
Inlet Protection 1,713
Earthwork
Cut, Move, & Place 5,298
Import Fill 181,000
Milling Existing Asphalt 2,015
Segmental Block Retaining Wall 30,200 236,121
PICKLEBALL COURTS
Engineering ( Storm Water, transportation civil docs) 49,500
Southeastern Survey and GeoTech (1/3 of cost) 13,350
Pickle Ball Courts & Fences 166,700
Electrical Contractor 50,000
Led Light Poles (40 Poles)(Outlets) 75,000
Shade Structures with bench (14) 60,000
SOD Replacement 25,000
Fill Dirt 50,000
Construction Fence 10,000
Concrete walkways 50,000
Water Fountains 2,500
Benches for common area 5,000
Shade Structure over common area 12,000
Landscaping 60,000
Irrigation 10,000
Potable water 50,000 689,050
PARKING LOT
Concrete
Ribbon Curb 68,261
Bollard 4,500
Striping and Signage 41,430
4" Concrete Sidewalk 26,076
Detectable Warning Pad 2,320
Wheel Stop 4,230
Paving
Limerock Base Group 4 102,462
Limerock Base Group 6 61,519
Plain Cement Pavement 6" 53,400
Pervious Pavers 191,143
Superpave Asphaltic Concrete, Traffic C 88,389
22
Electrical / Landscaping / Irrigation / Misc
Electrical Contractor 50,000
Led Light Poles (40 Poles)(Outlets) 75,000
Asphalt Inspector Consultant 5,000
Benches for common areas 2,500
Landscaping 60,000
Irrigation 25,000
861,229
STORM WATER
Exfiltration System
Contech System 105,570
Storm Pipe
8" HDPE Pipe 1,600
12" CMP Pipe 69,580
Structures
P7 Manhole 7,015
Yard Drain 4,200
Type C Inlet 35,829 223,793
RESTROOM
Restroom's (Similar to Torcaso's new one)175,000 175,000
Project Sub Total 2,185,193 2,185,193
5% Contingency 109,259 109,259
TOTAL PROJECT 2,294,452 2,294,452