HomeMy WebLinkAbout2023 03 13 Informational 200 - Current Development Projects Summary • INFORMATIONAL AGENDA ITEM 200
,n m=ared CITY COMMISSION AGENDA I MARCH 13, 2023 REGULAR MEETING
1959
TITLE
Current Development Projects Summary
SUMMARY
RECOMMENDATION
Staff recommends the City Commission receive and review this information.
39
• CITY OF WINTER SPRINGS, FLORIDA
COMMUNITY DEVELOPMENT DEPARTMENT
fneorp4ra[ed
Current Development Projects Summary
Pre-Applications and Non-Binding Reviews
• Pre-application meetings are required for all projects before a formal submittal is permitted.
During these meetings, applicants will outline their proposed project to staff and staff will
provide feedback and explain the development review process.
• Non-binding reviews are sometimes recommended by staff if a proposed project is potentially
controversial. Non-binding reviews undergo a very high-level review by staff with some
comments provided to the applicant. The intent is for the applicant to present the project to the
City Commission to gauge their receptiveness to the proposed project.
PROJECT
1270 Belle Ave West side of Belle Ave Pre-application meeting Awaiting formal submittal
lust south of SR 434 held on October 27
The Adel at Lake Jesup North side of Orange Ave N/A Non-Binding presentation
at March 27
City Commission
Dunkin' Donuts North side of SR 434 lust Pre-application meeting Awaiting formal submittal
east of Michael Blake held on December 15
Blvd
Dittmer RV Storage Southwest corner of Pre-application meeting Awaiting formal submittal
Shepard Rd. and Seven held on January 12
Oaks
The Oaks at Lake Irene South side of SR 434 lust Pre-application meeting Awaiting formal submittal
(Primarily in Seminole east of Hwy 17-92 held on February 16
County)
The Grove(Expansion) North side of Old Sanford Pre-Application meeting Awaiting formal submittal
Oviedo Rd. held on February 7
Fast Food Restaurant North side of SR 434 lust N/A Pre-Application meeting
(Unidentified) east of SR 417 to be scheduled
Titan Winter Springs South side of SR 419 lust N/A Pre-application meeting
Storage west of the split with SR to be scheduled
434
40
Development Protects in Review
• These are projects that have gone past the stage of a pre-application meeting and are in various
stages of the development review process.These projects could be anywhere from confirming
that the application is complete all the way through to approval of the project by the City
Commission or even beyond that to construction or final site acceptance.
PROJECT
Hickory Grove Town Center Preconstruction First Modification to
Townhomes meeting held on Development
Northeast of Bear Springs 06/01/22 Agreement approved
132 Single-Family Dr.and Blumberg Blvd. by City Commission on
meeting heelld on 8 8/19/222 ons
Homes(Attached) Second p February 27.
/19
Fifth Third Bank Town Center Pre-Construction Under Construction
Southwest corner of SR Meeting held on January
434 and Tuskawilla Rd. 26
Living Life Development North Side of W SR 434, Community Workshop Plans under staff review
(ILF) west of Fountaintree Dr. was held on February 22
Ace Hardware Town Center Pre-application meeting Aesthetic Review headed
Southeast corner of SR in July 2022 to City Commission in
434 and Tuskawilla, lust March or April
south of Mobil station
Excelsior Town homes Excelsior Pkwy N/A Awaiting complete
East side of Moss Rd. application materials
Tuskawilla Self-Storage County Enclave N/A Awaiting public hearing
(Not in city limits) East side of Tuskawilla date to be set by
Rd. lust south of Michael Seminole County
Blake Blvd.
Fisher Optometry Town Center Pre-application meeting Awaiting complete
East side of Tuskawilla in 2021 submittal
Rd. north of SR 434
41