HomeMy WebLinkAbout2024 03 25 Consent 301 - Tuskawilla Crossings Stormwater Pond - Pond 1 Emergency RepairCONSENT AGENDA ITEM 301
CITY COMMISSION AGENDA | MARCH 25, 2024 REGULAR MEETING
TITLE
Tuskawilla Crossings Stormwater Pond - Pond 1 Emergency Repair
SUMMARY
In response to the severely damaged stormwater pond, located in the Tuskawilla
Crossings subdivision, the City of Winter Springs and Pegasus Engineering have
undertaken the process, with Commission approval, to evaluate and reconstruct a
large portion of the existing pond facility. The City and Pegasus have been working
closely in this process with the St. John's River Water Mangement District (SJRWMD).
SJRWMD has requested that during the design and permitting phase with the WMD
the City temporarily install fill material at the breached location in order to avoid any
further direct discharge to the downstream wetlands without pollution abatement and
attenuation. Final reconstruction of the pond will occur once the design is final and
permitted through the SJRWMD.
FUNDING SOURCE
Third generation sales tax revenue will provide sufficient funding for this temporary
measure as required by the SJRWMD.
RECOMMENDATION
Staff requests Commission approval for the temporary emergency repair of Pond 1
located in the Tuskawilla Crossing subdivision. Staff recommends the contract be
awarded to Outdoor With It, LLC with a low bid of $75,792.39. This repair is a
temporary measure until such time that the final repairs are made to the overall pond
facility. Other bids were: Southern Development and Construction ($184,752.00), CL
Green Inc. ($135,000.00) and Florida Site Services ($79,252.40).
16
Contract
Date
2/28/2024
Estimate #
1182
Name / Address
City of Winter Spings
1126 East State Road 434
Winter Springs, FL 32708
CL Green, Inc.
P.O. Box 868
Windermere, FL 34786-0868
Pond Bankment Repair
Estimate good for 30 days! Thank you.
Phone #
407-909-0900
E-mail
clg@clgreeninc.com
Web Site
www.clgreeninc.com
Total
Job Site
Item Description Cost Total
Machine Machine time and labor 135,000.00 135,000.00
Mobilization x2 Machine transportation fees
Sod Bahia on repair embankment
Fill Fill dirt material 1,200 cy
compaction work Compaction work
Compaction Test Compaction Test
Materials Will use mats to protect pedestrian Trail
Dumpsters Dump for green debris
Trucking Dump truck time, and dump fees
Pumps Pumps if needed
Authorized Signature:_________________________________
Print
name:___________________________________Date__________
*Excess is 1422 Trailhead Point
*No permits
*No other washout repair
*No extra grass
$135,000.00
17
Florida Site Services
PROJECT NAME:Tuskawilla Pond Repair
ATTN:Stuart Maclean
DATE: 2/29/2024
Description Quantity Unit Unit Price Total
General Conditions, Mob
General Conditions 1.0 LS 9,638.00$ 9,638.00$
General Conditions, Mob 9,638.00$
Erosion Control & Maintenance
Silt Fence 200.0 LF 2.90$ 580.00$
Erosion Control Maintenance 1.0 LS 2,939.00$ 2,939.00$
Erosion Control & Maintenance 3,519.00$
Mats and Yard Restoration
Light Clearing & Grubbing 1.0 LS 6,100.00$ 6,100.00$
Install / Remove Mats for Yard/Drive Protection 1.0 LS 11,809.60$ 11,809.60$
Restore and Sod Yards 167.0 SY 28.21$ 4,711.07$
Restore Concrete 28.0 SY 136.64$ 3,825.92$
Street Sweep 4.0 Ea.1,024.80$ 4,099.20$
Mats and Yard Restoration 30,545.79$
Earthwork & Grading
Import Clean Fill 700.0 CY 43.76$ 30,632.00$
Grading Slope 400.0 SY 5.80$ 2,320.00$
Sod Pond Slopes 905.0 SY 2.87$ 2,597.35$
Earthwork & Grading 35,549.35$
Total Base Bid 79,252.14$
Option to Repair and Sod SE Corner of Pond
Import Clean Fill 128.0 CY 43.76$ 5,601.28$
Grading Slope 112.0 SY 5.80$ 649.60$
Sod Pond Slopes 112.0 SY 2.86$ 320.32$
Option to Repair and Sod SE Corner of Pond 6,571.20$
Payment and Performance Bond Add 1%
Exclusions:
1
2
3
4
5
6
7
8
250 International Parkway ● Heathrow, FL 32746 ● Suite 128-1 ● (Phone) 888-711-8121
No removal/handling of asbestos
Seed and mulch of site
Construction Testing/Inspection and cost of permits
Tie to state plane coordinates; certified benchmarks and brass disks.
a.) Final layout of buildings is by others
Payment and Performance Bond
Dust control and erosion control when not actively working on site
Excavation, backfill, and disposal of
a.) hazardous material
b.) Unsuitable Soil
Excavation and backfill of building footers, foundations, or elevator shafts
18
We have based our price on the following:
1
2
3
4
5
6
7
8
9
10
Import quantities were generated and furnished by engineer. FSS shall be paid unit price for overruns
Acceptance of this proposal based on satisfactory financial arrangement.
Acceptance of this proposal based on satisfactory review of Owners/General Contractors contract with owner and//or General
This is a unit price proposal.
Our price is valid for thirty (30) days
Deletion of quoted items by mutual agreement
Existing grades as shown on drawings
Relocation of existing utilities is not included.
Location of utilities installed by others is not included.
Cleanup included only for FSS work.
19
Oviedo, FL 32765
2544 Connection Point
Southern Development & Construction
Shane Cox
321-251-0535
Contact:
Phone:
Fax:
Job Name:Quote To:City of Winter Springs Emergency Retention Pond Repairs
Date of Plans:Attn: Stuart MacLean
Phone:Revision Date:407-327-7581
Email:smaclean@winterspringsfl.org
Proposal Date:2-29-2024
HCSS 24-041
AMOUNTITEM DESCRIPTION QUANTITY UNIT UNIT PRICE
MOBILIZATION LS1.00 10 17,000.00 17,000.00
CONSTR. LAYOUT / AS-BUILTS LS1.00 20 14,700.00 14,700.00
SINGLE ROW SILT FENCE LF600.00 50 7.00 4,200.00
CLEAR & GRUB LS1.00 70 19,400.00 19,400.00
POND DEWATERING -LS1.00 80 21,300.00 21,300.00
CAUSEWAY ACCESS / RESTORATION LS1.00 85 41,962.00 41,962.00
IMPORT FILL TCY800.00 90 69.00 55,200.00
SOD POND SLOPES (BAHIA)SY1,000.00 110 7.00 7,000.00
SEED - RESTORE LOT 1422 SY2,000.00 130 2.00 4,000.00
GRAND TOTAL 184,762.00
NOTES:
PROJECT SPECIFIC NOTES
* COST - This is Fixed Cost Proposal
* TIME - Upon a Notice to Proceed, this work shall be complete withing 20 calendar days
* Starting Date - It is anticipated the start date is March 11th, 2024
* Staging of Equipment & Fill material will occur at lots 1422 & 1426 - Trailhead Point and restore with seeding
* Silt fence shall be installed around lots 1422 & 1426 & to provide access across the trail to the work zone
* Access to the work zone will include crossing the Cross Seminole Trail. It's proposed to close the trail, however it's
anticipated the traveling public will still use it. As we access the work zone, we will have personnel monitoring the trail & it's
use.
* Access to repair the berm, will included pumping the exiting pond into the manhole in which the City is currently utilizing.
Based on the documents provided, it appears this storm system discharged to the Tract B-1 Conservation.
* Once the existing pond is pumped to a manageable level, an earthern causeway is contructed to access the north side of the
pond an make the repairs.
* At the completion of the repairs, the earthen causeway is removed
GENERAL CONDITIONS/ CONTRACT
1. This proposal is based on the following Plans:
Titled: Tuskawilla Crossing
Page 1 of 2
20
Prepared By:Pegasus
Dated: 1/2024
This proposal is based on the above referenced drawings only. Work and/or details shown in other drawings/ specifications is
not included in this proposal.
2. This proposal is based on the following Soils Report:
Prepared By: Not Provided
Dated:
3. Unless provided for otherwise in this proposal, this proposal is valid for 30 days from the date of the proposal. If a contract
or other agreement is not executed within 30 days, then this proposal is subject to be reviewed for adjustment.
4. This work is based on a completion 20 days after a exectued Notice to Proceed, or an agreed project schedule as an
attachment to the contract jointly prepared by Owner and SDC.
Page 2 of 2
21
MARSH ROAD WIDENING AND ROUNDABOUT IMPROVEMENTS 2022-2023
Orange County, Florida.
OWNER INFORMATION DESIGNER
City of Winter Garden Jon Williams Pegasus Engineering
300 W. Plant Street City Manager EOR Fursan Munjedm, P.E.
Winter Garden, Florida, 34787 RFP # 080059 301 W State Road 434, Ste 309
JWilliams@cwgdn.com Winter Springs, FL 32708
407-656-4111 fursan@pegasusengineering.net
DETAIL OF WORK PERFORMED
Value $ 9,238,255
This multi-phase project included the widening of Marsh Road ( 3,300 lf) from West of Johns Lake Overlook Drive to East of
Avalon Road and a new roundabout at Johns Lake Overlook Drive. The work consists of pavement reconstruction and widening,
29,00 cy of earthwork, 4,200 lf of storm drainage, 1,500 lf of Type II Pond underdrain, 8,100 sf of permanent sheet pile wall with
concrete barrier & bullet rail, 20,000 sy of base & asphalt paving, curb & gutter, concrete sidewalks, brick pavers, sodding,
signing & pavement marking, and utility relocations / adjustments.
PREMIER HEAVY CIVIL CONTRACTOR
LAND CLEARING • UNDERGROUND UTILITY • GRADING • EARTHWORK • ROADWAYS
2544 Connection Point. Oviedo, FL 32765 | www.SDCFL.com | (407) 977-9898 22
WOLF BRANCH SINK DRAINAGE IMPROVEMENTS 2021
Lake County, Florida.
OWNER INFORMATION DESIGNER
Lake County BOCC Terry Scott Lake County Public Works
315 W. Main Street JScott@LakeCountyFL.gov
Tavares, Florida 32778 352-253-9024
DETAIL OF WORK PERFORMED
Value $ 272,729
This project is located in Mount Dora off Wolf Branch Road and involved the installation of underdrain and improved pond
bottom soils to aid in the recovery of two dry ponds in the Wolf Branch drainage basin. Other work associated with this project
included over-excavation of the pond bottom, placing clean fill, sodding and drainage construction.
PREMIER HEAVY CIVIL CONTRACTOR
LAND CLEARING • UNDERGROUND UTILITY • GRADING • EARTHWORK • ROADWAYS
2544 Connection Point. Oviedo, FL 32765 | www.SDCFL.com | (407) 977-9898 23
FIVE POINTS CONNECTOR ROAD & STORM WATER POND 2019-2020
Seminole County, Florida.
OWNER INFORMATION DESIGNER
Seminole County BOCC Steve Miller, P.E. Pegasus Engineering
1104 East 1st Street Smiller02@seminolecoiuntyfl.gov
Sanford, Florida, 32771 407-665-5674
DETAIL OF WORK PERFORMED
Value $ 5,550,505
The 15-acre site underwent specialized clearing using floating machinery, encompassing 109,000 cubic yards of excavation,
35,000 cubic yards of subsoil excavation, 600,000 square feet of geogrid installation, 34,000 linear feet of wick drains and a
temporary surcharge embankment, along with 2,100 linear feet of storm drainage. Additionally, 3,700 square yards of base and
asphalt paving were executed. Remarkably, the project was successfully concluded six months ahead of the scheduled
timeframe.
PREMIER HEAVY CIVIL CONTRACTOR
LAND CLEARING • UNDERGROUND UTILITY • GRADING • EARTHWORK • ROADWAYS
2544 Connection Point. Oviedo, FL 32765 | www.SDCFL.com | (407) 977-9898 24
OVIEDO ON THE PARK 2017-2019
City of Oviedo, Seminole County, Florida.
OWNER INFORMATION
A Public Private partnership development between
City of Oviedo PAC Land Development
Mayor Dominic Persampiere Mr. Tom Cavanaugh
1000 Alexandria Boulevard 730 Bonnie Brae Street
Oviedo, Florida 32765 Winter Park, Florida 32789
DETAIL OF WORK PERFORMED
Value $21,000,000 over the 4 Phase Project
New Construction of 7,256 linear feet of minor arterial roads from Alafaya Trail, E. Michell Hammock Rd to Oviedo Blvd.
in Seminole County, project included underground utilities, directional bores, MOT, dewatering, clearing, erosion control,
milling, stabilized subgrade, lime rock base, asphalt, demucking, embankment, curb, driveways, endwalls, retaining walls,
traffic signalization, hardscape, sidewalk and conduit. Project also included new 4 way intersection with traffic control
lights at the connection of E. Mitchell Hammock Road to City Plaza Way and two new turn lanes on Alafaya Trail and E.
Mitchell Hammock Road.
PREMIER HEAVY CIVIL CONTRACTOR
LAND CLEARING • UNDERGROUND UTILITY • GRADING • EARTHWORK • ROADWAYS
2544 Connection Point. Oviedo, FL 32765 | www.SDCFL.com | (407) 977-9898 25
Thank you for choosing Outdoor With It LLC. We hope to work with you in the future.
Sincerely,
Elizabeth Geraghty/Randall Geraghty X_____________________ X___________________
Owners/Operators Customer signature Print
www.Facebook.com/outdoorwithit/
X___________________ X_____________________
Outdoor With It LLC Date
Outdoor With It LLC
650 Lake Harney Rd
Geneva, Fl 32732
Outdoorwithit@gmail.com
321-303-2045
03/07/24
City of Winter Springs, Florida Project location
1126 East State Road 434 1533 & 1529 Graceful Doe Lp
Winter Springs, FL 32708 Winter Springs, FL 32708
Tuskawilla Crossings berm
Failure
Proposal
• Entrance to the pond and access for equipment will be between address 1529 Graceful
Doe Lp and 1533 Graceful Doe Lp
• We will be putting ground mats down between the houses for trucks/equipment to cross
between properties.
• Backfill of retention pond burm that washed out from overflow along the Cross Seminole
Trail with 70 dump truck loads at 18 Cubic yards per truck with truck tickets for each
load. Estimation of total cubic yards to be used is 1,260.
• Reform the bank by grading and compacting to match remaining existing bank on both
sides of the washout.
• Excavate trees that are falling into the berm washout and haul them away.
• Excavate grass and muck in berm washout and haul away.
• Install an estimated 18,800 sqft of Bahia sod in the washout area and where
trucks/equipment travel to and from berm blowout to the entrance of the pond from
street.
• Restoration between houses 1533 & 1529 St Augustine grass estimated 800sqft
• All damages and or restoration from trucks and or equipment between houses will be
restored after job is completed back behind the houses to its original look with before
and after pictures being taken.
• If there is any leftover dirt from my estimated 70 loads, we will spread and fill in the other
previous washout areas along the bank by 1533 &1529 houses.
• Curb and sidewalk between 1533 &1529 houses to be repaired after all equipment and
mats are off the job.
Any extra dirt and/or sod needed outside this proposal will be made in a change order to the
City of Winter Springs paid to Outdoor With It.
Estimated dirt and sod are based off the discussion between City of Winter Springs and
Outdoor With It while on the site visit.
Total Cost
$75,792.39
26
Tuskawilla Crossing - Bids Received February 29, 2024
Bidder
Southern Development and Construction
CL Green Inc.
Florida Site Services
Outdoor With It
27
Quoted Amount
$184,762.00
$135,000.00
$79,252.40
$75,792.39
28