HomeMy WebLinkAbout2023 10 23 Awards/Presentation 100 - Update on Tuskawilla Crossing Retention PondAWARDS AND PRESENTATIONS ITEM 100
CITY COMMISSION AGENDA | OCTOBER 23, 2023 REGULAR MEETING
TITLE
Update on Tuskawilla Crossing Retention Pond
SUMMARY
FUNDING SOURCE
RECOMMENDATION
Staff recommends the Commission receive the presentation from David Hamstra.
6
TUSKAWILLACROSSINGSSUBDIVISIONPOND1 REPAIR ANDREHABILITATIONCity Commission Briefing on October 23, 20237
Project OverviewThe permitted stormwater management system includes a total of five (5) wet detention stormwater ponds that discharge to wetlands and conservation areas identified on the subdivision plat as Tracts A, B-1, B-2, C, and D.The operation and maintenance phase of the stormwatermanagement system began on December 17, 2019 when District staff issued SJRWMD Permit 148395-3.This project pertains specifically to Pond 1, which is located south of State Road 434, and north and east of the Cross Seminole Trail.28
32021 AERIALLOCATION9
Project OverviewThe water quality volume provided within Pond 1 is recovered by a 6-inch diameter circular orifice that is connected to a proprietary Nutrient Removal Filtration System that was installed to address the District’s nutrient removal criteria for discharges to Lake Jessup. Overflow discharge from Pond 1 is conveyed to the adjacent wetland and conservation area (Tract B-1) by a broad crested concrete weir.Sometime in late August or early September 2023, a berm failure occurred on the north side of Pond 1 that resulted in a nearly vertical breach that rapidly drained the pond with significant soil loss and sediment deposition within the downstream wetland and conservation area (Tract B-1).Local rainfall stations indicate that a storm event with significant intensity occurred on September 8th.410
Project OverviewThe following deficiencies will need to be addressed as part of repairing and rehabilitating Pond 1, and it is very likely that additional deficiencies may also be discovered after engineering design commences.1. Repair and reconstruction of the berm breach. Berm reconstruction will also need to address under berm seepage into the wetland that appears on aerial photographs since at least January 2023, as well as other issues related to the drainage flow way that existed at this same location before the property was ever developed.2. Side slope erosion around the entire pond perimeter.3. Localized erosion of the pond berm and side slope caused by a roof and yard drainage system located at 1533 Graceful Doe Loop.4. Elevated pond control water level caused by the drawdown orifice and the Nutrient Removal Filtration System.511
Project Overview5. Damaged fiberglass skimmer for the broad crested concrete weir.6. Erosion potential between the broad crested concrete weir and the downstream wetland and conservation area (Tract B-1).7. Erosion and scour at the outlet ends of the three (3) storm pipes that discharge into Pond 1.8. Exposed storm pipe and joint along the Pond 5 outfall system just after the 90 degree turn along the south side of Pond 1.9. Horizontal sock drains that were left over from the original pond dewatering that have been exposed and ruptured by the rapid loss of water in Pond 1.612
DEFICIENCYPHOTOGRAPHS–BERMFAILURE, DOWNSTREAMSEDIMENTDEPOSITIONANDPRE-DEVELOPMENTDRAINAGEFLOWWAY13
814
915
1016
1117
12See the Enlarged ViewFor the Topographic SurveySPECIFICPURPOSESURVEY18
1324” RCPOutfall Pipe24” CMP Outfall Pipe(Pre‐development Flow Way)18” RCPOutfall PipeTract B‐1(Wetland and Conservation Area)TOPOGRAPHICSURVEY19
14Pond Berm was “cut” at this Location to Allow Site DrainageFrom Tuskawilla CrossingsDuring ConstructionTract B‐1(Wetland and Conservation Area)Pond 1TuskawillaCrossingsSEPTEMBER3, 201820
DEFICIENCYPHOTOGRAPHS–SIDESLOPEEROSIONAROUND THEENTIREPONDPERIMETER21
1622
1723
1824
DEFICIENCYPHOTOGRAPHS–EROSIONCAUSED BY AROOF ANDYARDDRAINAGESYSTEMLOCATED AT1533 GRACEFULDOELOOP25
201533 Graceful Doe LoopGutter Downspouts Connected to a Yard Drainage System26
21Pond 127
DEFICIENCYPHOTOGRAPHS–ELEVATEDPONDCONTROLWATERLEVEL28
23Pond 1FiberglassSkimmerDrawdownOrificeNutrient RemovalFiltration SystemTract B‐1(Wetland andConservation Area)Broad CrestedConcrete Weir29
2430
2531
2632
DEFICIENCYPHOTOGRAPHS–DAMAGEDFIBERGLASSSKIMMER FOR THEBROADCRESTEDCONCRETEWEIR33
28Pond 1FiberglassSkimmerDrawdownOrificeNutrient RemovalFiltration SystemTract B‐1(Wetland andConservation Area)Broad CrestedConcrete Weir34
2935
3036
DEFICIENCYPHOTOGRAPHS–EROSIONPOTENTIAL BETWEEN THEBROADCRESTEDCONCRETEWEIRANDTRACTB-1 (WETLAND ANDCONSERVATIONAREA)37
3238
33Area of Erosion PotentialPond 1FiberglassSkimmerNutrient RemovalFiltration SystemTract B‐1(Wetland andConservation Area)Broad CrestedConcrete Weir39
34Outfall Pipe from the Pond 1 Nutrient Removal Filtration SystemTract B‐1(Wetland andConservation Area)40
DEFICIENCYPHOTOGRAPHS–EROSION ANDSCOUR AT THEOUTLETENDS OFTHESTORMPIPES THATDISCHARGE INTOPOND141
36Inflow Pipe from Wooded Vine DrivePond 1ScourHole42
37Side Slope Erosion and ScourInflow Pipe from the Cross Seminole Trail43
38Inflow Pipe from Graceful Doe LoopScour HoleErosion Caused by a RearYard Drainage System Locatedat 1533 Graceful Doe Loop44
DEFICIENCYPHOTOGRAPHS–EXPOSEDSTORMPIPE ANDJOINTALONG THEPOND5 OUTFALLSYSTEM45
40Pond 1ScourHoleInflow Pipe from theCross Seminole TrailSide Slope Erosionand Scour HolePond 5 Outfall Pipe46
41Pond 5 Outfall PipeCross Seminole Trail47
DEFICIENCYPHOTOGRAPHS–EXPOSED ANDRUPTUREDHORIZONTALSOCKDRAINSLEFTOVER FROM THEORIGINALPONDDEWATERING48
43PerforatedHDPE Pipe49
Questions and Answers44David W. Hamstra, P.E., CFMStormwater Department Manager301 West State Road 434, Suite 309Winter Springs, Florida 32708Phone: 407-992-9160, ext. 309E-mail: david@pegasusengineering.net50