HomeMy WebLinkAbout2019 11 18 Informational 200 - Current Community Development Projects Summary • INFORMATIONAL AGENDA ITEM 200
oo , CITY COMMISSION AGENDA I NOVEMBER 18, 2019 1
1959
REGULAR MEETING
TITLE
Current Community Development Projects Summary
SUMMARY
CURRENT COMMUNITY DEVLEOPMENT PROJECTS SUMMARY
PROJECT NAME LOCATION LASTACTION ITEM CURRENTSTATUS
AITC Office 863 N US 17- N/A DA, Final Engineering &
Building 92 Aesthetic Plans are under
Staff review.
Beazer Homes Town Center- Special Exceptions approved DA, Engineering &
Senior (55+) West side of by City Commission on Aesthetic Plans to be
Condominium Tuskawilla, 8/13/18. prepared bythe
Project(The north of Community Workshop was developer.
Gatherings at Blumberg held on 10/17/19.
Winter Springs-108
Units)
Dream Finders Town Preliminary Engineering DA, Final Engineering &
Townhomes Center- approved by City Aesthetic Plans are under
(Winter Springs East side of Commission on 1/8/18. Staff review.
Townhomes) -114 Michael
Units Blake Blvd.
Insight Partners 300 W SR N/A Final Engineering Plans
Inc. (Office and 434 are under Staff Review.
Warehouse
Renovation)
Iriye Suites Live Town Center Special Exceptions& Aesthetic Plans are
Work Community Development Agreement under Staff review.
approved by City
Commission on 1/28/19.
Northern Oaks:35 North side of Final Engineering &Waivers Site work complete.
Single-Family Homes SR 434, East approved 03/13/17.Aesthetic Single-Family Homes are
by Dream Finders of SR 417 Review approved 04/9/18. under construction.
Homes
Waiver request Site Acceptance is
recommended for approval pending.
by Planning and Zoning Waiver Request.
Board 10/02/19
Southern Oaks:54 West of Final Engineering,Aesthetic Site work complete.
single-family homes DeLeon St.& Review,& Development Single-Family Homes are
North of SR Agreement approved on under construction.
434
6/22/15. Commission accepted
site work on 8/14/17.
The Studios at Vistawilla Community Workshop was DA& Final Engineering
Tuscawilla Drive held on 07/19/19 Plans are under Staff
review.
Tuskawilla Town Center Final Engineering, Site work complete.
Crossings:379 Development Agreement& Single-Family Homes
Single-Family Aesthetics approved by City under construction.
Homes
Commission on 4/24/17. Plat
approved 8/13/2018. Phase 1
and Phase 2 Site work
approved by City
Commission.
Winter Springs E SR 434 Community Workshop was DA, Final Engineering
Medical Office held on 08/13/19 &Aesthetic Plans are
under Staff review.
Winter Springs Town Center Final Engineering, Site work under
Retirement Aesthetic Review,& construction.
Residence (Hawthorn Development Agreement
ILF):144 independent approved by City
living suites Commission on 1/22/18.
Winter Springs Town Center Final Engineering&Aesthetic Developer to schedule
Town Center Plans approved by City preconstruction
Retail Building Commission on 6/10/2019. meeting prior to
(Ocean Bleu) starting work.
Wendy's Town Center Community Workshop to be DA, Final Engineering &
scheduled. Aesthetic Plans are under
Staff review.
For more information please click the link below:
City of Winter Springs Community Development Projects List/Locations
RECOMMENDATION
Staff recommends the City Commission receive and review the information provided.
INFOPMATIONAL AGENDA ITEM 200