HomeMy WebLinkAbout2019 09 23 Informational 200 - Current Development Projects Summary INFORMATIONAL AGENDA ITEM 200
1959
CITY COMMISSION AGENDA I SEPTEMBER 23, 2019 1 REGULAR
MEETING
TITLE
Current Development Projects Update
SUM MARY
PROPOSED DEVELOPMENT PROJECTS
PROJECTNAME LOCATION LASTACTION ITEM CURRENTSTATUS
AITC Office Building 863 N US 17-92 N/A Final Engineering &
Aesthetic Plans are
under Staff review.
Winter Springs Medical ESR 434-West N/A Final Engineering
Office of Hacienda Dr. Plans are under Staff
review.Aesthetic
Plans are being
prepared.
Beazer Homes Senior Town Center- Special Exceptions Engineering &
(55+)Condominium West side of approved by City Aesthetic Plans to be
Project(The Gatherings Tuskawilla,north Commission on 8/13/18. prepared by the
at Winter Springs-108 of Blumberg developer.
Units)
Iriye Suites Live-Work Town Center Special Exceptions& Final Engineering
Community Development Plans are being
Agreement approved prepared by the
by City Commission on developer.Aesthetic
1/28/19. Plans are under Staff
review.
Wendy's Town Center N/A Final Engineering
Plans and Aesthetic
Plans are under staff
review.
Dream Finders Town Center- Preliminary Final Engineering and
Townhomes(Winter East side of Engineering approved Aesthetic Plans are
Springs Town homes) -114 Michael Blake by City Commission on under Staff review.
Units Blvd. 1/8/18.
The Studios at Tuscawilla Vistawilla Drive N/A Final Engineering
Plans are under Staff
review.A Community
Workshop was held
on J u ly 19,2019.
Insight Partners, Inc 300 W SR 434 N/A Final Engineering
Office and Warehouse Plans are under Staff
Renovation review.
APPROVED DEVELOPMENT PROJECTS/
UNDER CONSTRUCTION
PROJECTNAME LOCATION LASTACTION ITEM CURRENTSTATUS
Winter Springs Town Final Engineering &Aesthetic Developer to schedule
Town Center Center Plans approved by City preconstruction
Retail Building Commission on 6/10/2019. meeting prior to
(Ocean Bleu) starting work.
Tuskawilla Town Final Engineering, Site work complete.
Crossings:379 Center Development Agreement& Homes under
single-family Aesthetics approved by City construction.
homes
Commission on 4/24/17. Plat
approved 8/13/2018. Phase
and Phase 2 Site work
approved by City Commission.
Hawthorn ILF Town Final Engineering, Site work under
(Winter Springs Center Aesthetic Review,& construction.
Retirement Development Agreement
Residence):144 approved by City
independent Commission on 1/22/18.
living suites
Northern Oaks: North side Final Engineering &Waivers Site work under
35single-family of SR 434, approved by City Commission construction. Building
homes by Dream East of SR on 3/13/17. Preconstruction permits issued.
Finders Homes 417 meeting held 10/17/17.
Aesthetic Review approved by
City Commission on 4/9/18. Plat
is recorded.
Southern Oaks: West of Final Engineering,Aesthetic Site work complete.
54single-family DeLeon St. Review,&Development Homes under
homes & North of Agreement approved on construction.
SR 434 6/22/15. Plat is recorded.City
Commission accepted site
work on 8/14/17.
RECOMMENDATION
Staff recommends the City Commission receive and review the information
provided.
INFOPMATIONAL AGENDA ITEM 200
F
-`rY 4a
1;Lm d
jv F,
..
iJ 5 •3 v7
41 CJ
!r
N�,gf '.•-• $"�' �*"a�lb ,yh � S � ,t '�',".!,.. yrs�..
'w 7
04.
1' ;; ra -
�.. --
�4