Consent Agenda Item 301 from the February 25, 2019 City Commission meeting
authorized the purchase and electrical installation of a 175KW Generator at Police
Headquarters for Emergency Management purposes. The original request was
approved for $200,000. Although the cost of the Generator was known, the bids
for electrical installation were still being researched.
The cost for the Generator from Ping Power Systems is $92,100.90 (piggybacking
off the Florida State Contract Bid #2210100-15-1). Staff obtained three quotes for
Generator installation. The lowest cost for Generator installation resulted in
$118,723.00 by Computer Power Systems, Inc. The combined cost of the Generator
and installation is $210,823.90. In addition, a 5% contingency of $10,541.20 is
requested for any increase in scope or unknown conditions during installation. This
brings the total project cost (Generator, installation, and 5% contingency) to
$221,365.10.
RECOMMENDATION
Staff recommends that the City Commission authorize additional funding in the
amount of $21,365.10 to complete the installation of the 175KW Generator at Police
Headquarters for Emergency Management purposes.
Exhibit 1
Ring Powerx OLYMPIAN" `
GENERATORS
i— — — _:
Your North and Central Florida Caterpillar Dealer
ST.AUGUSTINE TALLAHASSEE OCALA ORLANDO TAMPA
500 World Commerce Prkwy 4752 Capital Circle NW 6202 N US 301/441 9901 Ringhaver Dr. 9797 Gibsonton Dr
St.Augustine,FL 32092 Tallahassee,FL 32303 Ocala,FL 34475 Orlando,FL 32824 Riverview,FL 33569
904-737-7730 850-562-1622 352-732-4600 407-855-6195 813-671-3700
SALES SERVICE PARTS LEASING RENTALS
QUOTATION./ SALES AGREEMENT ! SECURITY AGREEMENT
DATE: 12/28/18 QUOTATION NO: MB18-0021
CUSTOMER NAME: City of Winter Springs ESTIMATED SHIPPING LEAD TIME: 14-16 weeks
ADDRESS: SHIPPING VIA/FOB: Jobsite
CITY/STATE/ZIP: FL ESTIMATED SUBMITTAL LEAD TIME: 3 weeks
CONTACT: JOBSITE ADDRESS:
PHONE: CITY/STATE/ZIP: FL
PROJECT NAME: City Hall
TERMS:Full payment is due from buyer within 10 days of delivery or pickup of the equipment.
DESCRIPTION OF MATERIAL UNIT PRICE EXTENSION
Please ensure quote meets your expectations.
Pricing per Florida Department of Management Services"Construction and
Industrial Equipment"Contract No;22101000-15-1 July 1,2015-June 30,2018
Group 15 Power Generators
Caterpillar Base Equipment 20%MSRP Discount
NAC151 P-D175 60 HZ,208V Generator MSRP$34,850.00 $27,880.00
CERTESE-EPA Stationary Emergency
STANDBY-Standby Power Application
UL2200-2200 Listing MSRP$366.00 $292.80
OGNSEAA-LC5014H 60 HZ SE Generator MSRP$9,380.00 $7,504.00
OEM Options 10%MSRP Discount
WPIC-Weatherproof White Enclosure MSRP$7,095.00 $6,450.00
1000 gallon sub base fuel tank MSRP$9,913.20 $9,012.00
FSS-Fuel Level Alarms MSRP$232.00 $208.80
Quotation Accepted By: Date: Tax No.:
Customer: Salesman's Signature:Mark Barbarulo
Mark Barbarulo,EPG Sales.Central Florida
TERMS
• This offer to sell is made subject to buyer's acceptance within ten(10)days from this date(noted above).
• All quoted prices are subject to change without notice.Those in effect on the date of shipment shall prevail.
• Subject to credit approval.
• Used equipment is subject to prior sale.
• A 25%restocking fee will be assessed for all canceled orders or returned materials.
• No retainage to be withheld.Ring Power Systems is an equipment supplier and is not a sub-contractor.Our terms are Net 10 days.
• No sales tax is included.
• Buyer grants to seller a security interest in all equipment as described in this agreement until such time as payment is made in full
in accordance with the terms and conditions of this agreement and in accord with the seller's credit application.
• Ring Power requires a purchase order to secure this sales agreement.
Page 1 of 3
DESCRIPTION OF MATERIAL UNIT PRICE EXTENSION
CPOB-Control Panel Options Box MSRP$507.00 $456.30
WSS1-Low Coolant Shutdown Circuit MSRP$169.00 $152.10
CBR8001-800A Breaker MSRP 2,523.23 $2,271.00
SHTAUX-Shunt Trip&Auxiliary Contacts MSRP$158.00 $142.20
IVR12-Permanent Magnet Excitation MSRP$1,159.00 $1,043.10
PBC10NU-Battery Charger 10A NFPA MSRP$698.00 $628.20
WHH-Coolant Heater MSRP$226.00 $203.40
Accessories 5%MSRP Discount
Asco ATS-One(1)new Asco ATC300 Service Entrance Rated 1600A,208V,3-pole,
NEMA3R MSRP$23,745.75 $22,615.00
800A 208V Trystar Generator Docking Station
ETL Listed to UL 1008 Standards
Main 800amp breaker
UL 50 Listed MSRP$8,358.00 $7,960.00
Dealer Labor for Load Test Per DMS Contract 10111-017
NFPA 110 Load Test 8 hours @$104.00 per hour. $832.00
Freight from factory $2,650.00
Freight to jobsite. $1,800.00
Total NET for above $92.100.90
EXCEPTIONS:
Sizing of the generator is based off the power bill,
Startup will be done during normal business hours
mon-Fri, Electrical shut downs will be done on the
weekend,
No stairs included
NOTE:
1. The above price includes start-up, testing, and customer training.
2. Installation, labor, conduit, wire, equipment off loading, anchor bolts, pad, fuel or fuel piping is included.
3. No third party testing or NETA testing included and is by others.
4. No sales tax included
5. Startup work to be done during normal business hours 8am to 4pm.
6. Proposal is based on information supplied by the Customer.
7. Generators that come with an 800 amp breaker or larger are supplied with buss bar, Lugs are by others.
8. No specifications, drawings, or diagrams were received or reviewed. General exception is taken to any
other specifications and drawings not available at time of quotation. Equipment supplied will be limited to
that described in this proposal.
9. Ring Power will be supplying equipment as described in the attached documentation.
10. For fuel tanks over 550 Gallons, it is the Contractor or Owners responsibility to notify the appropriate State,
and/or local regulatory agencies prior to delivery of the fuel storage tank so that it can be inspected prior to
fueling. The FDEP Registration form will be provided in the Ring Power Submittal. Per FDEP Breach of
Page 2 of 3
r
DESCRIPTION OF MATERIAL UNIT PRICE EXTENSION
Integrity Testing Guidance, tanks will ship from the factory with a vacuum/gauge installed. On-site testing is
not included.
11 Ring Power will not release equipment for production until we have received the signed sales
agreement and signed and approved submittal from our customer. This is done to insure that we
are providing quality equipment that fits our customer's needs. If you need any assistance, please
contact your sales representative.
Thank you for considering Ring Power Systems for your generator needs
Mark Barbarulo
Ring Power Systems, Generator Sales Central Florida,
407-472-6231 Office-407-472-6271 Fax-407-383-5840 Cell
Mark.barbarulo@ringpower.com
Page 3 of 3
. �Ow computtar pcovv4er syr#
3421 State Road 419 Exhibit 2
Winter Springs, FL 32708
www.cpsfl.com
Ph: 407-327-7373 Fx: 407-327-7333
June 11, 2019
Len Hartman
City of Winter Springs lhartmangwinterspringsfl.org
1126 East S.R. 434 (407) 327-7580
Winter Springs, FL 32708 Proposal # 061119RK01
RE: Winter Springs Police Dept. Generator Installation
Dear Mr. Hartman:
Thank you for your interest in our products and service. As per your request, the
following quotation is submitted for your review to provide electrical installation of a
175KW generator and 1600A Automatic Transfer Switch at the Police Department
complex.
Pricing includes:
- Set and place new 1600 amp ATS.
- Remove existing generator(leave onsite,customer to utilize elsewhere).
- Offload and place new 175KW generator in same location as old generator.
- Provide and install 800 amp feed from generator to new ATS. Old ATS will be re-purposed as a
junction box.
- Intercept feed running from utility transformer to MDP and re-route to new ATS.
- Provide new 1600A feed from new ATS back to MDP.
- Provide control,battery charger,and block heater circuits run to new generator.
- Provide engineered drawings and permit as required.
- Coordinate power outage with Duke Energy during ATS cut-over.
- All critical transfer work to be performed during non-peak hours for customer.
- CPS technician onsite during generator start-up.
Price, System Installation ............................. $ 118,723.00
Items Not Included:
- Applicable state sales tax
- Generator
- ATS
- Fuel
- Wall modifications to fit generator(if needed)are not included.
- Any variation from our designed scope of work will be subject to price change.
Pricing is valid for 45 days. Please let me know if you have any questions. We look
forward to working with you on this project.
Sincerely, Accepted by:
(Print)
Rick Kuzmick
rickkgcp sfl.com (PO#)
Exhibit 3
COMMISSION AGENDA
Informational
ITEM 301 Consent x
Public Hearings
Regular
February 25, 2019 KS SB
Regular Meeting City Manager Department
REQUEST:
Finance and Administrative Services Requesting Approval to Piggyback off the Florida
State Contract Bid#2210100-15-1, for the purchase of one (1) Caterpillar 175KW
Generator and installation, for Police Headquarters Emergency Management purposes.
SYNOPSIS:
The purpose of this Agenda Item is to request approval for the purchase of one (1)
Caterpillar 175KW Generator for Police Headquarters Emergency Management from
RingPower Corporation and hire an installer at a cost not to exceed of$200,000.
CONSIDERATIONS:
This item is needed to provide permanent emergency power at key locations throughout the
City. The Police Headquarters' is the primary emergency operations center. During an
emergency it is imperative that the network and phone equipment continue to function. The
existing Police generator was purchased in 2000 and is functional. However, parts are no
longer available for repairs if they should be necessary.
The new generator will be installed at the police building within the next 180 days, if
approved. This approval is required due the long lead time for the physical generator not
the installation.
The Florida State Contract has already bid this item under Bid#2210100-15-1 for a total
cost not to exceed $200,000. This is the cost for equipment and
installation. Qualified electricians are being research and priced.
Consent 301 PAGE 1 OF 2-February 25,2019
FISCAL IMPACT:
This item is budgeted for Fiscal 2019 ($212,000). The total cost will not exceed $200,000
for equipment and installation.
COMMUNICATION EFFORTS:
This Agenda Item has been electronically forwarded to the Mayor and City Commission,
City Manager, City Attorney/Staff, and is available on the City's Website, LaserFiche, and
the City's Server. Additionally, portions of this Agenda Item are typed verbatim on the
respective Meeting Agenda which has also been electronically forwarded to the individuals
noted above, and which is also available on the City's Website, LaserFiche, and the City's
Server, has been sent to applicable City Staff; Media/Press Representatives who have
requested Agendas/Agenda Item information, Homeowner's Associations/Representatives
on file with the City, and all individuals who have requested such information. This
information has also been posted outside City Hall, posted inside City Hall with additional
copies available for the General Public, and posted at six (6) different locations around the
City. Furthermore, this information is also available to any individual requestors. City Staff
is always willing to discuss this Agenda Item or any Agenda Item with any interested
individuals.
RECOMMENDATION:
Staff Recommends that approval be granted to piggyback off Florida State bid #2210100-
15-1, for the purchase of one (1) Caterpillar 175KW Generator from RingPower
Corporation and hire an installer in a combined amount not to exceed $200,000.
Additionally, authorizing the City Manager and City Attorney to negotiate, prepare
and execute any and all applicable contract documents.
ATTACHMENTS:
None.
Consent 301 PAGE 2 OF 2-February 25,2019