HomeMy WebLinkAbout2019 05 13 Consent 303 - Tuskawilla Crossings Phase 2 Final Site Acceptance CONSENT AGENDA ITEM 304
1959
CITY COMMISSION AGENDA I MAY 13, 2019 1 REGULAR MEETING
TITLE
Tuskawilla Crossings Phase 2 Final Site Acceptance
SUMMARY
The Tuskawilla Crossings project consists of a 379-unit single family residential
subdivision by Lennar Homes. The project is located southeast of SR 434 and
Tuskawilla Road.The project area is approximately 133 acres and includes a central
amenity area and a commercial out-parcel.
This agenda item is for the conditional acceptance of the Phase 2 site
improvements. The site work has been constructed in substantial compliance
with the Final Engineering Plans approved by the City Commission, except as
noted on the attached punch-list, Exhibit A. At the November 11, 2018 City
Commission meeting, the City Commission approved the Tuskawilla Crossings
Phase 1 Site Acceptance. Phase 2 is the final portion of this project containing
public improvements.
Applicable Code:
Section 9-178. Required Improvements to be completed prior to building on lots;
exceptions.
(c) Where the building official has an authoritative method of assurance
that the improvements will be completed in accordance with approved
plans, such as withholding occupancy, the building official may issue
building permits upon advising the developer that all of the partial
occupancy will be restricted until satisfactory completion of the
improvements has been accomplished.
(d) ...Certificates of occupancy will not be issued until all improvements are
accepted by the City Commission.
RECOMMENDATION
Staff recommends that the City Commission validate the Staff recommendation
finding the Phase 2 portion of the Tuskawilla Crossings site work to be built in
substantial accordance with the Final Engineering plans, subject to satisfactory
completion of the remaining open punch-list items.
Incotip-orsCrd
1959
City of Winter Springs
Project Closeout List for City Commission Final Site Approval
Tuskawilla Crossings—Phase 2
1. Complete all sitework and pass the final engineering inspection. Contact Bryant Smith,
P.E. at 407-327-8979 to schedule a preliminary and/or final engineering inspection. The
final inspection will occur after receipt of the record drawings from the engineer-of-
record.
2. Obtain Approvals from all City Departments
Additional items to be completed prior to closeout (this is not a complete punchlist):
• Final lift of asphalt
• Final striping
• Complete lift station enclosure
• Complete street lighting
• Site cleanup