TITLE
Current Community Development Projects Summary
SUMMARY
CURRENT COMMUNITY DEVLEOPMENT PROJECTS SUMMARY
PROJECT LOCATION LASTACTION ITEM CURRENTSTATUS
NAME
AITC Office Building 863 N US 17-92 N/A DA, Final Engineering &
Aesthetic Plans are
under Staff review.
Beazer Homes Town Center- SE approved by City DA, Preliminary
Senior (55+) West side of Commission on 8/13/18. Engineering,Aesthetic
Condominium Tuskawilla,north Plans,and Waivers are
Project: of Blumberg Community Workshop under Staff review.
was held on 10/17/19.
(The Gatherings at
Winter Springs-
108 Units)
Chase Bank Town Center Community Workshop CUP is under Staff
was held on 02/20/20 review.
Dream Finders Town Center- Preliminary Engineering Site Work under
Townhomes East side of approved by City Construction.
(Winter Springs Michael Blake Commission on 1/8/18.
Townhomes): Blvd.
DA, Final Engineering,
114 Single-Family Waivers, &Aesthetic
(Attached) Units Review approved by the
City Commission on
12/09/2019
Insight Partners 300 W SR 434 N/A Engineering Plans are
Inc. (Office & under Staff Review.
Warehouse
Renovation)
Iriye Suites Live Town Center SE & DA approved by Aesthetic Plans are
Work Community City Commission on under Staff review.
1/28/19.
Northern Oaks: North side of Final Engineering & Site workcomplete.
35 Sin le-Famil SR 434, East of Waivers approved
g Y Single-Family Homes are
Homes by Dream SR 417 03/13/17.Aesthetic under construction.
Finders Homes Review approved
04/9/18. Site acceptance
Waiver approved by City complete (01/13/2020).
Commission on
11/18/2019
Southern Oaks: West of DeLeon DA, Final Engineering, Site work complete.
54sin le-famil St.& North of SR Waivers,&Aesthetic
g Y 434 Single-Family Homes are
homes Review approved on under construction.
6/22/15. Commission
accepted site work on Site acceptance
8/14/17. complete.
The Studios at Vistawilla Drive Community Workshop Final Engineering,
Tuscawilla was held on 07/19/19. Aesthetic, &Waivers
are under Staff Review.
DA approved by the
Planning &Zoning
Board on 12/04/2019.
DA approved by the City
Commission on
01/13/2020.
Tuskawilla Town Center DA, Final Engineering, Site work complete.
Crossings: Waivers, &Aesthetics Single-Family Homes
379 Single- approved by City under construction.
Family Homes Commission on 4/24/17.
Site acceptance
Plat approved 8/13/2018. complete.
Phase 1 and Phase 2 Site
work approved by City
Commission.
Winter Springs E SR 434 Community Workshop DA, Final
Medical Office was held on 08/13/19 Engineering &
Aesthetic Plans are
under Staff review.
Winter Springs Town Center DA, Final Site work under
Retirement Engineering,Waivers, construction.
Residence &Aesthetic Review
(Hawthorn ILF): approved by City
Commission on
144 independent 1/22/18•
living suites
Winter Springs Town Center Final Engineering & Preconstruction
Town Center Aesthetic Plans Meeting Pending.
Retail Building approved by City
(Ocean Bleu) Commission on
6/10/2019.
Wendy's Town Center Community Workshop Site Work Pending.
was held on 12/17/19.
DA, Final Engineering &
Aesthetic Review
approved by the
Planning and Zoning
Board on 02/05/2020
and City Commission on
02/10/2020.
For more information, please click the link below:
City of Winter Springs Community Development Projects List/Locations
N otes:
DA= Development Agreement
CUP = Conditional Use Permit
SE = Special Exception
RECOMMENDATION
Staff recommends the City Commission receive and review the information
provided.