CURRENT COMMUNITY DEVLEOPMENT PROJECTS SUMMARY
PROJECT NAME LOCATION LAST ACTION ITEM CURRENTSTATUS
AITC Office Building 863 N US 17-92 N/A DA, Final Engineering &
Aesthetic Plans are under Staff
review.
Chase Bank Town Center Community Workshop was Final Engineering &Aesthetic
held on 02/20/20 Plans are under Staff review.
CUP and DA approved by
the City Commission on
11/16/20.
Dream Finders Town Center- Preliminary Engineering Single-Family Homes Building
Townhomes East side of approved by City Permits under Staff Review.
(Seminole Crossing): Michael Blake Commission on 1/8/18.
Site work complete.
114 Single-Family Blvd. DA, Final Engineering,
(Attached) Units Waivers, &Aesthetic Review Site acceptance pending.
approved by the City
Commission on 12/09/2019.
Final Plat approved by the
City Commission on
09/28/20.
Iriye Suites Live Town Center SE & DA approved by City Final Engineering and Aesthetic
Work Community Commission on 01/28/19 Plans are pending.
Northern Oaks: North side of Final Engineering &Waivers Single-Family Homes are under
35 Single-Family SR 434, East of approved 03/13/17.Aesthetic construction.
Homes by Dream SR 417 Review approved 04/9/18. Site acceptance complete on
Finders Homes Waiver approved by City 01/13/20.
Commission on 11/18/19
Southern Oaks: West of DA, Final Engineering, Site acceptance complete.
54single-family homes DeLeon St.& Waivers,&Aesthetic Review Single-Family Homes were
North of SR approved on 06/22/15. complete as of 11/2020
434 Commission accepted site
wo r k o n 08/14/17.
The Studios at Vistawilla Drive Community Workshop was Final Engineering,Aesthetic, &
Tuscawilla held on 07/19/19. Waivers are under Staff Review.
DA approved by the City
Commission on 01/13/20.
Tuskawilla Crossings: Town Center DA, Final Engineering, Single-Family Homes under
379 Single-Family Waivers, &Aesthetics construction.
Homes approved by City Site acceptance complete.
Commission on 04/24/17.
Plat approved 08/13/18.
Phase 1 and Phase 2 Site
work approved by City
Commission.
2
Winter Springs E SR 434 Community Workshop was Site work started.
Medical Office held on 08/13/19
DA, Final Engineering &
Aesthetic Plans approved by
the City Commission on
11/16/20
Winter Springs SW Corner of Community Workshop was Site work started.
Marketplace SR 434 and held on 05/28/20
Tuskawilla DA, Final Engineering,
Five (5) Building Road g g'
Commercial Waivers, &Aesthetic Review
Shopping Center approved by the City
Commission on 02/22/2021.
Winter Springs Town Center DA, Final Engineering, Site work complete.
Retirement Residence Waivers,&Aesthetic Review Suites under construction.
(The Savoy): a pproved by City
144 independent Commission on 01/22/18.
suites
Winter Springs Town Town Center Final Engineering & Preconstruction Meeting
Center Retail Building Aesthetic Plans approved by Pending.
(Ocean Bleu) City Commission on 06/10/19.
Wendy's Town Center Community Workshop was Building under construction.
held on 12/17/19. Site work complete.
DA, Final Engineering & Site acceptance pending.
Aesthetic Review
approved by the
Planning and Zoning
Board on 02/05/2020 and
City Commission on
02/10/20.
For more information please click the link below:
City of Winter Springs Community Development Projects List/Locations
Notes: ADU = Accessory Dwelling Unit
CUP = Conditional Use Permit
DA= Development Agreement
PZB = Planning and Zoning Board
SE = Special Exception
3