CURRENT DEVELOPMENT PROJECTS SUMMARY
PROJECT NAME LOCATION LAST ACTION ITEM CURRENT STATUS
AITC Office Building 863 N US 17-92 N/A *DA,Final Engineering&Aesthetic
Plans are under Staff review.
Chase Bank Town Center Community Workshop was held Building Permits approved as of 02/25/22.
Adjacent to Wendy's. on 02/20/20 Chase Bank is under construction.
CUP and DA approved by the CC
on 11/16/20.
DA,Final Engineering,Waiver,
&Aesthetic Plans approved by
the CC 10/25/2021.
Dream Finders Town Center DA,Final Engineering, Waivers, Single-Family Homes are under
Townhomes(Seminole &Aesthetic Review approved by construction.
Crossing) East side of Michael the CC on 12/09/2019.
Blake Blvd. Final Plata roved b the CC on
114 Single-Family pp Y
Homes(Attached) 09/28/20.
Site acceptance complete on
07/12/2021.
Hickory Grove Town Center A Non-Binding review was held Preconstruction Meeting completed on
Townhomes Northeast of Bear at the CC on 02/25/2021. 06/01/22.
132 Single-Family Springs Drive and Community Workshop was held
Homes(Attached) Blumberg Blvd. on 08/26/2021.
DA,Final Engineering, Specimen
Tree Removal,Waivers,
Variance,&Aesthetic Review
PZB recommended approval on
02/10/22.
Waivers 1 &2,Variance,&
Aesthetic Review approved by
CC on 03/14/22.
DA,Final Engineering, Specimen
Tree Removal, &Waiver 3
approved by CC on 05/23/22.
Iriye Suites Live Work Town Center SE&DA approved by CC on Special Exception(SE)expired on
Community 150 Tuskawilla Rd. 01/28/19. 01/30/22.
Living Life Development West Side N/A Final Engineering is under Staff review.
(ILF) North Side of W SR
434,north of Sun Lake
Plaza.
The Studios at Tuscawilla Vistawilla Dr. Community Workshop was held Final Engineering,Aesthetic, &Waivers
Adjacent to Seminole on 07/19/19. are under staff review.
Trail Animal Hospital DA approved by the CC on
01/13/20.
Page 1&2
t9i9
Winter Springs Town Center Community Workshop was held Fifth Third Bank,DA,Final
Marketplace SW Corner of SR on 05/28/20. Engineering&Aesthetic Plans are
Five(5)Building
434 and DA,Final Engineering, Specimen under Staff review.
Commercial Shopping Tuskawilla Rd. Tree Removal, Waivers,&
Center Aesthetic Review approved by
the CC on 02/22/2021.
Aesthetic Plans for Chipotle
approved by the CC on 08/09/21.
Partial Site Acceptance complete
(Dollar Tree,Crunch Fitness,and
Dental Office)on 02/14/22.
Dollar Tree CO issued 02/22.
Dental Office CO issued 03/22.
Crunch Fitness CO issued 04/22.
Partial Site Acceptance(Aldi)
approved by the CC on 06/13/22.
Aldi CO issued 06/22.
Partial Site Acceptance
(Chipotle)approved by the CC
on 06/27/22.
Chipotle CO issued 07/22.
Retail Building(Ocean Bleu) Town Center Final Engineering&Aesthetic *Preconstruction Meeting
Adjacent to Starbucks Plans approved by CC on
06/10/19.
For more information please click the link below:
City of Winter Springs Community Development Projects List/Locations
Notes: ADU—Accessory Dwelling Unit
CC=City Commission
CO=Certificate of Occupancy
CUP=Conditional Use Permit
DA=Development Agreement
PZB=Planning and Zoning Board
SE=Special Exception
*Currently Inactive