HomeMy WebLinkAbout2022 03 14 Informational 200 - Current Development Projects Summary + , INFORMATIONAL AGENDA ITEM 200
CITY COMMISSION AGENDA I MARCH 14, 2022 REGULAR MEETING
TITLE
Current Development Projects Summary
SUMMARY
Staff is advising the City Commission of the status of current development
projects within the City.
RECOMMENDATION
No action required.
1
1959
CURRENT DEVLEOPMENT PROJECTS SUMMARY
PROJECT NAME LOCATION LAST ACTION ITEM CURRENT STATUS
AITC Office Building 863 N US 17-92 N/A DA,Final Engineering&Aesthetic Plans
are under Staff review.
Chase Bank Town Center Community Workshop was held Building Permits approved as of 02/25/22.
Adjacent to Wendy's.
on 02/20/20
CUP and DA approved by the CC
on 11/16/20.
DA,Final Engineering,Waiver,
&Aesthetic Plans approved by
the CC 10/25/2021.
Dream Finders Town Center DA,Final Engineering,Waivers, Single-Family Homes are under
Townhomes(Seminole &Aesthetic Review approved by construction.
Crossing): East side of Michael the CC on 12/09/2019.
114 Single-Family Blake Blvd. Final Plat approved by the CC on
Homes(Attached) 09/28/20.
Site acceptance complete on
07/12/2021.
Hickory Grove Town Center A Non-Binding review was held DA,Final Engineering,Waivers,
Townhomes at the CC on 02/25/2021. Variance,&Aesthetic Review
Northeast of Bear scheduled for CC on 03/14/22.
132 Single-Family Springs Drive and Community Workshop was held
Blumberg Blvd. on 08/26/2021.
Homes(Attached) g
DA,Final Engineering,Waivers,
Variance,&Aesthetic Review
PZB recommended approval on
02/10/22.
Iriye Suites Live Work Town Center SE&DA approved by CC on *Final Engineering and Aesthetic Plans
Community 01/28/19.
150 Tuskawilla Rd.
The Studios at Tuscawilla Vistawilla Dr. Community Workshop was held Final Engineering,Aesthetic,&Waivers
Adjacent to Seminole on 07/19/19. are under staff review.
Trail Animal Hospital DA approved by the CC on
01/13/20.
Tuskawilla Crossings: Town Center DA,Final Engineering,Waivers, *8 Single-Family lots remaining.
379 Single-Family SE Side of SR 434 &Aesthetics approved by CC on
Homes(detached) and Tuskawilla Rd. 04/24/17.Plat approved 08/13/18.
Site acceptance complete.
371 Single-Family Homes are
complete as of 10/2021.
Page 1 of 2
2
tncN*Mnb
1959
Winter Springs Medical 403 E SR 434 Community Workshop was held Site Acceptance Tentatively Scheduled
Office(Chau Medical) on 08/13/19. for City Commission 03/14/22.
DA,Final Engineering&
Aesthetic Plans approved by the
CC on 11/16/20.
Winter Springs Town Center Community Workshop was held Aldi,Crunch Fitness,Dental Office,and
Marketplace SW Corner of SR on 05/28/20. Chipotle Buildings are under
i
i
l E
Final d DA
an , nangneerng, construction.
Five(5)Building 434 Waivers,
Commercial Shopping Tuskawilla Rd. &Aesthetic Review approved by
Center the CC on 02/22/2021.
Aesthetic Plans for Chipotle
approved by the CC on 08/0
Partial Site Acceptance complete
(Dollar Tree,Crunch Fitness,and
Dental Office)on 02/14/22.
Dollar Tree CO was issued on
02/15/22.
Winter Springs Retirement Town Center DA,Final Engineering,Waivers,& The Savoy CO was issued on
Residence(The Savoy): 80 Michael Blake Aesthetic Review approved by CC 02/18/22.144 independent suites Blvd. on 01/22/18.
Site Acceptance complete on
02/14/22.
Retail Building(Ocean Bleu) Town Center Final Engineering&Aesthetic *Preconstruction Meeting
Adjacent to Starbucks Plans approved by CC on
06/10/19.
For more information please click the link below:
City of Winter Springs Community Development Projects List/Locations
Notes: ADU=Accessory Dwelling Unit
CC—City Commission
CO—Certificate of Occupancy
CUP—Conditional Use Permit
DA—Development Agreement
PZB—Planning and Zoning Board
SE—Special Exception
*Currently Inactive
Page 2 of 2