Current Development Projects Summary
SUMMARY
Staff is advising the City Commission of the status of current development
projects within the City.
RECOMMENDATION
No action required.
5
1954
CURRENT DEVLEOPMENT PROJECTS SUMMARY
PROJECT NAME LOCATION LAST ACTION ITEM CURRENT STATUS
AITC Office Building 863 N US 17-92 N/A DA,Final Engineering&Aesthetic Plans
are under Staff review.
Chase Bank Town Center Community Workshop was held Building Permits under review.
on 02/20/20
CUP and DA approved by the CC
on 11/16/20.
DA,Final Engineering,Waiver,
&Aesthetic Plans approved by
the CC 10/25/2021.
Dream Finders Town Center-East Preliminary Engineering Site work complete.
Townhomes(Seminole side of Michael Blake approved by CC on 1/8/18.
Crossing): Site acceptance complete on
Blvd. DA,Final Engineering,Waivers, 07/12/2021.
114 Single-Family &Aesthetic Review approved by
Attached the CC on 12/09/2019. Single-Family Homes are under
Homes
(Attached) construction.
Final Plat approved by the CC on
09/28/20.
Hickory Grove Northeast of Bear A Non-Binding review was held DA,Final Engineering,Waivers,&
Townhomes Springs Drive and at the CC on 02/25/2021. Aesthetic Plans are under Staff review.
Blumberg Blvd Community Workshop was held
133 Single-Family on 08/26/2021.
Homes(Attached)
Iriye Suites Live Work Town Center SE&DA approved by CC on Pending* -Final Engineering and
Community 01/28/19. Aesthetic Plans
The Studios at Tuscawilla Vistawilla Drive Community Workshop was held Pending* -Final Engineering,Aesthetic,
on 07/19/19. &Waivers
DA approved by the CC on
01/13/20.
Tuskawilla Crossings: Town Center DA,Final Engineering,Waivers, Site acceptance complete.
379 Single-Family &Aesthetics approved by CC on Currently 371 Single-Family Homes are
Homes(detached) 04/24/17.Plat approved 08/13/18. permitted and/or completed with 8
remaining.
Winter Springs Medical E SR 434 Community Workshop was held Site work started.
Office on 08/13/19. Medical Office Building under
DA,Final Engineering& construction.
Aesthetic Plans approved by the
CC on 11/16/20.
Page 1 of 2
6
1954
Winter Springs SW Corner of SR Community Workshop was held Site work started.
Marketplace 434 and on 05/28/20. Aldi,Crunch Fitness,Dollar Tree,and
Five(5)Building Tuskawilla Road DA,Final Engineering,Waivers, Dental Buildings under construction.
Commercial Shopping &Aesthetic Review approved by
Center the CC on 02/22/2021.
Aesthetic Plans for Chipotle
approved by the CC on
08/09/2021.
Winter Springs Retirement Town Center DA,Final Engineering,Waivers,& Site work complete.
Residence(The Savoy): Aesthetic Review approved by CC Suites under construction.
144 independent suites on 01/22/18. Estimated construction completion
date is 02/22.
Winter Springs Town Center Town Center Final Engineering&Aesthetic Pending* -Preconstruction Meeting
Retail Building(Ocean Bleu) Plans approved by CC on
06/10/19.
For more information please click the link below:
City of Winter Springs Community Development Projects List/Locations
Notes: ADU=Accessory Dwelling Unit
CC=City Commission
CUP=Conditional Use Permit
DA=Development Agreement
PZB=Planning and Zoning Board
SE=Special Exception
*No Current Activity