The Utility Department requesting City Commission approval to award a contract to Precon
Corporation in the amount of $59,800.00 plus a 20% contingency to make repairs to the 0.5
million gallon (MG) ground storage tank at Water Treatment Plant 41 located on Northern
Way.
SYNOPSIS:
The purpose of this Agenda Item is to authorize repairs in the amount of $59,800.00 plus a
20% contingency to Precon Corporation for the 0.5 MG ground storage tank repairs at
Water Treatment Plant 41 noted during a recent inspection of the storage tank.
CONSIDERATIONS:
This project is needed to perform major maintenance to the potable water ground storage
tank at Water Treatment Plant 41 on Northern Way. Staff removed the tank from service
and had an extensive inspection done in 2017.
This tank was constructed in 1972 by Crom Corporation. There are only two companies in
Florida that construct prestressed concrete tanks, Crom Engineering and Construction
Services, Inc. of Gainesville and Precon Corporation of Newberry. Staff solicited proposals
from both companies to implement all recommendations contained in the inspection report.
The Precon bid was $59,800.00 and the Crom bid was $96,100.00. Precon Corporation was
chosen because they were the low bid and are qualified to make such repairs.
FISCAL IMPACT:
Funding is appropriated in the Utility Enterprise Fund Construction in Progress (CIP) line
Consent 301 PAGE 1 OF 2 - April 23, 2018
code for ground storage tank repairs at Water Treatment Plant 41 for FY2018. The amount
requested for the repairs ($59,800.00 plus a 20% contingency) will be paid from this fund.
COMMUNICATION EFFORTS:
This Agenda Item has been electronically forwarded to the Mayor and City Commission,
City Manager, City Attorney/Staff, and is available on the City's Website, LaserFiche, and
the City's Server. Additionally, portions of this Agenda Item are typed verbatim on the
respective Meeting Agenda which has also been electronically forwarded to the individuals
noted above, and which is also available on the City's Website, LaserFiche, and the City's
Server; has been sent to applicable City Staff, Media/Press Representatives who have
requested Agendas/Agenda Item information, Homeowner's Associations/Representatives
on file with the City, and all individuals who have requested such information. This
information has also been posted outside City Hall, posted inside City Hall with additional
copies available for the General Public, and posted at six (6) different locations around the
City. Furthermore, this information is also available to any individual requestors. City Staff
is always willing to discuss this Agenda Item or any Agenda Item with any interested
individuals.
RECOMMENDATION:
Staff recommends the City Commission authorize Precon Corporation to perform the
ground storage tank repairs at Water Treatment Plant 41 for $59,800.00 plus a 20%
contingency, and authorize the City Manager and City Attorney to prepare and execute any
and all applicable documents.
ATTACHMENTS:
There are two attachments included:
Aerial Photo of Ground Storage Tank
Precon Proposal
Consent 301 PAGE 2 OF 2 - April 23, 2018
1PRECON1
Prestressed Concrete Tanks
April 3, 2018
March 8, 2018
March 6, 2018
Mr. Kyle Lanham
City of Winter Springs
1126 East State Road 434
Winter Springs, FL 32708
(407) 327-8992
klanham@winterspringsfl.org
PRECON CORPORATION
REVISED PROPOSAL
Subject: City of Winter Springs, FL
Repairs to Tank #1 at WTP #1
115 S.W. 140th Terrace
Newberry, Florida 32669
Fax 332-1199
(352) 332-1200
Description: 0.5 MG GST 70'-0" ID x 17.33' WH
1. MATERIALS AND SERVICES TO BE FURNISHED BY PRECON CORPORATION
Precon proposes to furnish all labor, material, equipment, scaffolding, forms and
supervision required to complete the repairs in accord with the request of the City of
Winter Springs and Precon Corporation's standard prestressed concrete tank design.
The services to be furnished by Precon Corporation are specifically:
a. Pressure wash exterior wall and dome at 5,000 PSI
b. Apply one coat of Sherwin-Williams Loxon Conditioner at 1 mil DFT to improve
bond between existing coating and new coating.
c. Stripe coat any cracks on exterior wall and dome with Sherwin-Williams Loxon
XP at 8 mils DFT.
d. Apply one coat of Sherwin-Williams Loxon XP at 6 mils DFT per coat
e. Remove and replace dome safety hooks with those meeting OSHA standards.
f. Sandblast and recoat existing manhole frame with two coats of epoxy paint
g. In 2 areas at floor wall connection with staining, chip back to diaphragm, repair
if necessary and patch over.
h. Remove delaminating coatings on walls
i. In areas on interior wall with staining, chip back to diaphragm, repair if
necessary and patch over.
j. Sandblast the entire area of the underside of the dome and top 3' of walls
k. Use Sherwin-Williams Duraplate 2300 to repair any areas with exposed
reinforcing on the underside of the dome
I. Coat entire interior dome and top 3' of interior walls with 2 coats of Sherwin-
Williams Macropoxy 646PW at 6 mils DFT per coat
m. Sandblast and paint discharge and inlet pipes with Sherwin-Williams
Macropoxy 646PW
City of Winter Springs, FL -2- April 3, 2018
Repairs to Tank #1 at WTP #1 March 8, 2018
March 6, 2018
04
3.
4.
6.
7.
Q
0
n. Replace insect barrier on fiberglass dome hatch
o. Caulk around screens on all emergency overflows
p. Cleanout aerator
q. Touch up any delaminated coatings in aerator
r. Replace any corroded hardware on aerator
s. Apply caulk around aerator screen
t. Repair Liquid Level Indicator (LLI)
u. Provide and install new exterior aluminum ladder with safety cage and
locking security door
v. Install new welded aluminum handrail around the dome access hatch
w. Replace insect barrier on dome access hatch
x. Inject any areas of the tank that appear to be leaking with urethane
y. Chip back to prestress wires in any areas where rust stains are present.
Clean off any corrosion and patch wall.
Total Lump Sum: $ 59,800.00
SERVICES FURNISHED BY OTHERS
a. Water for construction
b. Electricity for Construction
c. Sediment to remain on site
d. Disinfection and bacteriological testing of tank
COMMENCEMENT AND COMPLETION
We are prepared to furnish sufficient labor, materials and equipment to complete the work
within approximately 4 weeks per tank after a mutually agreeable start date.
SHOP DRAWINGS AND DESIGN DATA
We will submit all data required for approval prior to starting work.
BOND
The cost of a payment -performance -maintenance bond, issued for a one-year period, is
to be added to the bid price if required. The price for this bond is $12.00 per $1,000.00.
If utilizing sub -guard, any bonds required will be added to the tank price.
SAFETY
This proposal is based on performing the work in accordance with Precon Corporation's
Safety Program, which meets or exceeds CFR 1926 OSHA Standards. If any additional
safety requirements are placed upon us, such as additional site training or safety
equipment, the cost for such additional requirements plus overhead shall be reimbursed
to us.
INSURANCE
Precon will furnish an insurance certificate showing coverage of liability, property and
worker's compensation insurance upon request. Our insurance will be carried in accord
with the general condition requirements. An additional amount will be added to our
subcontract price if there are any extra requirements. Builder's Risk insurance will be
carried in accord with general conditions requirements.
ARBITRATION
Any dispute or claim between us shall be settled by arbitration in accord with the
American Arbitration Association rules relating to the construction industry. The
arbitrator's decision may be entered in any court having jurisdiction.
City of Winter Springs, FL -3- April 3, 2018
Repairs to Tank #1 at WTP #1 March 8, 2018
March 6, 2018
10. ACCEPTANCE
This proposal is offered for your acceptance within 15 days. This proposal is based on
the conditions of the AIA Standard Form of Agreement Between Contractor and
Subcontractor, and it shall be made part of any subcontract.
Accepted:
0
Title:
Offered: Precon Corporation
Adrian C. Moore