HomeMy WebLinkAbout2018 02 12 Consent 305 Professional Offices at Winding Hollow Site AcceptanceCOMMISSION AGENDA
ITEM 305
February 12, 2018
Regular Meeting
Informational
Consent
X
Public Hearings
Regular
KS
City Manager
is
Department
REQUEST:
The Community Development Department requesting the City Commission: 1) validate the
Staff recommendation finding The Professional Offices at Winding Hollow (east
side) sitework to be built in substantial accordance with the Final Engineering plans, subject
to the enclosed punchlist; and 2) accept the public infrastructure improvements for
ownership and maintenance.
SYNOPSIS:
Sitework for The Professional Offices at Winding Hollow project is substantially complete
and has been conditionally approved by the applicable City Departments. This agenda item
provides the site acceptance necessary before a final certificate of occupancy can be issued
by the Building Official.
CONSIDERATIONS:
APPLICABLE CODE:
Section 9 -178. Required Improvements to be completed prior to building on lots;
exceptions.
(c) Where the building official has an authoritative method of assurance that the
improvements will be completed in accordance with approved plans, such as
withholding occupancy, the building official may issue building permits upon
advising the developer that all or partial occupancy will be restricted until satisfactory
completion of the improvements has be accomplished.
Consent 305 PAGE 1 OF 2 - February 12, 2018
(d) ... Certificates of occupancy will not be issued until all improvements are
accepted by the city commission.
SUMMARY:
The Professional Offices at Winding Hollow project consists of three 3,500 SF single -
story office buildings located on the east side of Winding Hollow Boulevard, south of
S.R. 434. The Final Engineering Plans were approved by the City Commission at
the December 4, 2013 City Commission meeting. Sitework commenced in September
2014 and building construction started soon thereafter; however, construction stopped in
2015 and the project ownership was taken over by a bank. In April 2017, a new
developer, Coberturas Medicas of Florida, acquired the property and resumed
construction of the approved plans. The three buildings are expected to be complete and
occupied within the next several months.
This agenda item is for the conditional acceptance of the site improvements. The sitework
has been constructed in substantial compliance with the Final Engineering plans approved
by the City Commission, except as noted on the attached punchlist, Exhibit A. All items on
the punchlist must be complete, subject to Staff approval, prior to issuance of the certificate
of occupancy.
FISCAL IMPACT:
There is no fiscal impact associated with this agenda item.
COMMUNICATION EFFORTS:
This Agenda Item has been electronically forwarded to the Mayor and City Commission,
City Manager, City Attorney /Staff, and is available on the City's Website, LaserFiche, and
the City's Server. Additionally, portions of this Agenda Item are typed verbatim on the
respective Meeting Agenda which has also been electronically forwarded to the individuals
noted above, and which is also available on the City's Website, LaserFiche, and the City's
Server; has been sent to applicable City Staff, Media/Press Representatives who have
requested Agendas /Agenda Item information, Homeowner's Associations/Representatives
on file with the City, and all individuals who have requested such information. This
information has also been posted outside City Hall, posted inside City Hall with additional
copies available for the General Public, and posted at six
(6) different locations around the City. Furthermore, this information is also available to any
individual requestors. City Staff is always willing to discuss this Agenda Item or any
Agenda Item with any interested individuals.
RECOMMENDATION:
Staff recommends that the City Commission validate the Staff recommendation finding
the Professional Offices at Winding Hollow sitework to be built in substantial accordance
with the Final Engineering plans, subject to satisfactory completion of the remaining open
punchlist items.
ATTACHMENTS:
1. Exhibit A - Site Acceptance Punchlist
Consent 305 PAGE 2 OF 2 - February 12, 2018
EXHIBIT A
Tuesday, January 30, 2018
City of Winter Springs
Offices at Winding Hollow (East)
Items to Complete (This is not a final punchlist):
• FDEP Sanitary Sewer Certification
• Record drawings
• Engineer of Record Certification
• SJRWMD Certification
• Two -Year Maintenance Bond and Bill of Sale for utilities to be turned over to the City
(Potable Water, Sanitary Sewer, Reclaimed Water)
Additional Items to Complete
• Provide riprap at the stormwater pond outfall, per the plans
• Grade east side of property per the engineering drawings
• Install site lighting, per the plans
• Remove all excess sediment from stormwater structures
• Remove safety and silt fence when sod is established
• Install fence on retaining wall, per the plans
• Clean up all trash from the site and wetland area. This also includes the area on the
south side of the CMU wall
• Lower all cleanouts to grade
• Complete landscaping
• Complete irrigation
• Repair leaking backflow devices
• Paint fire hydrant, Sherwin Williams Safety Yellow
• Install and paint valve covers and concrete collars at all shutoff valve locations
• Restore the irrigation and landscaping along Winding Hollow Blvd
• Install detectable warnings
• Asphalt raveling at the east side of the driveway where it meets the parking lot
• There is a missing Type C inlet on the North East corner of Bldg #3 and it appears
the storm pipe configuration was installed differently than the final engineering plans.
These changes will need to be shown on the asbuilts.