REQUEST:
The Parks and Recreation Department requests the Parks and Recreation Advisory
Committee discuss the project updates for Sam Smith Park, Trotwood Park, Moss
Park, and Torcaso Park.
CONSIDERATIONS:
The Sam Smith Restroom Project began in August of 2017. The project goal was
to provide restroom facilities as a new addition to the playground improvements
completed in September 2017. The final phase of safety fencing for 2-5 area will be
installed in February 2018. The project will then be 100% complete. We will
evaluate the use and demand of the pavilion rentals to see if additional parking is
needed.
The Trotwood Park Family Pavilion is scheduled to begin in Spring 2018 pending
Commission approval. The project includes a large hexagon pavilion with walkway
to seat approximately 150 people. The expected completion date is set for the end
of September 2018.
The Parks and Recreation Department installed two new playgrounds at Moss
Park. The total cost for the playgrounds was $130,000 which included a 5-12 and
2-5 playground, mulch surfacing, ADA access, surface borders, and sod. The final
phase is safety fencing for 2-5 area which will be installed in February 2018.
The Parks and Recreation Department will be meeting with the CMAR from
Wharton-Smith for the proposed Fieldhouse. Construction discussions will begin in
February 2018.
RECOMMENDATION:
The Parks and Recreation Department is requesting that the Parks and Recreation
Advisory Committee consider and discuss the project updates.
ATTACHMENTS:
Attachment A – Sam Smith Park
Attachment B – Moss Park
MI.
84 ^
OAF
7jil
I IPF
-sad ..Fa.—
gas
_ Io0 s
k..
s'
s�4?
i�
......... ........
41
lit al m ill hi t1i ill L � ;�oueeeq i , ete,Stettina it
� rll N
K.