HomeMy WebLinkAbout2017 10 09 Consent 305 Integra 360 Phase 1 Conditional Site Acceptance
COMMISSION AGENDA
Informational
Consent
ITEM305
>
Public Hearings
Regular
October 09, 2017KSBF
Regular MeetingCity ManagerDepartment
REQUEST:
The Community Development Department requesting the City Commission: 1) validate the
Staff recommendation finding the Integra 360 Phase 1 sitework to be built in substantial
accordance with the Final Engineering plans, subject to the enclosed punchlist; and 2)
accept the Phase 1 public infrastructure improvements for ownership and maintenance.
SYNOPSIS:
Sitework for Phase 1 of the Integra 360 apartment project is substantially complete and has
been conditionally approved by the applicable City Departments. This agenda item
provides the site acceptance necessary before a final certificate of occupancy can be issued
by the building official for any Phase 1 apartment buildings.
CONSIDERATIONS:
APPLICABLE CODE:
Section 9178. Required Improvements to be completed prior to building on lots;
>
exceptions.
(c) Where the building official has an authoritative method of assurance that the
improvements will be completed in accordance with approved plans, such as
withholding occupancy, the building official may issue building permits upon
advising the developer that all or partial occupancy will be restricted until satisfactory
completion of the improvements has be accomplished.
(d) … Certificates of occupancy will not be issued until all improvements are
accepted by the City Commission.
Consent 305 PAGE OF October 09, 2017
13-
On January 25, 2016, the City Commission approved a PUD rezoning ordinance,
>
Development Agreement and Master Plan detailing the future development
of the 39.81 acre ICI property consisting of 29.81 acres of multifamily residential
>
development with a maximum of 340 apartment units and 20, two (2) story carriage
home units. This portion of the project is referred to as the "Integra 360" apartment
project. The remainder of the ICI property consists of ten (10) acres of
commercial/office development with a minimum of 100,000 square feet of
commercial/office uses. The ICI property is located on the north side of SR 434,
directly across from the Creek's Run subdivision.
Final Engineering plans for the Integra 360 project were approved by the City
>
Commission at the June 13, 2016 City Commission meeting. Sitework commenced
in July 2016. The sitework consists of two phases. Phase 1 is the western side of
the site and includes the main entrance road, clubhouse building, two apartment
buildings, and the carriage units along the main entrance road. This conditional site
acceptance agenda item is only for the Phase 1 site infrastructure. A separate Phase
2 site acceptance will be submitted at a later date for City Commission approval,
which will include the remainder of the site infrastructure including the eastern
entrance roadway and the associated right turn deceleration lane. Integra has
obtained the land from the adjacent property owner for construction of the turn lane,
and it will be built as part of the Phase 2 site infrastructure, along with the four
apartment buildings in Phase 2.
This agenda item is for the conditional acceptance of the Phase 1 site
>
improvements. The sitework has been constructed in substantial compliance with
the Final Engineering plans approved by the City Commission. The public
infrastructure being conveyed to the City for ownership and maintenance includes
roadway, sidewalk, stormwater, water, sewer and lift station components.
The Phase 1 site acceptance is subject to completion and acceptance of all items on
>
the attached punchlist (Exhibit A). No certificates of occupancy for any apartment
buildings will be issued until all items on the punchlist are complete.
FISCAL IMPACT:
There is no fiscal impact associated with this site acceptance.
COMMUNICATION EFFORTS:
This Agenda Item has been electronically forwarded to the Mayor and City Commission,
City Manager, City Attorney/Staff, and is available on the Citys Website, LaserFiche, and
>
the Citys Server. Additionally, portions of this Agenda Item are typed verbatim on the
>
respective Meeting Agenda which has also been electronically forwarded to the individuals
noted above, and which is also available on the Citys Website, LaserFiche, and the Citys
>>
Server; has been sent to applicable City Staff, Media/Press Representatives who have
requested Agendas/Agenda Item information, Homeowners Associations/Representatives
>
on file with the City, and all individuals who have requested such information. This
information has also been posted outside City Hall, posted inside City Hall with additional
copies available for the General Public, and posted at six (6) different locations around the
Consent 305 PAGE OF October 09, 2017
23-
City. Furthermore, this information is also available to any individual requestors. City Staff
is always willing to discuss this Agenda Item or any Agenda Item with any interested
individuals.
RECOMMENDATION:
Staff recommends that the City Commission: 1) validate the Staff recommendation finding
the Integra 360 Phase 1 sitework to be built in substantial accordance with the Final
Engineering plans, subject to the attached punchlist; and 2) accept the public infrastructure
improvements for ownership and maintenance.
ATTACHMENTS:
1. Exhibit A Phase 1 Sitework Punchlist (1 page)
>
Consent 305 PAGE OF October 09, 2017
33-
EXHIBIT A
Integra 360
Phase 1 Site Acceptance Punchlist
/ƩĻĻƉƭ wǒƓ ĻƓƷƩǤǞğǤ ƩĻƭƷƚƩğƷźƚƓ Ʒƚ ğƓ Ļqual or better appearance than prior to
construction. Paving was being completed on 10/3 and 10/4. All striping, landscaping,
and cleanup to be complete before a Certificate of Occupancy will be issued.
Storm video inspection complete and approved
Complete lift station enclosure
Meter and Backflow assemblies to be painted black, per the approved plans
Complete pond grading and install mulch path around the pond per the approved plans.
Complete pond bank grading and stabilization per the approved plans
Install PVC cap at the pond outfall structure
Provide updated survey of the ponds showing the weirs and grading after the washout
repairs
Install a water main valve cap and cover at the future connection to the west parcel
Clean up and remove all construction and tree debris from the front parcels
The roundabout signage and pavement markings do not match the engineering
drawings. Temporary signage and striping are acceptable.
Repair all cracked sidewalk panels on the main entry way sidewalk
Install conservation area signage
Submit the recorded deed and copy of submitted FDOT permit application for the right
turn deceleration lane at the east entrance roadway
Decorative landscaping, irrigation, the final lift of asphalt, and all final striping in the
Phase 1 area shall completed in Phase 2.