REQUEST:
Police Department requests the City Commission to approve and utilization of P.N.L.
Commercial for the purpose of expanding the Police Department's Crime Lab. Funding is
requested from Police Impact Fees in the amount of $18,525.00.
SYNOPSIS:
The Florida Department of Law Enforcement's Crime Lab in Orlando services the Winter
Springs Police Department and other law enforcement agencies across Central Florida and the
State of Florida. With the amount of evidence processed state wide it creates a backlog in results
for criminal cases. Recently, due to budget restraints, the Florida Department of Law
Enforcement has implemented restrictions in processing certain cases.
The Winter Springs Police Department has a trained certified crime Scene Analyst that can
process the majority of the items. In order for our Analyst to process evidence safely and
effectively some minor upgrades need to be done in the crime lab by a licensed contractor.
CONSIDERATIONS:
By improving our ability to respond to the increased call load of Criminal Investigation's and the
need for processing crime scene evidence, the police department has trained and currently has a
certified Crime Scene Analyst capable of processing much of the criminal evidence previously
CITY OF WINTER SPRINGS, FLORIDA
CITY COMMISSION
MEETING -July 26, 2010
CONSENT AGENDA ITEM "200"
PAGE 2 OF 2
sent to the Florida Department of Law Enforcement's Crime Lab in house. By expanding this lab
the police department and our citizens will recognize a quicker disposition in lab results.
Having a quicker disposition on case evidence will allow our investigators the needed
information for successful prosecution of criminal cases.
FISCAL IMPACT:
The Winter Springs Police Department secured three written quotes from licensed contractors to
perform the work with the direction of engineering plans and specs from Architects Design
Group, Inc. out of Winter Park, FL. PNL Commercial Corporation quoted $18,525.00, Air -Pak
Product & Services, Inc. quote was $21,355.00 and Patrick Stack Inc quoted $28,834.00.
Funding is requested from Police Impact Fees in the amount of $18,525.00. The available
balance in Police Impact Fees is $91,940.80.
The City Engineer reviewed the quotes and felt that PNL was acceptable. The Cities Building
Department reviewed each contractor's background for complaints and found no complaints and
that all three have been in business for 9 to 10 years.
COMMUNICATION
EFFORTS:
Posting of the agenda prior to the meeting at various locations throughout the city.
RECOMMENDATIONS:
The City Commission to approve the expenditure of $18,525.00 from Police Impact Fees and
approve utilization of P.N.L Commercial as the contractor for this project.
ATTACHMENTS:
Quotes from the following; Patrick Stack Inc., Air -Pak Products and Services and PNL
Commercial.
Page 1 of 1
Patrick Stack Inc.
9500, Handley Ct.
Orlando, FL.
32817.
CGC. 062224. CCC. 1327447.
Ph (407) 947 3724.
Proposal
June 15, 2010.
Project Address,
Winter Springs Police Department. Architect: ADG.
1126, East State 434, Project #646B -10
Winter Springs, FL. 32708.
Ph. (407) 327 1000.
Attn. Captain Michael Noland.
General Scope.
Permit acquisition
Permit Fees
Job Prep
Dumpster Fee
Demo Ceiling
Demo Flooring
Demo Wall
Electrical Permit and Labor
Electrical Materials
New Hom/Strobe Alarm Co
No Fire Sprinkler Included
Drywall install and repair
Install new Door and Frame
New Drop Ceiling
New drop in Light Fixtures
Replace Exhaust Fan
Painting Lab and Material SW.
Cabinetry Labor and Materials
Install Owner provided Sink
Plumbing Permit and Labor
New Vinyl Flooring per Specs
New Cove Base per Specs
New Counter Tops per Specs
Periodic and Final Cleaning
Supervision
ADG Specs and Drawings Dated May 19, 2010.
Bid Price $28,834.00.
Payment Terms:
Per AIA Documents
Submittal valid for a period of ten days from date of proposal.
Contract Documents to be drawn up upon acceptance of proposal.
Proposed By // At, •�
Pain. tack GC.
file: / /C:\Documents and Settings\mnoland \Local Settings \Temporary Internet Files \Conten... 6/29/2010
AirPak QUOTATION
PRODUCTS r, SERVICES, INC. For Job: City of Winter Springs Police Department
6966 Venture Circle Town: Winter Springs, FL
Orlando, FL 32807 Architect: Architects Design Group, Inc.
(407) 678 -1847 Structural Engineer:
Electrical Engineer.
QUOTATION TO: Mechanical Engineer:
City of Winter Springs Police Department Fire Sprinkler Engineer:
Attn: Captain Mike Nolan Landscape Architect:
300 N. Moss Road
Winter Springs, FL 32708 -2510
Quote Date: 6/30/2010 Take off by: Riggs Bid Date: 6/30/2010 Terr:
This price quote applies only to these specifications and this job. Do not use for any other quotes. Please obtain new quote from Air -Pak Products & Services, Inc. .
NOTE: This quotation is made in accordance with Air -Pak Products & Services, Inc.'s understanding of the job requirements as Building Contractor.
See (attachment below) for complete Acceptance Terms and Conditions, which is wholly part of this quotation.
AIR -PAK PRODUCTS & SERVICES, INC. . IS PLEASED TO QUOTE THE FOLLOWING:
Scope of Work to include: Interior Lab Renovations
Specifications Dated: 5/19/2010
Drawings Dated: N/A
Drawing Revisions Dated: N/A
Project No. 6468 -10
Drawing Pages: A -1.01
1) Remove existing countertops in Work Area and Dark Room and cap plumbing. Remove existing exhaust fume. Remove partition wall
frame and door. Remove existing VCT floor covering and base. Remove end section of upper cabinet in dark room. Remove existing
ceiling tile.
2) Repair walls and paint with epoxy paint per specifications.
3) Provide and install new vinyl flooring per specifications.
4) Provide and install new chemical resistant plastic laminate countertops / install owner provided stainless steel sinks and faucets.
5) Provide and install p -lam cabinet fillers and laminate as specified.
6) Provide and install new ceiling tile as specified.
7) Provide new electrical outlet in work room; repair exhaust fan; provide and install new emergency exit Tight, new horn and strobe to
match existing in Room 103.
8) Provide and install new double action door for Room 103.
9) Provide and install 2 new 2x4 lay -in troffer lights into existing ceiling grid system and tie into generator circuit.
10) Proposal includes permits. All interior wall and door work to be performed at night to minimize interruption to operations.
GRAND TOTAL BID: $ 21,355.00
TWENTY ONE THOUSAND THRE U D FIF FIVE DOLLARS.
AUTHORIZED SIGNATURE: TITLE ! ✓i DATE: ,J Jt5
� 1
ACCEPTANCE SIGNATURE: TITLE DATE:
ASBESTOS INSPECTION SURVEY/ REMOVAL IF REQUIRED FOR ANY REASON, IS A ADDITIONAL CHARGE TO OWNER.
QUOTE IS GOOD FOR THIRTY (30) DAYS FROM DATE OF QUOTE
Mike Noland
From: pcbsinc @aol.com
Sent: Wednesday, July 14, 2010 10:20 AM
To: Mike Noland
Subject: PNL Revised Proposal 07/12/10
Attachments: PNL_ proposal _WSPD_REVISED_071210.xls
Jay Duncan, President
P.C.B.S, Inc.
Ph - 407 - 339 -1072
Fx - 407 - 339 -1003
Original Message
From: pcbsinc @aol.com
To: MNoland @WinterspringsFl.org
Sent: Tue, Jul 13, 2010 10:17 am
Subject: PNL Revised Proposal 07/12/10
Mike,
Attached is our lump sum proposal letter as discussed.
Please let me know as soon as possible the final decision so I can schedule appropriately.
I look forward to working with you and your team.
Sincerely,
Jay Duncan, PCE
PNL Commercial
Ph - 407 - 339 -1072
Fx - 407 - 339 -1003
1
Winter Springs
Police Department
Interior Renovation
Revised 7/12/2110
DIVISION 1- GENERAL CONDITIONS
PERMITTING Included
ASBESTOS SURVEY /ABATEMEN' By Owner
TEMPORARY POWER By Owner
TEMPORARY WATER By Owner
TOILET Use on site
TEMORARY LABOR Included
FINAL CLEAN UP Included
TRASH REMOVAL Included
LAYOUT / DIRECTIVES By Owner
BLUE PRINT REPRODUCTION Included
SUPERVISION Included
PROJECT MANAGEMENT Included
DIVISION 2 - SITEWORK
EARTHWORK Not applicable
DIVISION 2 - DEMOLITION
AS PER DRAWINGS Included
DIVISION 3 - CONCRETE
CONCRETE Not applicable
7/14/2010 P.C.B.S., Inc. Ph: 407 - 339 -1072 / Fx 407 - 339 -1003
Winter Springs
Police Department
Interior Renovation
Revised 7/12/2110
DIVISION 4 - MASONRY
MASONRY Not applicable
DIVISION 5 - STEEL
STEEL Not applicable
DIVISION 6 - CARPENTRY
MILLWORK - COUNTER TOP Included
MISCELLANEOUS BLOCKING Included
DIVISION 7 - THERMAL & MOISTURE
INSULATION / ROOFING Not applicable
SUBTOTAL DIV 7
DIVISION 8 - DOORS & WINDOWS
HOLLOW METAL FRAME Included
3' -0' X 7' -0 BIRCH DOOR AND HARDWARE
SUBTOTAL DIV 8
DIVISION 9 - FINISHES
FLOORING Included
FRAMING AND DRYWALL Included
PAINTING Included
CEILINGS (Includes patching) Included
SUBTOTAL DIV 9
7/14/2010 P.C.B.S., Inc. Ph: 407 - 339 -1072 / Fx 407 - 339 -1003
Winter Springs
Police Department
Interior Renovation
Revised 7/12/2110
DIVISION 10 - SPECIALTIES
SPECIALTIES By Owner
SUBTOTAL DIV 10
DIVISION 12- FURNISHINGS
MISCELLANEOUS Not applicable
SUBTOTAL DIV 12
DIVISION 14 - CONVEYING SYSTEMS
SUBTOTAL DIV 14 Not applicable
DIVISION 15 - MECHANICAL
PLUMBING Included
HVAC - Allowance repair / new exhaust fan
FIRE PROTECTION Not Applicable
SUBTOTAL DIV 15
DIVISION 16 - ELECTRICAL
FIXTURES Included
OUTLETS Included
WIREING Included
FIRE ALARM STROBE (1) Included
SUBTOTAL DIV 16
OVERHEAD & PROFIT Included
EXTENDED TOTAL AS PER PLAN $18,525.00
7/14/2010 P.C.B.S., Inc. Ph: 407 - 339 -1072 / Fx 407 - 339 -1003