REQUEST: Public Works Department is advising the City Commission of the status of various
Capital Improvement Projects
PlURPOSE: This agenda item is to update the Commission on the status of current Capital
Improvement projects.
CONSIDERATION:
TI1AFFIC/TRANSPORTATION IMPROVEMENT
SR 434 Improvements (Village Walk) - The preconstruct ion meeting was held on May 11th with the
contractor, APAC, and CEI, American Bridge/WCG Joint Venture. The Notice to Proceed is expected to
be: issued late August to Early September, Project completion for the 270 day project is anticipated to be
June 2005, Contractor preparing his construction schedule now and it is expected to be completed for
approval by the end of July, The planned turn lanes at Moss Road and Hayes Road design is ongoing,
When the contractor provides a detailed construction schedule outlining the critical events it will
forwarded to the City Commission, Progress Energy has providing the preliminary design for burying the
power, We have reviewed the plans and walked the site with Progress Energy representative for some
proposed changes, Progress Energy hopes to complete the design/cost analysis by the end of August. If
approved and funded, Progress Energy anticipates a construction start date in November. Landscape
easements that were identified as needing corrections have been returned to the property owners for new
signatures, (7/26/04)
Main Street / Hickory Grove Streetscape - This $850K project includes sidewalks, irrigation, and
landscaping on Tuskawilla Road, Blumberg Boulevard, and Doran Drive in the Town Center. Contract is
substantially complete with punch list items remaining. Landscape maintenance is underway, The
additional work authorized for J Raymond has been completed, Magnolia Park size (0,64 or 0,79 acres)
being negotiated with Schrimsher. (6/28/04)
SR 434 Town Center Corridor Analysis - Update was provided to the City Commission on July lih by
Walter Kulash. Project is to review opportunities and alternatives available to redefine 434, Glatting
Jaekson will be reporting back to the City Commission in 60 days, (7/26/2004)
.
.
.
July 26, 2004
Information Item 303
Page 2
SR 434/ Doran Drive Traffic Signal - This is a joint design project with CPH Engineers and PEC, Inc,
the project involves installation of traffic signal at Doran Drive and SR 434, with asphalt stamping similar
to the intersection of Tuskawilla Road and Winter Springs Blvd, and adding an additional right turn out of
the Town Center at Publix, The City Hall/Tuskawilla Trails median opening will be required to be
changed to a directional only to get signalization at Doran Drive. Both plans have been reviewed with
changes made. Second revision plans are under review for final acceptance, On site test digs have been
performed to determine location of mast arms for traffic signals. Glatting Jackson recommended that we
proceed with this project as it is consistent with the ultimate circulation in the Town Center. Permit
applications are pending submittal to FDOT, The additional right of way from Mrs, Blumberg is
appraised at $7.25 per square foot for a total of$11,360, Fire Dept. staff received authorization from Mrs,
Blumberg for a temporary access from City Hall to Doran Drive to improve response time, (6/28/04)
SR 434 Highway Beautification Grant - Funding amount approved $214,079,03. Notice to Proceed
issued March 2003 for 12 month construction period with a 6 month extension for the' conflict with the
trail bridge, Irrigation is complete and plant installation is 95% complete, awaiting completion of trial
bridge, Work being performed by Public Works and Utility Department staff with a completion of
summer 2004, (4/26/04)
SR 419/ Moss Road Turn Lane - This project was bid with a bid closing date of30 June 2004, The JP A
to take advantage of the FDOT cost sharing of $100,000 will be brought for Commission consideration
wiithin the next 30 days, Professional Engineering Consultants are reviewing the bids, Expect
recommendation for contract award will be brought to the commission within the next 30 days. (7/26/04)
Cross Seminole Trail (Gee Creek to Town Center/Bridge to Gardena Avenue) - Project was bid as of
May lOth, Recommendation of Award of contract is being scheduled for the County Commission meeting
in the next 30 days, Construction is projected to begin in August 2004 with a 9 month construction period,
The proposed construction limits for the paved trail are from Gee Creek to approximately 500 east of
Magnolia Park and from the SR 434 trail bridge to Gardena. The unpaved portion of the trail and paved
portion in the middle of the Schrimsher property impacted by the eagle are not included in the project.
(6/26/04)
Pedestrian Bridge - Cross Seminole Trail- Construction by the design/build team of Jones Bros,/Mactec
underway. We have requested revisions to the $240,000 proposal for lighting the bridge to only include
tht~ conduit at this time. A proposal for upgrading the fencing is pending, Both proposals will be brought
to the City Commission when finalized, The deck pour is scheduled for July which will require some
traffic detours. Scheduled deck pour may be delayed until mid-July due to concrete delivery delays. The
designlbuild contract is scheduled to be completed November 2004, The next progress meeting is
scheduled for 2 August 2004, (6/28/04)
Cross Seminole Trail (Wade Street to Wekiva Trail) - The Preliminary Design and Corridor Analysis
was presented by the County and VHB. City Manager is working on garnering financial support for the
City preferred alignment north of the industrial park versus the County preferred alignment through the
industrial park. (4/26/04)
Fi,~her Road - Project is complete. Signage to be added to allow left turns in front of the circles for
oversized vehicles/trailers, Minor modifications to the some of the radius pending, Additional landscaping
.
.
.
July 26, 2004
lnfonnation Item 303
Page 3
planned for June underway. Landscaping work being performed by the Public Works Department
(6/28/04)
Central Winds Park Way - Final road design ongoing by CPR. Additional right of way has been
requested from the Leerdam property, (7/26/04)
Deceleration Lane Study - Final amended report adopted by the City Commission with the consolidated
pmject priority lists on May 10th, Ordinance adopted 14 June 2004. (6/28/04)
Ur,nter Springs Boulevard Reconstruction - Proposal for phased pavement analysis and scope of repairs
was approved on May 10th, Pavement analysis will begin in June. Geotechnical work will be conducted
in July/August to capture the rainy season ground water table information, (5/24/04)
UTILITY
SR 434 Water Main (Vistawilla Road to Spine Road) - Design 90% complete. Waiting for Casscells to
execute the utility easement. Schrimsher easement is pending, (11/10/03)
Utility / Pu.blic Works Compound - Design 40% complete. Plan review by staff and SRI was held on 21
Jlll~, Final site layout has been complete pending Environmental Services, Inc. (ESI) report. Met on May
2St with FDEP to review the impact of wetlands on site, Site study has been performed on 22 June, by
Environmental Services, Inc, with report pending for wetlands impact. (7/26/04)
JJell #4 - Driller at 300 feet and is 70% complete, Drawdown tests for volume and water quality were not
satisfactory, Test well completed 7/16/04 at 450 feet. Staff and geotechnical consultant reviewing
information from small test well with course of action to be determined, Sunshine Building and
Development is contractor for this $271,956 project. (7/26/04)
Reclaimed Water Augmentation - Final report will be delivered by CPH end of July, (5/24/04)
Jfest Water Reclamation Facility Roof Replacement - This $41,787.00 project replaces the existing roof
with a gabled truss shingle roof The contract was awarded to Ernest and Hutch Contracting with a Notice
to Proceed issued for 8 June 2004, This 90-day construction project has a scheduled completion date of 6
Sc;:ptember 2004, Project proceeding as scheduled. (7/26/04)
PARKS and RECREATION
Central Winds Park Expansion Phase I (Sitework) - Clearing, grubbing and grading complete,
Certificate of Substantial Completion has been issued. Commission approved mediation settlement on 28
June. Contractor has one more payment application to submit as per the settlement agreement. (7/26/04)
Central Winds Park Expansion Phase II (Landscape& Irrigation) - Design complete, Pump station
installation complete, awaiting Progress Energy power connection for pump station. Due to delays in the
Clearing and Grubbing phase plan is to perform irrigation work in conjunction with underground storm
water pipe installation so as to take advantage of the remainder of the growing season. (7/26/04)
Central Winds Parkway Stormwater Piping - Stormwater piping installation began 12 July. Contract is
a ]120 day contract with a scheduled completion date of9 November 2004, (7/26/2004)
.
.
.
July 26, 2004
Information Item 303
Page 4
Moss Park Buffer Wall- Project is complete, (7/26/04)
POLICE
Public Safety Building Expansion - This $185,000 contract by Tim Williams Builders is complete with
punch list items remaining. (5/24/04)