COMMISSION AGENDA
ITEM 300
CONSENT
INFORMATIONAL X
PUBLIC HEARING
REGULAR
December 8, 2003
Meeting
MGR.~EPT fr
Authorization
REQUEST: Community Development Department is advising the City Commission of
the status of various current planning projects.
PURPOSE: This agenda item is to update the Commission on the status of current planning
projects.
CONSIDERATION:
Badcock Shopping Center - On June 5, 2003, plans were submitted for a 27,000 square foot
addition to the 45,700 square foot recently up-graded shopping center, located at the northwest
comer of Sherry Avenue and SR 434. The plans were reviewed at the June 17,2003, DRC.
The traffic study is being reviewed by the City's consultants and the site plan was reviewed at
the October 7,2003 DRC. Revised final site plans were submitted on November 24,2003, and
are to be reviewed at the December 9,2003, DRC meeting. per 12/08/03 agenda.
Barclay Woods (Townhomes) - On October 14,2003, a conditional use application and
supporting concept site plan were submitted for an 88 unit town-home project on 7.56 acres on
the north side of SR 434, just west of the entrance to Barrington Estates and immediately west
of the Don King Concrete office. The conditional use was discussed at the October 21 DRC
and was heard at the 11/06/03 BOA. It is scheduled for this City Commission meeting. per
12/08/03 agenda
Belfaire (aka "Barrington Estates" & formerly "Battle Ridge'J - Home construction
continues. Storm, under-drain, and R/W inspections have been completed. As-built utility
inspection was completed 10/22/03. "Punch-lists" have been generated and forwarded to
developer. Final acceptance and the landscape plans are both scheduled for this City
Commission meeting. per 12/08/03 agenda
Colt Drive - The City Attorney has provided a warranty deed to Richland Properties,
requesting that they execute it to convey possession of Colt Drive to the City. per 7/14/03
agenda
November 10, 2003
Information Item 300
Page 2
Dr. Courtney's Office - In December 2002, Dr. Courtney submitted preliminary
engineering/site plans for a dentist office on the wooded 0.72 acre site immediately west of
City Hall, between City Hall and the equipment rental facility. The engineering plans were
revised, consistent with the geometry plan that was conceptually approved at the February 10,
2003, City Commission meeting. The final engineering plans, architectural renderings, and
floor-plan for the eastern Y2 of the building were approved at the October 13, 2003, City
Commission meeting. per 10/27/03 agenda
Dollar General Store - Plans for an 8,125 square-foot Dollar General store were submitted on
April 15, 2003, for the 1.3 acre parcel between the Winter Springs Golf Club and the Sheoah
Section 1 dwellings. The final engineering plans were approved at the September 8,2003, City
Commission meeting, but the applicant has withdrawn the application. Another entity has met
with staff and expressed interest in developing the site. per 12/08/03 agenda.
Dumpster Enclosure Noticing - Certified Letters were sent out to 105 property owners
noticing them about the dumpster enclosure ordinance and the March I, 2004, compliance
date. Staff received 18 phone calls within the first week. The primary questions have been
related to what alternative materials can be used, since the Code states".. .Dumpsters shall be
screened by an opaque wall made of concrete, brick, stone, or other suitable durable material,
provided, ..." and "Dumpsters shall be placed on a concrete pad or other impervious surface
deemed suitable.. .". per 9/22/03 agenda.
Fox Run Preliminary Subdivision Plan- On March 26, staff received the application and plans
for preliminary subdivision of a 5-10t residential subdivision on 1.28 acres at the west end of
Panama Circle. This item was reviewed at the April 2, 2002, DRC. Staff awaits are-submittal
per 4/22/02 agenda
Garcia Driveway Re-locate. -Construction has resumed, as of November 18,2003, after
ceasing, due to high water levels. The crew is continuing cutting out the new road way
configuration and drive, completing the sub-base on November 26,2003. As of December 1,
the crew has completed the stabilized base and paving is scheduled for December 5, 2003. per
12/08/03 agenda
Highlands Apts., Phase II - The 42 unit apartment (3 floor) final site plan was approved on
October 14, 2002. A pre-construction conference was held March 27, 2003. The applicant
needed to provide either a storm-water permit or letter of exemption from the SJRWMD (the
site was once part of the larger adjacent Seville on the Green) before commencing clearing.
Building plans were reviewed by staff and the applicant must resubmit revised plans. On
August 8, 2003, the applicant submitted a revised final engineering/site plan with on-site
storm-water management, which was reviewed at the August 26, 2003, DRC. per 9/08/03
agenda
JDC Calhoun - Construction continues. Buildings 9, 10, 11, 13, and 14 have received
certificates of occupancy (Cas). Building No. I is under construction. An incomplete plat to
subdivide the Wendy's site from the 15 acre JDC tract was submitted May 7 and reviewed at
the June 2, 2003, staffDRC meeting. Staffis awaiting changes to the plat and the legal
description attached to the title certification, in order for the City's consultant to certify the plat
and for staff to bring it to the City Commission for approval.
November 10, 2003
Infonnalion Item 300
Page 3
A Second Amendment to the Development Agreement was approved at the June 23, 2003,
commission meeting, allowing Building No. 1 to be a tall single floor structure with the
appearance of a 2 floor structure, designed to accommodate a second floor if/when the market
dictates.
A revised site lighting plan was provided to staff, reviewed by the City Manager, and was
approved on August 25,2003.
City records indicate the following businesses are locating in the JDC Calhoun Town Center:
Building 8 - Leslie Pool Supply, a dentist, and a tanning salon;
Building 9 - Red Bug Cleaners, E-Nails, Great Clips, California Yogurt, and Subway;
Building 10 - Washington Mutual;
Building 11 - State Farm, H & R Block, Rachel Nicole's Salon, ShapeXpress, and a dentist;
Building 12 - Publix;
Building 13 - Winter Springs Liquors, Mailboxes, Etc., and Choice Cellular;
Building 14 - Papa Via's Take & Bake and China Feast; and
Building 15 - Wendy's.
Two commissioners, the City Manager, and the City's 2 planners attended the Urban Land
Institute's "Place Making" conference in Reston, Virginia, to learn more about town center
development. The Doran team also had a significant entourage at the conference.
per 11/10/03 agenda
Miranda - The applicant submitted a site plan on October 17,2002, and re-submittals on
December 24, January 29, and June 2. The staffDRC reviewed and provided comments at the
June 17,2003, staffDRC meeting. A request to amend the signage was denied at the June 23,
2003, commission meeting. The final engineering/site plan and development agreement
building rendering exhibit were approved at the August 11,2003, City Commission meeting
and a pre-construction meeting was held September 5. Revised site signage and a construction
sign were approved by the City Commission at the October 27,2003, meeting. per 11/10/03
agenda
Nursery Road (Phil Reece) - The City closed on the park properties on November 25, 2002.
The final engineering/site plan was submitted 10/30/03 and was discussed at the November II,
2003, DRC. per 12/08/03 agenda
Oak Forest Unit 7 (Triangular-shaped O.86-Acre Tract between Oak Forest & Tuskawilla
Office Park) Trees that the homeowners removed without a permit have not been replaced.
BJM Associates has submitted 2 draft plats and I boundary survey for preliminary review.
Staff met with BJM and reviewed the progress on the plat. BJM is in the process of having the
plat executed, which is complicated by the number of owners and mortgage holders. Staffhas
met with BJM and have provided necessary documentation to mortgage holders to help
expedite the re-plat. per 2/24/03 agenda
Parkstone - The FLU amendment was heard by the LP A at its September 3 and October I,
2003, meetings and had a transmittal hearing at the October 27,2003, City Commission
meeting. The applicant has had 2 pre-application conferences with the DRC to discuss a
subdivision plan submittal. per 12/08/03 agenda
November 10, 2003
Infonnalion Item 300
Page 4
SR 434 Retail(a.k.a. Villagio) - Vertical construction continues. One segment of the sanitary
sewer construction will not take place until building is to a point that the construction of the
last section of sanitary will not conflict with vertical facet construction. per 12/08/03 agenda
Tuskawilla Office Park - The City accepted water and sewer at the November 10,2003,
meeting. per 12/08/03 agenda
Tuskawilla Trails. - Mid-State (the subcontractor) has completed the direction bore for new
force main which originated at new phase and tied into existing sanitary system at the Avery
Park subdivision. Mid-State road crew is now in the process of bringing lots to grade and
hauling off the stock piled "unsuitable" material that was a result of the clearing process. This
had been put on hold until the owner and Mid-State could agree to the price tag the hauling
would incur. The water main boring that will cross Tuskawilla Rd. has still not taken place and
is not yet scheduled. per 12/08/03 agenda
Wagner's Curve (a.k.a. Heritage Park) - Home building has not yet begun. C. W. Meyer
(the site contractor) has formed and poured sidewalks within the development and leading out
to the crossing at SR 434. The Meyer crew is continuing to import fill and is grading out
building pad areas. Last week's site inspection generated a small punch list which was
forwarded to Meyer for resolution.
Centex has proposed an up-grade in fence material from vinyl to aluminum along a portion of
the west property boundary. The proposal will require amending the development agreement.
per 12/08/03 agenda
Winter Springs Elementary. - A memo has been sent to the City Attorney requesting
verification of the applicability of the City's sign and dumpster pad enclosure regulations on
school sites. The City Attorney has verbally opined that signage is subject to the City's
regulations. per 9/23/02 agenda
Winter Springs Elementary (New - located on SR 419) - A preliminary site plan for a new
elementary school, located generally northwest of the intersection of SR 434 and SR 419, was
submitted August 21 and reviewed on September 3, 2002, and again conceptually at the
January 7,2002, DRC. Other re-submittals were reviewed at the February 4 and May 20,
2003, DRC meetings. A Future Land Use designation amendment (from Industrial to
Public/Semi-Public) had a Transmittal Hearing at the June 9, 2003, City Commission meeting.
The final site plan was approved in conjunction with a letter of understanding and permission
to remove a number of specimen trees. per 7/14/03 agenda
Board of Adjustment - No new variance requests or conditional use requests have been
received for the BOA. per 12/08/03 agenda
FUNDING: None required
RECOMMENDATION: None required
ATTACHMENTS: None
COMMISSION ACTION: