REQUEST: The Public Works Department requests the City Commission validate the staff
recommendation finding Colonial Bank to be built in substantial accordance with the
Final Engineering plans
PURPOSE: The purpose of this Agenda Item is to request the City Commission validate the staff
recommendation finding Colonial Bank to be built in substantial accordance with the Final
Engineering plans per Section 9-178 in order for Certificates of Occupancy to be issued. The
site is located at the southwest corner of S.R. 434 and Vistawilla Drive.
APPLICABLE CODE:
Section 9-178. Required Improvements to be completed prior to building on lots; exceptions.
( c) Where the building official has an authoritative method of assurance that the improvements will
be completed in accordance with approved plans, such as withholding occupancy, the building
official may issue building permits upon advising the developer that all or partial occupancy will be
restricted until satisfactory completion of the improvements has be accomplished.
(d) ... Certificates of occupancy will not be issued until all improvements are accepted by the city
comnussIOn.
FINDINGS:
1) The site has been constructed in substantial accordance with the final engineering plans approved
by the City Commission at the March 13,2006 City Commission meeting.
2) All City agencies have found the work to be acceptable, except as noted below in the
recommended condition of approval.
092506_ COMM _ Consent_ 400_ Colonial_Bank _Acceptance
September 25, 2006
Consent Agenda Item 400
Page 2
3) The sitework complies with the applicable conditions of the Developer's Agreement approved by
the City Commission at the June 12, 2006 Commission meeting.
4) Colonial Bank has conveyed to the City the land along the S.R. 434 frontage necessary for a
future right-turn deceleration lane, per the terms of the Developer's Agreement.
RECOMMENDED CONDITION OF APPROVAL:
1) All landscaping and ground cover shall be complete and accepted by the City prior to issuance of a
Certificate of Occupancy
RECOMMENDATION:
Staff recommends that the City Commission validate the staff recommendation finding
Colonial Bank to be built in substantial accordance with the Final Engineering plans, subject to the
one condition listed above.
IMPLEMENTATION:
The Certificate of Occupancy can be issued after Commission approval.
ATTACHMENTS:
None
CITY COMMISSION ACTION: