HomeMy WebLinkAbout2006 04 24 Informational Item 501 Capital Improvement Projects
COMMISSION AGENDA
ITEM 501
CONSENT
INFORMATIONAL X
PUBLIC HEARING
REGULAR
April 24, 2006
Meeting
MGR./DEPT
Authorization
REQUEST: Public Works Department is advising the City Commission of the status of
various Capital Improvement Projects
PURPOSE: This agenda item is to update the Commission on the status of current
Capital Improvement projects.
CONSIDERATION:
TRAFFIC/TRANSPORTATION IMPROVEMENT
SR 434 Improvements (Village Walk) - Substantial Completion awarded on December 10,
2005. Contractor had 30 days to complete all remaining Punch List items before additional
liquidated damages are accessed. A walkthrough with FDOT performed January 12. CEI cost
has currently exceeded the contingency funds provided by the City from the 1999 One Cent
Sales Tax Agreements. Asphalt Stamping repair completed. Final resolution of Liquidated
Damages was tentative on the contractor completing the work. As of April 21, 2006, the
contractor has still not met requirements for completion. Contractor has agreed to replace
plant material damaged by frost as well as any material that had not returned to required
fullness. (4/21/06)
SR 434 Town Center Corridor Analysis - City received letters of support from Oviedo,
Longwood, and Seminole County which were forwarded to FDOT Secretary Stuttler April 5th as
requested. (4/19/2006)
SR 434/ Hayes Road Turn Lane - Design is complete and traffic accident information has been
forwarded to PEC for development of traffic study. Survey has been completed and city attorney
continues work for obtaining the needed Right of Way. (11/8/05)
SR 434 / Doran Drive Traffic Signal - Traffic Control Devices (TCD) has completed the
installation of the mast arm along with the pull boxes and conduit. Doran Drive paving is
complete. CFE attempting to locate pavers specified for the area on Blumberg that are
currently out of production. Scheduling the lane closures for removal of the concrete
apron median and asphalt is being coordinated with power being provided to the traffic
signals. Progress Energy has made connection for power to the traffic signal. (4/21/06)
April 24, 2006
Information Item 50 I
Page 2
Cross Seminole Trail Connector (Wade Street to Wekiva Trail) - County staff are reviewing
constructing the "temporary trail alignment" on Old Sanford-Oviedo Road as discussed at the
March 27th City Commission meeting. (4/24/06)
Magnolia Park Phase II - Phase II of Magnolia Park consists of the construction of the
Amphitheater with restrooms and drinking fountains to act as a trail head for the Cross Seminole
Trail and an inter active water feature in this 0.67:1:: acres. Starmer Ranaldi Planning and
Architecture, Inc (SRI) was approved by the Commission on January 10, 2005, for the
architectural services. CPH Engineers, Inc has been authorized by the Commission under
Amendment 78 on June 9, 2003, for services related to the landscape and hardscape design in
conjunction with SRI. Both SRI and CPH Engineers are currently developing the plans for the
construction of Magnolia Park Phase II. City property has been surveyed and comers marked.
Environmental consultant is evaluating wetland impact if trail is shifted. Property has been bush
hogged to give depth perspective for plan development. (3/21/06)
Blumberg Boulevard Trail - The Blumberg Boulevard Trail consist of the construction of the
trail with amenities from Magnolia Park to the intersection of Blumberg Boulevard and Doran
Drive. The trail will have stone pavers with sitting arboretum and proposed sculpture gardens, to
include the Rotary Club sponsored Veterans Memorial. Starmer Ranaldi Planning and
Architecture, Inc (SRI) was approved by the Commission on January 10, 2005, for the
architectural services. CPH Engineers, Inc has been authorized by the Commission under
Amendment 78 on June 9, 2003, for services related to the landscape and hardscape design in
conjunction with SRI. Plans are 100% complete. Copy of plans has been submitted to State
StafTfor review. (4/21/06)
Central Winds Park Way - Final road design ongoing by CPR. Additional right of way has
been requested from the Leerdam property and they will be submitting a conceptual site plan to
the City Commission. Final Plan review will incorporate their proposed site plan. (4/18/05)
Winter Springs Boulevard Reconstruction - 30% plans were reviewed and commented on in
March. Projected Schedule:
. 60% submittal- May 12, 2006
. Bid Advertisement - July 2, 2006
. Bid Award - September 11, 2006
Final Plans - June 9, 2006
Bid Opening - August 16, 2006
Start construction - October 2006
Village Walk Beautification Phase II Trees - Project Complete. (3/21/06)
SR 434 Beatification Trees and Curbing - Completing plan design by CPH pending funding
becoming available for plan to be submitted for FDOT Highway Beautification Grant (1/13/06)
Orange Avenue Extension - Initial scope development under consideration by Staff (1/13/06)
UTILITY
April 24, 2006
Information Item 501
Page 3
Utility/Public Works Compound - As of March 17 all trees have been cleared and contractor in
process of hauling debris from site. Building permits pending. Site final grading being
performed. Underground work scheduled to start last week of April. (4/21/06)
Well #4 - Well development complete. Installation of 12" water line complete. Pump
installation and electrical remaining. (3/20/06)
Reclaimed Water Augmentation - Phase I of the project has been included in the FY2007-
FY2010 SJRWMD grant funding for a total of $2.42 million. CPR engineers will be
submitting the Consumptive Use Permit for withdrawing from Lake Jesup by May 31.
( 4/24/06)
Electrical Improvements WTP #3 - Recommendation for contract award presented to
Commission on February 27, 2006 for award of contract to Florida Industrial Electric (FIE) for
$281240.00. Awaiting scheduling of Pre-Construction meeting. (3/20/06)
Village Walk Overhead Utility Under grounding - Cost received by Progress Energy on August
5, 2005, Progress Energy provided staff with the cost to convert Progress Energy's lines from
overhead to underground. The cost was $403,017.00. Additional cost may be incurred to provide
property owners that have parking lot lighting installed on the power poles with an alternative
lighting solution. The cost provided by Progress Energy does not include the cost to bury other
utility lines. The cost to bury these lines is usually 50% to 75% of the cost to convert the power
lines. There are up to four other utilities with lines on the Progress Energy poles. The estimated
cost to convert these lines is $806,032 to $1.2 million. Total cost to convert the overhead utility
lines to underground is $1.2 million to $1.6 million. (1/13/16)
PUBLIC BUILDINGS
City Hall Expansion - The design of the expansion of City Hall was approved by the
Commission on February 28, 2005. Starmer Ranaldi Planning and Architecture, Inc (SRI)
provided the design of this 4,980 square foot addition to City Hall in the northwest corner of the
City Hall building. New layout presented to Commission at 8/1 workshop and direction
received. 40% Plans presented to staff for comments week of January 3. SRI anticipates plans
to be ready for final review in time to advertise in May-June. (3/20/06)
PARKS AND RECREATION
Senior Center Therapy Pool - Commission approved moving forward with design to enclose the
pool March 13,2006. (3/21/06)
FIRE DEPARTMENT
Fire Station House #28 - Initial conceptual site layout proposal received 4/14/06. (4/24/06)
COMMISSION ACTION:
Exhibit 1 - Legacy Park Vicinity Map
Exibit 2 - Lake Drive Project Map
Exhibit 3- Legacy Park Trip Distribution