REQUEST: The Parks and Recreation Department is requesting the City Commission consider
phasing the Trotwood Park Project or provide other direction.
PURPOSE:
This agenda item is needed for the City Commission to determine if it
desires to phase the Trotwood Park Project or provide other direction
because of escalating project costs and the shortfall in Park Impact Fees.
CONSIDERATIONS:
· On July 24, 2006 the City Commission approved the execution of a FRDAP Grant for
Trotwood Park for $ 200,000. The project budget estimated to be $ 500,000 was done in
2005.
· CPH has done several current cost estimates of the proposed project and staff has
reviewed ways to reduce current costs and phase the project.
· There is currently $ 446,160 available for the project however; $ 232,700 is pledged from
Park Impact Fees which is not yet received. In fact no impact fees have been received
since May, 2007.
· The project needs to go out to bid this fall and be awarded in early 2008 in order to have
the Splash Playground open by the summer of 2008. Also these improvements in phase I
will insure that the city will receive the $ 200,000 matching FRDAP Grant prior to the
2009 grant deadline.
Phase I
Splash Playground
Pump House
Restroom/Storage Renovation
Pavilion
Total
$ 198,655
$ 35,035
$ 74,965
$ 55.600
$ 364,255
Agenda Item
Regular 604
Page -2-
Phase II
Parking Lot, Drainage, Demo
Total
$ 322,491
Phase III
4 New Tennis Courts
2 Playground Resurfacing
2 Playground Shade Structure
Total
$ 205,903
$ 85,450
$ 52,544
$ 343,897
Estimated Project Total
$ 1.030.643
. Staff and CPH are ready to prepare Phase I to go out for bid and will bring back to the
City Commission the bids, recommendation and firm construction costs.
. Phase II is still being permitted with St. John's Water Management.
. Phase II and Phase III may be budgeted in future FY's.
FUNDING:
No additional funding authority is needed at this time.
RECOMMENDATIONS:
The Parks and Recreation Department recommends that the City Commission decide if it desires
to phase the Trotwood Park Project or provide other direction.
ATTACHMENTS:
Attachment # 1
CPH and staff current cost estimates.
COMMISSION ACTION:
PHASE 1
Trotwood Park Improvements Date: 10/2/2007
Winter Springs, FL By: ACL
CPH Project number W04132 Checked by: ACL
Opinion of Probable Cost
Phase I - Splash pad and appurtenances Construction
Quantity Unit Unit Cost Current Total
Sitework
Mobilization (10% of sub-total) LS $15,299.55
Clearing and Grubbing 1 LS $5,000.00 $5,000.00
Silt Fence, Staked (Type Ill) 405 LF $2.00 $3,616.00
Sod Distrubed Areas 45 SY $2.00 $90.00
Sub-total $8,706.00
Flatwork
Remove sidewalk 40 LF $10.00 $400.00
4" Thick Concrete Sidewalk 40 LF $20.00 $800.00
Sub-total $1,200.00
Splash pad
Concrete pad (6" thick) 315 SY $40.00 $12,600.00
Piping, pumps, appurtenances * 1 LS $60,032.00 $60,032.00
Fog Feature · 1 LS $31,120.00 $31,120.00
Hose bib 1 EA $750.00 $750.00
6 inch Gravity Sewer Line 100 LF $20.00 $2,000.00
Connection to existing on-site lift station 1 EA $2,000.00 $2,000.00
Gravity Sewer Clean Outs 2 EA $250.00 $500.00
1" Water Line 105 LF $12.50 $1,312.50
Supply lines from Equipment room to Splash
Pad Spray Features 1200 LF $12.50 $15,000.00
Connection to existing water main 1 EA $1,000.00 $1,000.00
Footwash and Shower · 1 EA $1,500.00 $1,500.00
Shower Return Drain 1 EA $250.00 $250.00
Trench Drain and Grate (at splash pad) 50 LF $25.00 $1,250.00
8" Drain Line (from spalsh pad) 80 LF $30.00 $2,400.00
Waste Receptical 1 EA $250.00 $250.00
4' Decrative Aluminum Fence 125 LF $25.00 $3,125.00
Metal Benches 8 EA $1,000.00 $8,000.00
Sub-total $143,089.50
Project sub-total $152,995.50
Mobilization $15,299.55
PROJECT BASE TOTAL $168,295.05
Additive Alternates
6' Sidewalk Around Perimlter of Splash Pad 210 LF 30.00 $6,300.00
Additional Benches Around Splash Pad 6 EA 1,000.00 $6,000.00
$12,300.00
Total Base Project and Alternates $180,595.05
10% for incidentals (colltingencies) $18,059.51
PROJECT TOTAL $198,654.56
Notes:
Estimate does not include cost for buildings (restroom, pavilion, pump room)
. Splash pad and fog system based on quotes from suppliers
OPC-Trotwood Park 9-21-07.xls
OPINION OF PROBABLE COST- PUMP HOUSE FACILITY (264 SF)
Trotwood Park Improvements
Winter Springs, Florida
CPH Project Number W04132
EXCAVATION:
Foundation
Sub-Total
CONCRETE:
Floor Slabs
Sub-Total
MASONRY:
Concrete Masonry Units
Brick
Sub-Total
CARPENTRY:
Wood Trusses
Sheathing
Underlayment
Sub-Total
DOORS:
Walk Door
Sub-Total
MOISTURE PROTECTION:
Metal Standing Seam Roof
Soffit and Fascia
Sealants
Sub-Total
MEP:
Lighting
Ventilation
Eyewash Station
Sub-Total
Total Approximate Cost
10% For Incidental (Contingencies)
Project Total
$10,500.00
$ 8,400.00
$2,000.00
$ 600.00
$ 600.00
$4,500.00
$ 700.00
$ 400.00
$ 300.00
$ 500.00
$ 750.00
$ 750.00
$ 1,100.00
$18,900.00
$ 3,200.00
$ 750.00
$ 5,600.00
$ 1,550.00
$31,850.00
$ 3,185.00
$35.035.00
Sept. 27th, 2007
1
OPINION OF PROBABLE COST- STORAGE I RESTROOM FACILITY
(REMODEL)
Trotwood Park Improvements
Winter Springs, Florida
CPH Project Number W04132
DEMOLITION:
Walls, Partitions Etc.
Sub-Total
CONCRETE:
Floor Slabs
Sub-Total
MASONRY:
Concrete Masonry Units
Brick
Glass Block
Sub-Total
CARPENTRY:
Stucco I Wood Framing
Sub-Total
DOORS:
Walk Doors
Coil Door
Sub-Total
FINISHES:
Paint
Tile
Sub-Total
SPECIAL TIES:
S.S. Counters
ADA Signage
Diaper Changing Station
Toilet Partitions
Sub-Total
$6,300.00
$4,750.00
$4,000.00
$1,800.00
$2,000.00
$3,100.00
$6,500.00
$ 800.00
$ 200.00
$ 600.00
$3,600.00
$3,500.00
$3,500.00
$15,050.00
$6,000.00
$3,800.00
$7,600.00
$5,200.00
Sept. 2ih, 2007
1
Trotwood Park
MECHANICAL, ELECTRICAL AND PLUMBING
Mechanical
Electrical
Plumbing
Sub-Total
Total Approximate Cost
10% Incidental (Contingencies)
Project Total
$ 5,500.00
$ 4,000.00
$14,000.00
$23,500.00
$68,150.00
$ 6,815.00
$74.965.00
2
OPINION OF PROBABLE COST- PAVILION (580 SF)
Trotwood Park Improvements
Winter Springs, Florida
CPH Project Number W04132
SITEWORK:
Clear and Grub
Excavation
Sub-Total
CONCRETE:
Floor Slab
Column's with Masonry Trim
Sub-Total
METALS:
Tube Steel Trusses
Anchor Plates
Sub-Total
CARPENTRY:
Eng. Lam. Wood Beams
Cedar Framing
Hangers
Sheathing
Sub-Total
MOISTURE PROTECTION:
Underlayment
Metal Standing Seam
Sub-Total
ELECTRICAL:
Light and Power Outlet
Total Approximate Cost
10% for Incidental (Contingencies)
Project Total Cost
$ 500.00
$2,000.00
$2500.00
$2,000.00
$9,000.00
$11,000.00
$6,000.00
$ 600.00
$6,600.00
$9,000.00
$5,000.00
$ 750.00
$1,200.00
$15,950.00
$1,200.00
$10,800.00
$12,000.00
$2,500.00
$50,550.00
$ 5,050.00
$55.600.00
Sept. 27th, 2007
PHASE II
Trotwood Park Improvements
Winter Springs, FL
CPH Project number W04132
Date: 10/2/2007
By: ACL
Checked by: ACL
Opinion of Probable Cost
Phase II - Parking Lot Construction
Quantity
Unit
Unit Cost
Current Total
Sitework
Mobilization (10% of sub-total)
LS
1 LS $8,000.00
2,228 SY $10.00
22 SY $10.00
170 LF $10.00
5 EA $2,500.00
1 EA $3,000.00
540 LF $25.00
390 LF $30.00
1 EA $1,000.00
1 EA $1,000.00
3 EA $500.00
Clearing and Grubbing
Turbidity Barrier, Floating
Silt Fence, Staked (Type III)
Maintenance of Traffic
Sod Distrubed Areas
Sub-total
1
261
1,808
1
1238
LS
LF
LF
LS
SY
Demolition
Remove handball courts
Remove existing stabilized parking / drive
Remove concrete driveway appron
Remove sidewalk
Storm Drainage
FOOT Type C Inlets
Pond Out fall Structure
15" RCP Pipe
18" RCP Pipe
18" Miltered End Section
15" FDOT U-lype Endwall
Concrrete Rubble at MES in pond
Sub-total
Pavement
Sub-base for new pavement (12")
Limerock base (6")
Asphalt pavement
Concrete Valley Gutter
Striping and signage
Wheel Stops
4" Thick Concrete Sidewalk
Handicap Ramps
Concrete Flatwork
Saw cut exist pavement
Sub-total
2830
2795
235
80
1
51
175
2
7
178
SY
SY
TN
LF
LS
EA
SY
EA
SF
LF
Existing on-site Force Main
Sleeve and Adjust Existing FM
260
LF
Project sub-total
Mobilization
PROJECT BASE TOTAL
10% for incidentals (contingencies)
PROJECT TOTAL
$26,652.16
$5,000.00
$25.00
$2.00
$5,000.00
$2.00
$5,000.00
$6.525.0C>
$3,616.00
$5,000.00
$2,476.00
$22,617.00
$8,000.00
$22,280.00
$220.00
$1,700.00
$32,200.00
$12,500.00
$3,000.00
$13,500.00
$11,700.00
$1,000.00
$1,000.00
$1,500.00
$44,200.00
$5.00
$15.00
$220.00
$25.00
$6,000.00
$250.00
$54.00
$500.00
$54.00
$100.00
$14,150.00
$41,925.00
$51,651.60
$2,000.00
$6,000.00
$12,750.00
$9,450.00
$1,000.00
$378.00
$17,800.00
$157.104.60
$40.00
$10,400.00
$266,521.60
$26,652.16
$293,173.76
$29.317.38
$322,491.14
Notes:
Estimate does not include cost for buildings (restroom. pavilion, pump room)
* Splash pad and fog system based on quotes from suppliers
Cost also includes all storm piping from pond to Lake Tuskawilla. This cost may not be part of the site development
based on comments from Water Management District.
OPC- Trotwood Park 9-21-07.xls
PHASE III
Trotwood Park Improvements
Winter Springs, FL
CPH Project number W04132
Opinion of Probable Cost
Phase III - Tennis Court Construction
Sitework
Mobilization (10% of sub-total)
Clearing and Grubbing
Silt Fence, Staked (Type III)
Sod Distrubed Areas
Remove tennis courts
Swale grading
4" Thick Concrete Sidewalk
Tennis Court Construction
Tennis Court, 1" Asphaltic Concrete
Tennis Court, 6" Iimerock base
Tennis Court, 12" sub-base
12 foot high chain link fence
4 foot swing gates
Tennis court striping and appurtenances
Project sub-total
Mobilization
PROJECT BASE TOTAL
10% for incidentals (contingencies)
PROJECT TOTAL
OPC-Trotwood Park 9-21-07.xls
Date:
10/2/2007
By: ACL
Checked by: ACL
Quantity Unit Unit Cost Current Total
1 LS $17,016.80
1 LS $5,000.00 $5,000.00
1,808 LF $2.00 $3,616.00
50 SY $2.00 $100.00
1467 SY $10.00 $14,670.00
1 LS $2,500.00 $2,500.00
83 SY $54.00 $4,482.00
180 TN $220.00 $39,600.00
3,200 SY $15.00 $48,000.00
3,280 SY $5.00 $16,400.00
720 LF $40.00 $28,800.00
2 EA $1,000.00 $2,000.00
1 LS $5,000.00 $5,000.00
$139,800.00
$170,168.00
$17,016.80
$187,184.80
$18,718.48
$205,903.28
Chuck Pula
From: Jeff Caldwell [mailto:jeff@repservices.com]
Sent: Wednesday, September 26, 2007 2:47 PM
To: Alan Greene
Subject: RE: price for the forever lawn
Yes, here it is.
$77,682.00 plus 10% contingency is $7,768= Total $85,450
This is completely supplied and installed. The site prep work is up to you to remove the old
mulch and get the grade just right with fill and flattening.
If for some reason you cannot do any site work this would probably cost between 4,000 and
5,000 in labor.
In addition, the surfacing is under the Jax contract so it can be purchased very easily. If you get a
chance to go and see Masters Academy new playground, take Chuck and I'll meet you there. We
just put down 9,000sqft of playground grass on their new play environment featuring an Evos.
See ya,
Jeff
From: Alan Greene [mailto:agreene@winterspringsfl.org]
Sent: Wednesday, September 26, 2007 9:39 AM
To: Jeff Caldwell
Cc: Chuck Pula
Subject: price for the forever lawn
Hello,
Also, we are looking into maybe doing the Trotwood artificial turf in the forever lawn stuff instead
of poured in place.
I don't know if you still have the measurements from before but here they are:
2-5 age area 72,912 sq ft
5-12 age area 74,150 sa ft
Total 77,062
And do you need concrete for this? I don't think you do but we need it stabilized.
Thank you and I look forward to the price for this material.
Thanks,
Alan Greene
City of Winter Springs
Parks & Recreation Operations
Superintendent Parks and Grounds
Off: 407-327-6592
Fax: 407-327-4763
REP SERVICES
Exoerts at Plav & Outdoor Soaces
Please mail checks to:
Rep Services, Inc.
902 Waterway Place
Longwood, FL 32750-3573
PROPOSAL.
Qty Part No. Description Unit Wt Unit Price Ext. Weight Ext. Price Class Discount
Shade Systems, Inc.
1 CP-TROTWOOD
50' x 50' Mega Span Shade System, 10' high, powder-coated metal
Shade Structures $19,696.00
1 CP-TROTWOOD 20 20' x 30' Rectangular Shade System,
10' high, powder-coated metal $7,196.00
Global Discount Applied: 3.00% ($806.76)
Subtotal Shade Systems, Inc. $26,892.00
Equipment Subtotal Total $26,085.24
Other Charges: Sealed Eng. Dwgs: $1,694.00 :
Equipment Installation: $17,403.43, Permitting: $1,210.00:= Total $18.613.43
Freight Charge: $1,380.00
We are pleased to provide you with this proposal.
If you have any questions, please contact us at:
Equipment Subtotal:
Grand Total: $47,772.67
10% Contingency $4,772
Total $52.544.67
With all global discounts and costs included
ALL PO's AND CONTRACTS SHOULD BE SUBMITTED AS NOTED IN THE HEADERI
REP SERVICES, INC. . 902 Waterway Place' Longwood, FL 32750-3573 . 407.831.9658 (P) .
407.834.5366 (F)
800.992.5357 . Offices Statewide' www.repservices.com
~
Proposal No: 26808 Page 2 of 2 Proposal To: City of Winter Springs
Proposal Dated: 2/16/2007 Project 10: 453 Option: B Revision: 1
IN ADDITION, ORDERS PLACED BASED ON THIS PROPOSAL ARE SUBJECT TO MANUFACTURER'S STANDARD
LEAD TIME. REQUESTS
FOR EXTENDED SHIPPING TIMES MAY RESULT IN ADDITIONAL COSTS, SUCH AS FREIGHT INCREASES, RAW
MATERIAL COST
INCREASES, ETC.
Shipping Notes: FREIGHT COMPANY MUST CALL 24 HOURS PRIOR TO DELIVERY: Alan Greene 407-327-6592
To order, please sign below and return to Rep Services Inc. at the address or fax number noted below. Thank You.
Name Date
We are pleased to provide you with this proposal.
If you have any questions, please contact us at:
REP SERVICES, INC.' 902 Waterway Place' Longwood, FL 32750-3573' 407.831.9658 (P).
407.834.5366 (F)
800.992.5357 . Offices Statewide' www.repservices.com