REQUEST:
The Community Development Department informing the Commission of the timing of the Cross
Seminole Trail bridge over S.R. 434.
PURPOSE:
The purpose of this agenda item is to bring the Commission up to date on the status of the
ISTEA - Intermodal Surface Transportation Efficiency Act grant approved to design and build a
pedestrian overpass over S.R. 434 and to request that the Commission authorize the City
Manager to sign contracts totaling $34,625 for appraisals and surveys of the realigned trail
segments.
CONSIDERATIONS:
. On March 25, 1998, Congressman John L. Mica notified Winter Springs that $1,678,000
has been authorized to design and construct a pedestrian overpass over State Road 434.
. The design and construction of the pedestrian bridge is funded by FDOT through the Local
Agency Program (LAP). In order to receive money from FDOT, the County must have an
executed LAP agreement. In order for FDOT to execute the LAP agreement, all of the
rights of way needed to construct the project must be finalized.
. There are two significant dates. The first is the date the LAP contract is executed by the
County and FDOT. Since the money is funded in FDOT's Fiscal Year 1999/2000, which
CDD/Apri13, 2000/1:52 PM
APRIL 10, 2000
REGULAR AGENDA ITEM F
Page 2
ends June 30, 2000, it is important that the agreement is executed by this date. This means
that the money has been available since July 1, 1999, but we have not used it. While the
money can be rolled over into the next fiscal year, FDOT would be penalized on their
performance review as missing a contract date. This make:s it difficult for local agencies to
appeal to FDOT for future money and control over local pmjects.
. The County can get an executed LAP agreement by June 30, 2000 from FDOT by certifying
the existing trail right of way. Once we have the preferred trail/bridge rights of way, the
County can request that FDOT re-certify the new rights of way. However, we cannot
advertise the designlbuild contract until we have the prefelTed rights of way owned and
certified by the state.
. The second date of concern is the LAP contract expiration date, which is March 31, 2002.
We must have the bridge completely designed and constructed by that date. While we can
request an extension from FDOT, it is not guaranteed that they will grant it. Again, a delay
may bring into question the County's ability to manage LAP projects. In order to complete
the bridge by March 31, 2002, we need the preferred right of way in hand by early August
2000. This allows only four months for the City to receive: the necessary approvals to move
the trail bridge location and get the deeds for the rights of way.
. It is imperative that Winter Springs finalize the trail realignment agreements with the
property owner and the State as to the trail bridge location as soon as possible so that the
County can advertise, design and construct the bridge.
. The Governor and Cabinet do not meet in August, so July 25, 2000 is the critical meeting.
There is a 10 week review period in Tallahassee after the survey and appraisals are
complete. Therefore, all surveys and appraisals must be complete no later than May 12,
2000.
FUNDING:
Appraisals and surveys for the project will cost $34,625. The source of funds will be
appropriations from the general fund balance.
STAFF RECOMMENDATION:
It is recommended that the City Commission authorize the City Manager to advance funds for
immediate appraisals and surveys for the Town Center trail realignment.
CDD/April 3, 2000/1:52 PM
APRIL 10,2000
REGULAR AGENDA ITEM F
Page 3
ATTACHMENTS:
A. Letter from Heather Bradshaw-Ellis, P.E., Seminole: County Engineer
B. Bid results - Trail Relocation
COMMISSION ACTION:
CDD/ApriI3, 200011:52 PM
ATTACHMENT A
ENGINEERING DIVISION
~
SEMINOLE CoUNTY
f'LOIIIDA'S NATUrw. CHOICE
PUBLIC WORKS DEPARTMENT
March 30, 2000
RECEBVED
Mr. Charles Carrington
City of Winter Springs
Community Development Director
1126 East SR 434
Winter Springs, FL 32708-2799
,.\ f)f) 0 ... 2"0"
t--\ ,\ j _U U
CITY OF WINTER SPRINGS
Community Development
Subject:
. .
C!'o55 Seminole Trail Bridge over SR 434
Dear Mr. Carrington:
I am writing to clarify any misunderstanding concerning the timing of the Cross Seminole Trail
Bridge over SR 434.
The design and construction of the bridge is funded by FDOT through the Local Agency Program
(LAP). In order to receive money from FDOT, we must have an executed LAP agreement. In
order for FDOT to execute the LAP agreement, we must have all of the right of way needed to
construct the project in hand.
There are two significant dates. The first is the date the LAP contract is executed by the County
and FDOT. Since the money is funded in FDOT's Fiscal Year ][999/2000, which ends June 30,
2000, it is important that we execute the agreement by this date. This means that the money has
been available since July 1, 1999, but we have not used it. While the money can be rolled over
into the next fiscal year, FDOT is penalized on their performance review as missing a contract
date. This makes it difficult for local agencies to appeal to FDOT for more money and control
over local projects.
However, we can get an executed LAP agreement by June 30, 2000 from FDOT by certifying the
existing trail right of way. Once we have the preferred traillbridge right of way, we can request
FDOT re-certify the new right of way. However, we cannot advertise the design/build contract
until we have the preferred right of way in hand and certified.
The second date of concern is the LAP contract expiration date, which is March 31, 2002. We
must have the bridge completely constructed by that date. While we can request an extension
from FDOT, it is not guaranteed that they will grant it. Again, a delay may bring into question
our ability to manage LAP projects. As you can see from the: attached schedule, in order to
complete the bridge by March 31, 2002, we need the preferred right of way in hand by early
August 2000. This allows a mere four months for the City to receive the necessary approvals to
move the trail bridge location and get the deeds for the right of way.
Therefore, it is imperative that Winter Springs get the necessary agreements from the property
owner and from the State as to the trail bridge location as soon as possible so that we can
advertise, design and construct the bridge.
520 West lake Mary Boulevard Suite 200 Sanford fl 32773-7424 Telephone (407) 665-5674 fax (407) 665-5789
Letter to Mr. Carrington
March 30, 2000
Page 2
Please call me at (407) 665-5657 if you have any questions.
Sincerely,
dJ.~~-~
Heather Bradshaw-Ells, P.E.
Principal Engineer
Enclosure
cc: Ginger: Hoke, County Planning
David Martin, Principal Engineer (Trails)
Jerry McCollum, County Engineer
John Moore, Major Projects/Principa1 Engineer
Marianne Takacs, FDOT Planning
Vince Vacchiano, FDOT LAP
Cross Seminole Trail Bridge
over SR 434 (Winter Springs)
3/30100
LAP Agreement signed BCC
4/25/00
RIW certified by FDOT
(Existing Trail RIW)
4/25/00
LAP Agreement signed FDOT
5/19/00
Preferred R/W acquired by
Winter Springs
8/7/00
RIW Re-Certified by FDOT
8/21/00
Advertise Design/Build Contract
9/3/00
Open proposals & shortlist; 3 firms
will be chosen to prepare 15% plans
as proposals
9/27/00
Review 15% plans proposals, select firm
12/8/00
Recommend firm to BCC for approval
And begin contract negotiations
1/9/01
Negotiated contract with BCC for
Notice to proceed
2/13/01
Selected firm begins final design, construction
2/28/01
Project complete
3/31/02
NOTE:
Project is subject to all StateIFederal criteria for design and right-of-way
and construction. FDOT and FHW A must approve design in stages. This
assumes FHW A is responsive to review times and no unforeseen issues
occur. Assumes no major utility relocations.
All work must be completed by LAP Agreement expiration date of March
31,2002.
ATTACHMENT B
Surveying Services
Tinklepaugh
BID RESULTS
Appraisal Services
Clayton, Roper & Marshall
Total
$27,000
$ 7,625
$34.625