ITEM 601
March 24, 2008
Meeting
CONSENT
INFORMATIONAL
PUBLIC HEARING
REGULAR X
MGR /DEPT ,~/ i~
Authorization
REQUEST: Public Works Department requesting the City Commission's authorization to
enter into an agreement with J. Raymond Construction to remove a portion
of an existing block wall from the public sidewalk along SR 434 at Jesup's
Reserve
PURPOSE: The purpose of this agenda item is to request the City Commission's authorization
to enter into an agreement with J. Raymond Construction for $9,500 to remove a
portion of an existing block wall from the public sidewalk along SR 434 at
Jesup's Reserve.
CONSIDERATIONS:
• Levitt & Sons, the builder for Jesup's Reserve, was required by Developer's Agreement
to construct a 6-foot screen wall along the western property line of the subdivision,
immediately adjacent to the recently constructed West End Center office building
property.
• Levitt & Sons obtained a building permit for the 6-foot screen wall, and the wall has been
constructed but not accepted by the City (see Exhibit A). The wall was not constructed in
accordance with the building permit or the approved final engineering plans for Jesup's
Reserve. As constructed, the wall encroaches into the 10-foot wide sidewalk easement
along SR 434 frontage, an area that was to be reserved for the public sidewalk.
• The 10-foot wide public sidewalk along the Jesup's Reserve and West End Center SR
434 frontage is located within the first 10-feet of each property, outside of the FDOT
right-of--way.
• The City notified Levitt & Sons in August 2007 that the end of the wall was built
approximately 10-feet closer to SR 434 than was shown on the approved plans. Levitt's
field representative acknowledged the error and agreed to modify the wall at Levitt's
032408_COMM_Regular_601_Remove Wall from Public Sidewalk at Jesups Reserve
Agenda Item 601
March 24, 2008
Page 2
expense per the approved plans. However, in October 2007, Levitt & Sons abandoned
Jesup's Reserve and the wall has not been modified as required.
• In October 2007, the City prepared a punchlist of incomplete and/or incorrectly
constructed items and initiated the legal process to have these items completed under the
performance bond on file at the City. As of March 17, 2008, the extent and timing of the
work that can be completed under the performance bond claim is unknown.
• As currently constructed, the wall encroaches into and significantly obstructs the 10-foot
wide public sidewalk (see Exhibit A). The wall conflict has prevented the West End
Center contractor from completing the 10-foot wide sidewalk connection between Jesup's
Reserve and West End Center as planned. The continuity of the 10-foot wide sidewalk
and the planned double row of trees is an essential component of the design for both
Jesup's Reserve and West End Center. Since this is the public sidewalk, Staff
recommends removing the wall at the City's expense and pursuing reimbursement
through the performance bond claim or through direct reimbursement from the Jesup's
Reserve developer.
• Staff requested and received a price of $9,500 from J. Raymond Construction to repair
the wall and bring it into compliance with the approved Jesup's Reserve plans. J.
Raymond is the current general contractor for the West End Center. The work generally
consists of demolishing the final 10-feet of the existing wall and constructing a stone
column at the new end of the wall. Construction necessary to complete the sidewalk
connection and make up the grade differential between Jesup's Reserve and West End
Center is entirely the responsibility of the West End Center development and is not being
funded through this request.
• The wall is located in a sidewalk easement dedicated to the City by the Jesup's Reserve
plat. All work will be performed within the sidewalk easement.
FUNDING:
The funding source for this repair to the public sidewalk is the Roadway Improvement Fund,
#115. Staff intends to pursue reimbursement for the full $9,500 through the performance bond
claim for Jesup's Reserve or through direct reimbursement from the Jesup's Reserve developer.
RECOMMENDATION:
Staff recommends approving $9,500 to remove the portion of the wall interfering with the public
sidewalk.
ATTACHMENTS:
1. Exhibit A -Photo of Wall to be Removed
032408_COMM_Regular_601_Remove Wall from Public Sidewalk at Jesups Reserve
Agenda Item 601
March 24, 2008
Page 3
2. Exhibit B -Design Drawing Showing Wall Location
3. Exhibit C -Proposal from J. Raymond Construction
COMMISSION ACTION:
032408_COMM_Regular_601_Remove Wall from Public Sidewalk at Jesups Reserve
~.
:~
~' ~ ~'T.~
~. ~="
~`
. ~x'~'t~, ,~ #.
._ ~ iii ~r ~ -~ - •~6S ~ ~. ~
~~~-. i
- 's • i
~~ - ~ r
Move Wall Out of
Sidewalk to Here _,_~ _ -. - oo u
per Plans = ~ -~-_ ~1 Sidewalk _
Across Plaza
- ~ -~-- _
~~-Te
10-foot Permanent Public Sidewalk ~~ ";•'"=°~~"• ~`°' ~~'~
Across Jesup s Reserve Frontage -,+,~:.::.~,~^Y~~.~~%~
`,., `~
~orary Sidewalk
EXHIBIT B
S . R. 434
~; ~ j~~ - ; ~ ~- urr y ~
. - ,.
!.-~- w--.~.-~---~. ! `~- ~ C stru ed
-, ~ - . -~ -~ v,. `~
- ;~~~ _ ~-
_ - _
- -- , ,~ _ -
. _.
y_
~~ ~ dry.,-i ~-_ i.-i-__.._. ~,. __ _ ,~,_ i~' _ - a ,`T'-+r~^ w ~ {,;t-,« ,--~~;~a...'ae+l+ ~..-~--~r--...,.'•~''~'`~ Ij!s ~ ~ _.
f
- ..
..
~' - ~ a
f __ _ 4. ., .. _ -- ~ ~ i
~.
q ~ K
_ 3
,,. ~ - <
.:-- ,m ,.
1. ,.. •. . ~ .__ t__~J
West .End Center _ -~
_` i .. ,. .....
,~ ~ .e - ~' ~.. w i
~ ~-•.l 1
EXHIBIT C
'West End / Jesup's Reserve Sidewalk /Wall Demo
Construction cost estimate J Raymond Construction
465 West Warren Avenue
Revised :3/17/2008 Longwood Florida 32750
Per Existing Conditions Contact: Scott Bryan
407-948-3384
Demolition
remove column, footer, and wall (10 If)
demo and remove existing sidewalk
(approx 500 SF?)
Repair /compact subgrade
Surveying & Layout
New column and footer
concrete foundation
masonry column (rebar and filled cell)
cultured stone veneer (match existing)
precast cap (match existing)
Patch stucco finish and wall cap (both sides)
J.RAti'MONO
C ON iTl~ U CTI ON
cost Subtotal Total
1 EA $900.00 $900.00
1 EA $750.00 $750.00
1 EA $500.00 $500.00
1 EA $250.00 $250.00
1 EA $500.00 $500.00
1 EA $750.00 $750.00
1 EA $500.00 $500.00
1 EA $250.00 $250.00
1 EA $750.00 $750.00
repair sod 1 LS
relocate irrigation heads 1 LS
General Contractor supervision 5 days
General Contractor general conditions 5 days
Construction subtotal
Overhead and profit 10
Project total
"""' Design, and materials er existin Cit a
,,*, P g y pproved plans (need copy)
JRCC not responsible for engineering or design
$536.00 $536.00
$200.00 $200.00
$0.00
$300.00 $1,500.00
$250.00 $1,250.00
$8, 636
$864
$9,500