COMMISSION AGENDA
ITEM
A
REGULAR
CONSENT X
INFORMATIONAL
March 24. 1997
Meeting
MGR IAEPT ILl-
Authorization
REQUEST: Public Works/Stormwater Division Requesting Authorization to Enter Into a
Contract Agreement for Orange Avenue Drainage and Roadway
Improvements
PURPOSE: The purpose of this Board item is to request authorization to enter into a contract
agreement with Esterson Construction Company, Inc. for Orange Avenue
Drainage and Roadway Improvements at a cost of$184,375.00 plus 10%
contingency.
CONSIDERATIONS:
This project is needed to address the degrading effects the runofffrom Central
Winds Park has on Orange Avenue. This impact was most notable in July, 1995 when a
five inch storm event created two to three foot deep washouts on Orange Avenue. Three
vehicles were stuck and an Orange Avenue resident suffered property damage from the
runoff. The resident is positioned to litigate with the City if improvements are not made.
The scope of work for this project is a stormwater piping system with connections
to the park overflow points, raising the road grade to its approximate level prior to the
park, establishing a stabilized subbase, and a 1~" asphaltic surface. The extent of the
work is that portion of Orange Avenue adjacent to Central Winds Park plus approximately
200 east to a outfall to Lake Jesup. Orange Avenue is County right of way which is
maintained by the City due to a 1987 interlocal agreement. We are currently unable to
maintain Orange Avenue adjacent to the park during large storm events due to the runoff
from Central Winds Park. The City Attorney is pursuing potential litigation against the
March 24, 1997
Consent Agenda Item A
Page 2.
park designers due to possible deficiencies in the stormwater design.
The project was advertised for bids as Bid #97-002. Bids were opened on
February 12, 1997 with five bidders submitting bids. The low bidder was Esterson
Construction Company, Inc. ofLongwood, with a base bid of$167,155.00. Esterson's
bid for alternate #1, ($4,830 credit) was for a shell base in lieu of soil cement and alternate
#2 ($17,220) is for a 1!f2" of asphalt. We recommend including the cost of #2 because a
shell road will still erode and require a higher level of maintenance than a paved road.
Esterson Construction has previously satisfactorily completed a project for the
City and has constructed the infrastructure for several developments in the City.
Esterson's bid bond and performance bond are in order. The Deputy City Clerk's bid
summary is attached.
FUNDING:
The funding sources for this $184,375.00 project is from the 1993 Bond
Construction Fund (303-56310) as outlined in the Revised Fiscal Year 1997 Budget. The
funds for this project will be expended within 210 days of approval.
RECOMMENDATION:
It is recommend that authorization be given to enter into a contract agreement
with enter into a contract agreement with Esterson Construction Company, Inc. for
Orange Avenue Drainage and Roadway Improvements at a cost of$184,375.00 which
includes alternate #2 plus 10% contingency. The funding source would be the 1993 Bond
(303-56310).
March 24, 1997
Consent Agenda Item A
Pagel
IMPLEMENTATION SCHEDULE:
The contract period for this project is 180 days from the Notice To Proceed. We
expect that construction will begin by May 1, 1997. Construction administration for this
project will be handled by Chris Murphy, Storm water Utility Manager. Residents
impacted by construction will allowed access through the park as they currently already
can. The road shall remain open during construction.
ATTACHMENTS:
1. Agreement Form
2. Deputy City Clerk Bid #97-002 Summary
COMMISSION ACTION:
"
Attachment No. 1
SECTION 00500
AGREEMENT FORM
1. GENERAL
1.01 THIS AGREEMENT, made this _ day of , 199_, by and between
(1) the Citv of Winter Sorinas , hereinafter called the OWNER, and
(2) doing business as a
(3) I and hereinafter called the CONTRACTOR.
1.02 WHEREAS, the OWNER and the CONTRACTOR are desirous of entering into an Agreement for
construction of a by CONTRACTOR for OWNER.
NOW, THEREFORE, for and in consideration of the mutual promises hereinafter exchanged
the parties agree as follows:
1. Contract Documents - The Contract Documents consist of this Agreement; all Technical, General,
and Supplementary Conditions and Sections contained in the Project Manual; the Drawings as listed on the
Bid Form and Index to Drawings; all Addenda issued prior to and all Change Orders issued after execution
of this Agreement. These form the Contract and all are as fully a part of the Contract as if attached to this
Agreement or repeated herein.
2. Scone of Work - The CONTRACTOR shall perform all work required by the Contract
Documents for the construction of Oranae Avenue Improvements.
3. Contract Time - The CONTRACTOR shall begin work within ten (10) days after the issuance of
a written Notice to Proceed and shall complete the work within one hundred fifty (180) calendar days from
the date of the Notice to Proceed. .
4. Liauidated Damaaes - OWNER and CONTRACTOR recognize that time is of the essence of this
Agreement and that OWNER will suffer financial loss if the Work is not substantially complete within the
time specified in Paragraph 3 above, plus any extensions the'reof allowed in accordance with the General
Conditions. They also recognize the delays, expense, and difficulties Involved in proving in a legal
arbitration proceeding the actual loss suffered by OWNER if the Work is not substantially complete on time.
Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated
damages for delay (but not as a penalty) CONTRACTOR shall pay OWNER $500.00 for each day that
expires after the time specified in Paragraph 3 for final completion until the work is finally complete.
5. Contract Price. Lumo Sum Contract - The OWNER will pay the CONTRACTOR in current funds for
the performance of the work, subject to additions and deductions by Change Order, the Total Contract
Price of Dollars ($ ). Payments will be made to the
CONTRACTOR based on the Lump Sum Bid amount, the Schedule of Values, and subject to completion
of the work, in accordance with the Contract Documents.
(1) OWNER
(2) CONTRACTOR
(3) Sole Proprietor, Partnership, or Corporation
00500-1
6. Pavments - The OWNER will make payments as provided in the General Conditions
and Supplementary Conditions.
7. Enaineer - The Project has been designed by Conklin, Porter & Holmes-Engineers, Inc., referred
to in the documents as the Engineer, whose authority during the progress of construction is defined in the
General Conditions and Supplementary Conditions.
8. .6.Qod - CONTRACTOR shall supply a materials, performance and payment bond(s) in accordance
with Florida law and to the satisfaction of OWNER.
9. MediationlVenue - The parties agree that should any dispute arise between them regarding the
terms or performance of this Agreement, both parties will participate in a mediation. The parties agree to
mutually select a mediator and in the event they cannot mutually agree upon a mediator, one will be
appointed by the American Arbitration Association. The parties agree to equally share the cost of the
mediator. Should the parties fail to resolve their differences through mediation, then any cause of action
filed hereunder shall be filed in the Circuit or County Court for Seminole County, Florida.
10. CONTRACTOR warrants the Oranae Avenue Imorovements will be fit for the City's intended use
and purpose and will comply with all Federal and State laws and regulations.
1.03 IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and year first above
written.
CONTRACTOR:
Name of Firm
(Seal)
By (Signature and Titlel
Attest
OWNER:
The City of Winter Sorinas
Name of Firm
(Seal)
By (Signature and Title) Ron McLemore, City Manager
Attest
END OF SECTION
00500a/winspgs/spec
00500-2
..
.
. ;.
Attachment No.2
PROJECT TITLE: Orange A venue Drainage Improvements
BID NUMBER: 97-002
BID OPENING DATE: Februarv 12.1997
The bid opening was called by: J.P. Petrencsik
Title and Time: Purchasing Director
Bid opening was closed:
2:04 p.m.
2:17 p.m.
Present as witness: Kip LockcufI. Public WorkslUtilitv Director
Sherri Fragomeni. Representaive from Conklin. Porter & Holmes
N ancv V orbornik. Administrative SecretarylPurchasing
Bid Bond Required: YES Performance Bond Required: YES
Bids Received:
1. Prime Construction Group, Inc.
P.O. Box 590507
Orlando, FL 32859-0507
in the amount of$223,000
Alt. #1: - $ 5,000
Alt. #2: +$19,500
2. Allstate Paving, Inc.
5284 Patch Road
Orlando, FL 32822
in the amount of $200.000
Alt. #1: +$ 3,000
Alt. #2: +$18,000
3. Central Florida Environmental Corp.
1000 Savage Ct. #215
Longwood, FL 32750
in the amount of$185,711.00
Alt. # I: - $ 4.506.00
Alt. #2: +$19,500
4. Esterson Construction Company, Inc.
794 Big Tree Drive, Suite 108
Longwood, FL 32750
in the amount of$167,155.00
Alt. # I: - $ 4,830.00 Alt.#2: +$17,220.00
~ ..
. -)
5. Gibbs & Register. Inc.
438 North Dillard Street
Winter Garden. FL 34787
in the amount of $277,700.00
Alt. #1: + $ 4.000
Alt. #2: +$19,000
~~
Margo opIdns. ty Clerk
cc: Public Works Department
City Manager
Purchasing Department